What is in Mayo's $666.5 million core and shell permit?
On Sept. 30, 2026, CannonDesign filed two records with the City of Rochester for Mayo Clinic's Ozmun Site Building at 415 SW 2nd St. The first carries a job value of $666,500,000 for "Core and Shell components for building on Ozmun Site", covering "Release 15 - Core, Release 18 - Enclosure". The second is the same submission titled "MEP REVIEWS". Both were In Plan Review on Nov. 10, 2026.
The building already holds two permits: $22,000,000 for footings, foundations and below-slab plumbing (Gilbane Building Company) and $122,000,000 for the steel and superstructure. The $666.5 million is the job value on one application, not the building's total cost.
Who holds the HVAC, piping and plumbing permits on the Ozmun site?
Harris Rochester Inc holds every mechanical, plumbing and gas permit at 415 SW 2nd St since 2025. Three cover the Geothermal Exchange Plant in the future Ozmun building, filed July 9, 2026: $8,164,086 of "chilled-water, heating-hot-water, geothermal-exchange, and groundwater-supply piping", $410,791 for "two air handling units" and their ductwork, and $62,860 of plumbing.
Harris also holds the permit for "Six (6) new Elevator Sump Basins and Piping for Ozmun Building" ($229,097, filed June 18) and a temporary winter gas line on the site, issued Oct. 20, 2026 ($155,000). Across Mayo's Rochester permits filed Aug. 3 to Oct. 30, 2026, Harris holds $5.46 million of $8.06 million in mechanical permits.
Who holds the electrical permits on the Ozmun building?
Egan Company holds the geothermal plant's electrical permit, at $7,050,000 (filed June 23, 2026). Parsons Electric holds a $775,000 permit to "Install duct banks and sleeves through foundation walls of building" (filed May 13).
The core and shell's own electrical is part of the MEP review that is still open. Rochester issues each trade a separate permit, so those permits come after the review.
What is the Ozmun building's geothermal plant?
Knutson Construction holds the $41,000,000 building permit for Mayo's "Geothermal Exchange Plant in the future Ozmun building" (filed Feb. 11, 2026). Burns & McDonnell's project page puts it "within the subway level of the new clinical building on the Ozmun block", "Designed to house four 1,000-ton heat pump chillers", drawing on the Jordan aquifer.
How does the Ozmun building fit Mayo's $5 billion plan?
Mayo's Bold. Forward. Unbound. in Rochester plan is about $5 billion: KTTC reported in August 2025 that its "$5 billion cost has not changed". ENR reported five buildings totaling 2.4 million sq ft, with Gilbane as construction manager and Foster + Partners and CannonDesign as designers. mcdmag reported two new clinical buildings "on the sites of the current Ozmun complex and Damon Ramp". KTTC says the Ozmun site building is expected to be complete in 2030.
How do the ways into Mayo's Ozmun building compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The mechanical contractor on the record | A call to Harris Rochester, on every HVAC, piping and plumbing permit at the site | HVAC equipment, pipe, valve, pump and hydronic reps | The firm with $9 million of permits on the site and the core and shell still to come | Its project staff aren't listed publicly, so start at the main line |
| The electricians | A call to Egan (geothermal plant, $7.05 million) or Parsons (duct banks) | Gear, wire, lighting and low-voltage reps | The firms already wiring inside the building | The core and shell's electrical isn't permitted yet |
| The construction manager | A call to Gilbane about core and shell packages | Any MEP or specialty firm not yet on the job | Who will hold the core and shell's HVAC, plumbing and electrical | Gilbane may already have some packages let |
| The designer | A call to CannonDesign about the basis of design | Manufacturer reps who sell by specification | Getting a product named before the trades buy | The design is far along; the MEP review is already with the city |
Who should go after Mayo's Ozmun building, and who shouldn't?
| HVAC, hydronic and plumbing supply reps | Harris Rochester holds every mechanical, plumbing and gas permit on the Ozmun site, and two of every three HVAC dollars on Mayo's Rochester permits filed Aug.-Oct. 2026. |
|---|
| Electrical distributors and gear reps | Egan holds the geothermal plant's $7,050,000 electrical permit; the core and shell's electrical is still in review. |
|---|
| MEP subcontractors | Ask Gilbane which core and shell packages are open. |
|---|
| Not for: residential suppliers | Every row is hospital, plant or campus work. |
|---|
What should you do next on Mayo's Ozmun building?
- If you sell HVAC equipment, pipe or valves, call Harris Rochester's main line, 507.281.4000, and ask for the team on Mayo's Ozmun building.
- If you sell electrical gear or wire, call Egan's Rochester office, 507.289.4522.
- If you're an MEP subcontractor, call Gilbane and ask which core and shell packages are still open.
- Open the full list for every permit and firm, with each company's line.
Questions people ask about Mayo Clinic's Ozmun building
Who is the mechanical contractor on Mayo Clinic's Ozmun building?
