What is being built to replace Baltimore's Key Bridge?
The Francis Scott Key Bridge carried I-695 over the Patapsco River at the Port of Baltimore. It fell on March 26, 2024, after the container ship Dali hit it. The Maryland Transportation Authority (MDTA) owns the road and is building the new bridge.
The new bridge is cable-stayed. Its main span is 1,665 feet long and sits 230 feet over the shipping channel, held by two towers over 600 feet tall. The whole bridge is more than 2 miles long. MDTA says Congress committed to cover 100% of the replacement cost.
How much will the new Key Bridge cost?
In November 2025, MDTA raised its estimate to $4.3 billion to $5.2 billion, with opening in late 2030. In 2024 the estimate was $1.7 billion to $1.9 billion. MDTA kept the same range in May 2026. It is a cost range, not money spent.
In May 2026, MDTA split the rest of the work into four contracts. The main span and marine approaches (KB-4907) are $3.5 billion to $4 billion. The South Land Approach (KB-4908) is $300 million to $400 million, the North Land Approach (KB-4909) is $200 million to $300 million, and demolition is $50 million to $100 million.
What happened to Kiewit on the Key Bridge rebuild?
On Aug. 29, 2024, MDTA's board approved a $73 million Phase 1 contract naming Kiewit Infrastructure Co. the progressive design-builder. Phase 1 later grew to $211 million, and Kiewit is set to be paid nearly $500 million for construction work.
In April 2026, Maryland said Kiewit's price for Phase 2 was unacceptable and far above the state's own cost estimates, and dropped it from the main build. U.S. Rep. Andy Harris said the rebuild could have cost up to $9 billion under Kiewit. Kiewit is still finishing its early work: land demolition ended in winter 2026, the temporary trestles in fall 2026, and the foundation and pier-protection piles for the main span towers run through spring 2027. Kiewit and its affiliates may not bid the main span contract (KB-4907).
Who won the Key Bridge demolition contract?
On Nov. 19, 2026, MDTA's board approved a $38.6 million demolition and marine work contract (KB-4906) to Joseph B. Fay Company, the lowest-priced, qualified bidder. MDTA's own estimate for the work was nearly $92 million.
Fay will remove and salvage the remaining three-span steel girder sections near each bank, demolish 8 piers in the water, fully remove 2 piers on land, take 9 marine foundations down to the riverbed and clean out the 96-inch steel piles for the new bridge. The contract runs 671 calendar days, with notice to proceed expected in December 2026.
Which Key Bridge contracts are still to be awarded?
MDTA asked for qualifications on the main span contract (KB-4907) on July 21, 2026, with statements due Aug. 19. It planned a shortlist in fall 2026; we found none published as of Nov. 19, 2026. MDTA plans a stipend of up to $1 million for each unsuccessful shortlisted team that meets the RFP terms, and a performance bond of half the contract value, capped at $1.5 billion.
MDTA planned to advertise bids for the South Land Approach (KB-4908) in fall 2026 to winter 2027 and the North Land Approach (KB-4909) in winter 2027. No firm has been named on any of the three yet.
Which engineering firms are on the Key Bridge rebuild?
On Jan. 8, 2025, MDTA named Bridging Maryland Partnership, a joint venture of WSP, RK&K and JMT, its general engineering consultant on a $75 million contract. On Feb. 12, 2025, it named three $20 million construction management and inspection teams: Greenman-Pedersen with Gannett Fleming, Michael Baker International with STV, and AECOM.
MDTA's list of firms that may not bid the main span also names COWI, Arup, Moffatt & Nichol, Thornton Tomasetti, RWDI and Mass Electric. The list covers Kiewit affiliates, the engineering and inspection firms, the firms drawing the main span plans and Kiewit's Phase 1 subcontractors, but it does not say which applies to which firm. 17 firms in all are on the list below.
How do the ways into the Key Bridge rebuild compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Key Bridge rebuild | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The contracts still to be awarded | A place on a team bidding the main span (KB-4907) or a land approach (KB-4908, KB-4909) | Builders, marine and steel subcontractors | A share of a contract worth $200 million to $4 billion | No award yet, and firms on MDTA's restricted list may not take part in the main span |
Who should go after the Key Bridge rebuild?
| Marine, steel and demolition suppliers | Joseph B. Fay's $38.6 million demolition and marine contract, and Weeks Marine's crane barges with Kiewit on the foundation piles. |
|---|
| Engineering, survey and testing firms | The general engineering team (WSP, RK&K, JMT) and the three inspection teams (GPI and Gannett Fleming, Michael Baker and STV, AECOM). |
|---|
| Builders and big subcontractors | The $3.5 billion to $4 billion main span and two land approaches are still to be awarded. The main span is closed to Kiewit, its affiliates and firms on MDTA's restricted list. |
|---|
What should you do next on the Key Bridge rebuild?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the Francis Scott Key Bridge rebuild in Baltimore.
- Watch for MDTA's main span shortlist and the land approach bids, planned for fall 2026 to winter 2027.
Questions people ask about the Key Bridge rebuild
How much will the new Key Bridge cost?
MDTA estimates $4.3 billion to $5.2 billion, set in November 2025 and kept in May 2026. In 2024 the estimate was $1.7 billion to $1.9 billion. It is a cost range, not money spent. The main span contract alone is $3.5 billion to $4 billion.
