$150M STADIUM: WHO YOU CALL

Who's building Seattle's $150 million Memorial Stadium

By Porter Stanley. Updated .

Seattle Public Schools owns the new Memorial Stadium at Seattle Center, and the City of Seattle holds the development contract. A partnership of the Seattle Kraken, Oak View Group and One Roof Foundation is leading the project. Sellen Construction is the general contractor, and Generator Studio is the architect. The anticipated cost is $150 million, and completion is planned for fall 2027. State filings name 91 companies on the job. We found no public bid date, because the work runs through Sellen and the firms it hired.

$150MAnticipated cost
6,500Seats
91Companies on state filings
95Opportunities listed

Get all 95 jobs and who to call

Each one with who's on the record and the date. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 95 jobs and who to call

Each one with who's on the record and the date. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

What are all the opportunities on Memorial Stadium in Seattle?

We list 95: 85 name a firm or door on the record, 6 are planned with no date, and none has a public bid date. Each row shows the firm, who hired it and its expected start where a filing states one.

1Latest recordJun 3, 2026

Premier Field Development

Likely buys drain stone, base rock, drain pipe, shock pad and grading rental

On the stadium job

$996,792 on the state filing

Work: Athletic field construction

Who to call: Premier Field Development
(360) 563-5680

The opportunity: Hired by Coast to Coast Turf. Filed June 3, 2026, with an expected start of Jan. 1, 2027. Its site lists field construction and subsurface drainage, so field base and drainage are its likely scope. Materials may already be bought.

2Latest recordOct 7, 2026

Eckstrom Industries

Likely buys sheet and tube metal, finishes, fasteners and shop supplies

On the stadium job

$1,880,760 on the state filing

Work: Likely architectural metals

Who to call: Eckstrom Industries

The opportunity: Hired by Sellen. Filed Oct. 7, 2026, with an expected start of Nov. 9, 2026. Its site lists architectural metal work, so that's its likely scope here.

3PlannedNov 4, 2026

Sellen Construction, through Seattle Public Schools

Architectural wood casework, upper and lower, Wilsonart or approved equal

On the stadium job

Work: Casework, millwork

The opportunity: The district lists this as a potential Sellen subcontract, with target installation in January 2027. It gives no bid date, and no casework firm has filed yet. Posting doesn't guarantee a bid or award. Virginia Bethea at the district takes interest.

Who is working on Memorial Stadium in Seattle?

Seattle Public Schools will own Memorial Stadium, and the City of Seattle holds the development contract. Memorial Stadium Redevelopment LLC leads the design and construction. That LLC hired Sellen Construction as general contractor, and Generator Studio is the architect.

Washington law requires the contractor and each subcontractor on the job to file a statement of intent to pay prevailing wages. Each filing names the company and the firm that hired it. Through Oct. 27, 2026, the state holds 116 filings for this job.

Those filings carry 92 names, but Stoneway Concrete and Gary Merlino Construction share a state business ID, so we count 91 companies. Sellen itself made 1 filing. Firms hired by Sellen made 60, and firms hired by other subs made 55.

One chain runs 4 tiers below Sellen. Sellen hired AstroTurf, AstroTurf hired Coast to Coast Turf, Coast to Coast hired Premier Field Development, and Premier hired Caliber Concrete Construction.

A filing shows that a company told the state it's on the job. It doesn't state the company's scope. Its amount is an estimate, and a sub's filed amount can exceed the amount its hiring firm filed. Read the amounts as a sign of size, not as prices.

  • Prime Electric filed $10,808,057, and city permits name it on the stadium's electrical work.
  • Gary Merlino Construction filed $8,823,200, and its site lists excavation and underground utilities.
  • Metals Fabrication Co. filed $7,947,000, and its site lists metals fabrication.
  • KLB Construction filed $7,865,458, and its site lists heavy civil work.
  • Bethlehem Construction filed $3,693,692, and its site lists structural and architectural precast.

What is being bought for Memorial Stadium in Seattle, and when?

Structural steel and precast erection began May 4, 2026, and Seattle Center said both were nearing completion in September 2026. Interior buildout began by August 2026. So the firms on the structure are already at work, and finish and field work comes next.

Washington's labor report shows the same order. It records 227,407 hours on the job so far, including 32,729 for laborers and 19,902 for ironworkers. It records 120 hours for painters and 44 for soft floor layers. It records none for glaziers, elevator constructors or cabinet makers.

The filings give expected start dates for what's coming, and they appear below. These dates come from each firm's filing, and some firms file after they start. A start date doesn't show what the firm has already ordered.

Seattle Public Schools also lists 4 potential scopes under Sellen. They are acoustical ceilings, flooring, wood casework and a Greenscreen vine trellis. The district's page says posting doesn't guarantee that a scope will be bid or awarded. We found no public bid date for any of them.

  • Nov. 9, 2026: Eckstrom Industries, $1,880,760 filed, expected start.
  • Jan. 1, 2027: Premier Field Development, $996,792 filed, expected start.
  • January 2027: Wood casework, Wilsonart or approved equal, the district's target installation.
  • Jan. 4, 2027: Building Specialties NW, $383,725 filed, expected start.
  • Jan. 11, 2027: Treble Interiors, $86,559 filed, expected start.
  • January to April 2027: Greenscreen vine trellis, the district's target installation.
  • June 25, 2027: AstroTurf, $1,909,130 filed, expected start.
  • 1 VRF system and 38 mini-splits: the refrigerant permit the city issued Vet First Mechanical on Oct. 15, 2026.