Harris Rochester Inc. The city's records name Harris on every mechanical, plumbing and gas permit at 415 SW 2nd St since 2025: hydronic piping ($8,164,086), two air handling units ($410,791) and plumbing ($62,860) for the geothermal plant, filed July 9, 2026; six elevator sump basins ($229,097, filed June 18); and a temporary winter gas line ($155,000, issued Oct. 20, 2026). No HVAC or plumbing permit for the building's core and shell is on the record yet.
Who is the electrician on the Ozmun building?
Two firms hold its electrical permits so far. Egan Company holds the geothermal plant's $7,050,000 electrical permit (filed June 23, 2026), and Parsons Electric holds a $775,000 permit for duct banks and sleeves through the foundation walls (filed May 13). The core and shell's electrical is still in the city's MEP review.
Who is building Mayo Clinic's new Rochester buildings?
Gilbane Building Company is the construction manager, per ENR's Nov. 30, 2023 report on the board's choice. Gilbane is the licensed contractor on the Ozmun building's $22 million foundation permit. Foster + Partners and CannonDesign are the designers, and CannonDesign is the applicant on the core and shell.
How much is the Ozmun building's permit?
The core and shell application carries a job value of $666,500,000 for "Release 15 - Core, Release 18 - Enclosure". It was filed Sept. 30, 2026 and was In Plan Review on Nov. 10. Earlier releases were permitted at $22,000,000 (footings and foundations) and $122,000,000 (structure). The job value on a permit is not the building's total cost.
What is the Ozmun site?
It's the block of the former Ozmun complex in downtown Rochester, at 415 SW 2nd St. Mayo's Bold. Forward. Unbound. in Rochester plan puts a new clinical building there; mcdmag reported in 2023 that two new buildings would rise "on the sites of the current Ozmun complex and Damon Ramp".
What is the geothermal plant in the Ozmun building?
Mayo's Geothermal Exchange Plant (project ROXX23C0250) sits in the new building's subway level. Burns & McDonnell's project page says it is "Designed to house four 1,000-ton heat pump chillers" and draws on the Jordan aquifer. Its building permit carries $41,000,000 (Knutson Construction, filed Feb. 11, 2026).
How much is Mayo Clinic spending in Rochester?
About $5 billion. KTTC reported on Aug. 25, 2025 that "Bold. Forward. Unbound's $5 billion cost has not changed." ENR reported five buildings totaling 2.4 million sq ft.
When will the Ozmun building open?
KTTC reported in August 2025 that the Waterman Building and the Ozmun site clinical building are expected to be complete in 2030.
What hasn't been permitted yet?
The core and shell's HVAC, plumbing and electrical. The city lists a separate "MEP REVIEWS" record, In Plan Review since Sept. 30, 2026. Rochester issues each trade its own permit, so those come after review.
Who else is working on Mayo's Rochester campus?
From Mayo's Rochester permits filed Aug.-Oct. 2026: DMC Plumbing & Heating on the Gonda 4 surgical area ($1.2 million plumbing, $811,000 hydronic), Egan on the ambulance dispatch center ($892,470) and the Eisenberg locker rooms, Weis Builders and Knutson as builders, WHV on HVAC, Adair Electric on many small jobs, and Metropolitan Mechanical on the Waterman Building's elevator drains. Harris holds 12 of the 62 mechanical permits in that window and $5.46 million of their $8.06 million.
What are the risks?
The core and shell is still in review, so its scope and timing can change, and Gilbane may already have some trade packages let. A permit's job value is the applicant's figure, not a contract amount.
How we built this list
We read every City of Rochester permit at 415 SW 2nd St on the city's public permit portal (the address list and each record page, read Nov. 10, 2026), the portal's keyword search for "Ozmun", Mayo Clinic's other Rochester permits filed Aug. 3 to Oct. 30, 2026 in ATI's records, and ENR, mcdmag, KTTC, KSTP and Burns & McDonnell. A row is on the list only if a city record ties it to the Ozmun site or to a Mayo-owned building or Mayo project number. Company phone lines come from each firm's own website or the company block on its city permit; we list no person's name or number. First published Nov. 20, 2026. We'll update this page when the core and shell permit is issued and its HVAC, plumbing and electrical permits are filed.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 10, 2026- City of Rochester permit portal, records at 415 SW 2 ST
- City of Rochester permit portal, R26-0427CB (core and shell, $666,500,000)
- City of Rochester permit portal, R26-0428CB (MEP reviews)
- City of Rochester permit portal, R26-0048CB (geothermal plant, $41,000,000)
- City of Rochester permit portal, R26-1129CE (geothermal plant electrical, $7,050,000)
- City of Rochester permit portal, R26-1211CM (geothermal plant hydronic, $8,164,086)
- City of Rochester permit portal, R25-0506CB and R26-0249CB (foundations and structure)
- ENR, Mayo Clinic picks Gilbane to lead $5B Minnesota expansion (Nov. 30, 2023)
- mcdmag, Project team selected for transformative Mayo Clinic multiyear initiative (Nov. 29, 2023)
- KTTC, What you can expect from Mayo Clinic's Bold. Forward. Unbound. in 2025-2026 (Aug. 25, 2025)
- Burns & McDonnell, Healthcare Campus Expansion Program
- Harris, office locations
- Egan Company, contact