Who is rebuilding the Key Bridge?
The Maryland Transportation Authority (MDTA) owns the job. Kiewit Infrastructure Co. is finishing Phase 1 early work through spring 2027, and Joseph B. Fay Company won the $38.6 million demolition contract on Nov. 19, 2026. 17 firms are named on the job, listed above.
Who won the Key Bridge demolition contract?
Joseph B. Fay Company, the lowest-priced, qualified bidder, at about $38.6 million, approved by MDTA's board on Nov. 19, 2026. MDTA's own estimate was nearly $92 million. The work runs 671 calendar days, with notice to proceed expected in December 2026.
Why did Kiewit leave the Key Bridge rebuild?
In April 2026, Maryland said Kiewit's Phase 2 price was unacceptable and far above the state's independent cost estimates, and dropped it from the main build. U.S. Rep. Andy Harris said it could have cost up to $9 billion. Kiewit is still finishing its early work through spring 2027.
When will the new Key Bridge open?
MDTA's target is late 2030. News reports say replacing Kiewit with four new contracts could push that later, and the biggest contract, the main span, is not yet awarded.
Which Key Bridge contracts are still to be awarded?
Three: the main span and marine approaches (KB-4907, $3.5 billion to $4 billion), the South Land Approach (KB-4908, $300 million to $400 million) and the North Land Approach (KB-4909, $200 million to $300 million). The land approach bids are planned for fall 2026 to winter 2027.
How can subcontractors get on the Key Bridge rebuild?
Call the firms already on the job, starting with Joseph B. Fay Company for demolition and marine work. For the three contracts still to be awarded, the way in is a team that bids them. Kiewit, its affiliates and the other firms on MDTA's restricted list may not bid the main span.
Who is paying for the Key Bridge rebuild?
MDTA says Congress committed to cover 100% of the replacement cost, through federal Emergency Relief funding. MDTA owns the bridge and runs the contracts.
How big will the new Key Bridge be?
The main span is a 1,665-foot cable-stayed span, 230 feet over the shipping channel, held by two towers over 600 feet tall. The whole bridge is more than 2 miles long, on 96-inch concrete-filled steel pipe piles.
Which engineering firms work on the Key Bridge rebuild?
WSP, RK&K and JMT form Bridging Maryland Partnership, the $75 million general engineering consultant. Greenman-Pedersen with Gannett Fleming, Michael Baker International with STV, and AECOM hold the three $20 million construction management and inspection contracts.
What happens next on the Key Bridge rebuild?
Fay's notice to proceed is expected in December 2026. Kiewit's foundation piles run through spring 2027. MDTA planned a main span shortlist for fall 2026 and land approach bids for fall 2026 to winter 2027. We'll update this page when a new contract or firm appears.
How we built this list
We read MDTA's news releases on the cost, the four contracts, the demolition award, the main span request for qualifications, the engineering consultant and the inspection contracts; MDTA's main span forum questions, presentation and restricted list; Kiewit's own 2024 release; and news reports, all on Nov. 19, 2026. We kept each firm a public record names on this project. Eleven have a stated role; six are on the list only because MDTA names them among firms that may not bid the main span, and we do not guess their role. Contract values for joint ventures are for the whole team, not one firm's share. Left out: an oil spill response firm, a power utility listed only as a stakeholder, the landowner of the staging yard, a 2024 design concept never hired, the 2024 wreck removal firms (a separate federal job), and more than 30 other firms on MDTA's restricted list. We did not find how many firms bid the demolition contract. Phones are each firm's own line from its own site; Kiewit, Weeks Marine, AECOM, Moffatt & Nichol, Thornton Tomasetti and RWDI are headquarters lines, Fay's is its parent's Maryland office, and WSP, GPI, Gannett Fleming, COWI, Arup and Mass Electric show no main line on their sites. First published Nov. 19, 2026. We'll update this page when a new contract, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 19, 2026- MDTA: updated cost estimates for the Key Bridge rebuild (Nov. 17, 2025)
- MDTA: four separate construction contracts for the Key Bridge rebuild (May 19, 2026)
- MDTA: Key Bridge rebuild demolition and marine work contract awarded (Nov. 19, 2026)
- WMAR-2 News: Maryland awards $38.6 million contract to remove remaining Key Bridge structures (Nov. 2026)
- Construction Dive: Kiewit out of Baltimore Key Bridge rebuild (April 28, 2026)
- CBS Baltimore: former Key Bridge contractor's cost estimate (May 4, 2026)
- Kiewit: MDTA board approves progressive design-build contract (Aug. 29, 2024)
- MDTA: general engineering consultant contract (Jan. 8, 2025)
- MDTA: construction management and inspection services contracts (Feb. 12, 2025)
- MDTA: request for qualifications for the main span and marine approaches (July 21, 2026)
- Construction Dive: Maryland issues RFQ for Key Bridge main span (July 24, 2026)
- MDTA: main span industry forum questions and answers (July 2, 2026)
- MDTA: KB-4907-0000 restrictions on participation (June 2026)
- MDTA: main span industry forum presentation (June 18, 2026)
- MDTA: Key Bridge Rebuild project site (read Nov. 19, 2026)