How do the ways into Memorial Stadium in Seattle compare?

Way inWhat it isBest forWhat you getThe limit
Sellen's vendor doorBuildingConnected and a Preferred Vendor formTrades and suppliers new to SellenA place on Sellen's bid platformIt isn't a bid invitation, and it lists no dates for this job
The district's scope postingA Seattle Public Schools page with 4 potential scopesCeiling, flooring, casework and trellis firms, including small and minority- and women-owned firmsA named contact who takes interestPosting doesn't guarantee a bid or award, and the page is undated
Selling to a firm on the filingsA call to a company named on the state filingsSuppliers and lower-tier subsA named buyer with a filed amount and an expected startFilings state no scope, and that firm may already have bought
City inclusion helpThe City of Seattle's Purchasing and Contracting office, (206) 684-0444Minority- and women-owned firms and any sub that needs help with the planInformation on the project's inclusion rulesIt offers help, not work
After the stadium is builtOne Roof Sports & Entertainment, the first operatorMaintenance, janitorial and event service vendorsA buyer for at least the first 5 yearsWe found no vendor process, and this isn't construction work

Who should go after Memorial Stadium, and who shouldn't?

Field base and drainage suppliersPremier Field Development filed $996,792 and listed a Jan. 1, 2027 start.
Metal suppliersEckstrom Industries filed $1,880,760 and listed a Nov. 9, 2026 start.
Casework firmsThe district lists wood casework for January 2027, and no casework firm has filed.
Firms that need a public bid dateThis isn't the job for you, because we found none. Excavation and early-phase suppliers should also expect much of that work to be bought.

What should you do next on Memorial Stadium?

  1. Register with Sellen on BuildingConnected and fill out its Preferred Vendor form.
  2. Contact Seattle Public Schools if your firm fits a posted scope.
  3. Call the firms on the filings whose next start falls in your window.
  4. Open the full list to see every firm, who hired it and its expected start.

Questions people ask about Memorial Stadium in Seattle

Who is building Memorial Stadium in Seattle?

Sellen Construction is leading construction, and Generator Studio designed the stadium. Memorial Stadium Redevelopment LLC hired Sellen. That LLC is a partnership of the Seattle Kraken, Oak View Group and One Roof Foundation.

Who is the general contractor on Memorial Stadium in Seattle?

Sellen Construction is the general contractor. Washington's filings list a contract award date of June 23, 2025, and an estimated contract amount of $145,220,600.

Who owns Memorial Stadium in Seattle?

Seattle Public Schools owns it and will keep owning it. The City of Seattle is the contracting entity and runs the development agreement. One Roof Sports & Entertainment will operate and maintain the stadium for at least the first 5 years.

How much does Memorial Stadium in Seattle cost, and who pays?

The anticipated cost is $150 million. Seattle Public Schools puts in $69.3 million, the City $40 million, the state $3.95 million, and the King County Parks Levy more than $5 million. Private donors cover the rest.

When will Memorial Stadium in Seattle open?

Seattle Center plans completion for fall 2027, and its FAQ says the project will be done by the end of 2027. An April 2025 schedule showed a Sept. 3, 2027 grand opening, but we found no opening date announced since.

Is Memorial Stadium in Seattle being renovated or replaced?

It's being replaced. City records say most of the old stadium would be demolished, and crews finished that work in late 2025. Memorial Wall stays, and it's being cleaned and repaired, with its fountains brought back.

How do subcontractors get on Memorial Stadium in Seattle?

Sellen uses BuildingConnected for all its projects and has a Preferred Vendor form. Seattle Public Schools also posts potential scopes and takes interest from firms. Lower-tier firms can also be hired by the companies named on the state filings.

When is Memorial Stadium in Seattle bidding?

We found no public bid date now. The last dated sub-bid deadline we found was April 24, 2025. The district lists 4 potential scopes, and it says posting them doesn't guarantee a bid or award.

Who are the subcontractors on Memorial Stadium in Seattle?

State filings name 90 companies under Sellen through Oct. 27, 2026. They include Prime Electric, Gary Merlino Construction, Metals Fabrication, KLB Construction, AstroTurf and Daktronics.

What rules apply to subcontractors on Memorial Stadium in Seattle?

Contractors at every tier must assent to the Seattle Public Schools Student and Community Workforce Agreement. They must pay prevailing wage and file with the state. A posted project goal calls for more than 20% participation by minority- and women-owned firms.

What are the risks of chasing Memorial Stadium in Seattle?

We found no public bid date, and structural work was nearing completion in September 2026. Many trades may already be bought. Filings don't state scope, and their amounts are estimates, not prices.

What happens after I contact Sellen or the district about Memorial Stadium?

Neither gives a timeline. The district says any final bid or award comes directly from the contractor once a scope is confirmed. A contact doesn't guarantee an invitation.

How we built this list

We read all 116 state prevailing wage filings on this job, the city's permits, the project agreements, the district's posted scopes, and each firm's own page where we could. A row is on the list only if a record ties it to the stadium. We merged names that share a state business ID, so 92 filed names count as 91 companies. Where a record doesn't state a firm's trade, the row says likely. We mark each row by how firm it is, and a row with no bid date is never shown as up for bid. First published Nov. 4, 2026. We'll update this page when a new filing, permit or bid date appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 95 jobs, free

All 95 opportunities on Memorial Stadium

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.