What is being built at the Ahwatukee data center?
Menlo Digital, part of Menlo Equities, is building a data center campus it calls MD-PHX1 at 4801 E Thistle Landing Dr in the Ahwatukee Foothills of Phoenix. City records call it Thistle Technology Center and the East Thistle Landing Data Center. It sits on the site of four old call center buildings, which were torn down in late 2025.
The plans show five two-story buildings of 204,480 sq ft each, 1,022,400 sq ft on about 38 acres, and an onsite substation. Menlo says the campus has a 257 MW utility feed from Salt River Project and 180 MW of IT load. Gensler designed it in Corten steel, per Dezeen (May 21, 2026).
How much is the Ahwatukee data center?
Menlo has given no total cost. Phoenix's issued permits on the job add up to about $141 million so far, the sum: about $137.2 million for the buildings, $1.17 million for civil and utility work, and $2.78 million for demolition.
The two biggest permits are $76,177,413 for the shells of Buildings 1 and 2 (392,271 sq ft, issued July 17, 2026) and $51,055,182 for the Building 5 shell (issued July 2, 2026). The Buildings 1 and 2 foundation permit is $7,418,390 (May 21, 2026). A $7.5 million substation permit, BLD T969689, is not issued yet. Each value covers shells, foundations and site work only, not the data halls or their equipment.
How far along is the Ahwatukee data center?
Site work started with grading permits issued Jan. 7, 2026, and the steel frames were up in a Cronkite News photo from Oct. 22. Menlo's own page lists the substation and shell for 2026 Q4 and the first data hall delivery for 2027 Q1.
The newest issued permit is Kerns Plumbing's private fireline with backflow, CFB 26010992, issued Oct. 27, 2026. No separate electrical or mechanical trade permits are on file yet; the shell permits include plumbing, electrical and structural work.
Why are Ahwatukee neighbors fighting the data center?
On Nov. 20, 2026, lawyer Anthony Ramirez filed an $11 million notice of claim against Phoenix for the Ahwatukee Community Alliance, per KTAR: $1 million for lost home values and $10 million for ongoing nuisance. A notice of claim comes before a lawsuit, and residents want a judge to halt the work. Residents told Cronkite News the data center is going up 100 to 150 feet from homes.
Phoenix adopted stricter data center rules in July 2025, but the campus got its first approval in 2024, per KTAR. The plans call for 120 diesel backup generators, and Maricopa County made Menlo resubmit its air permits for all five buildings, per Ahwatukee Foothills News (Aug. 26 and Sept. 23, 2026). In August, Councilman Kevin Robinson said a Menlo executive gave his campaign $5,000, which he said he will return.
Who is building the Ahwatukee data center?
Clune Construction is the contractor of record on the city's shell permits for Buildings 1, 2 and 5, the foundation permit, the site civil permit and the retaining wall. Clayco is named as the permit professional on the three building permits.
Sundt Construction holds the permit for the substation's foundation and underground electrical conduit. Kimley-Horn is the civil engineer and Rick Engineering the surveyor on the city's final site plan, and ABLA drew the landscape plan.
Which trade firms are on the Ahwatukee data center?
Ricor holds the grading permit, which moves 36,045 cubic yards of dirt out and 68,918 in, plus the water, sewer, storm drain and paving permits around the site. Dickens Quality Demolition tore down the four old call center buildings, about 397,000 sq ft. Kerns Plumbing holds the fireline and hydrant permits, RCI Systems holds the fire flow test permit, and Sun Valley Landscape holds the native plant permit.
Menlo names Salt River Project as the utility, and the city issued a right-of-way permit on Sept. 15, 2026 for a 69kV line loop-in tagged East Thistle. 13 firms in all are on the list below.
Who Menlo Digital hired before
Menlo picked Clune to build its 48 MW Herndon, Virginia data center too.
- Clune Construction: builder on MD-VA1, a 48 MW, 307,000 sq ft data center, Herndon, VA, 2025. Also on this job.
- Southland Concrete: concrete on Menlo Equities McLearen Road data center, Herndon/Fairfax County, VA, current.
- BKF Engineers: civil engineer and surveyor on 888-894 Ross Drive data center, Sunnyvale, CA, 2026.
These are earlier or other jobs for the same owner. They are not counted in the 13 firms on this job.
How do the ways into the Ahwatukee data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Menlo Digital's Thistle Landing data center in Ahwatukee | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Ahwatukee data center?
| Concrete, steel and site suppliers | Clune Construction and Clayco on five 204,480 sq ft shells with $127 million in shell permits, Ricor on grading and utilities, and Dickens Quality Demolition. |
|---|
| Fire protection, plumbing and electrical reps | Kerns Plumbing on the firelines, RCI Systems on fire flow, and Sundt on the substation conduit and grounding, on a campus whose data halls are still to come. |
|---|
| Power and engineering firms | Salt River Project on the 257 MW feed, Gensler, Kimley-Horn, Rick Engineering and ABLA. |
|---|
What should you do next on the Ahwatukee data center?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Menlo Digital's Thistle Landing data center at 4801 E Thistle Landing Dr in Ahwatukee, Phoenix.
Questions people ask about the Ahwatukee data center
How much is the Ahwatukee data center?
Menlo Digital has given no total cost. Phoenix's issued permits add up to about $141 million so far, the sum, led by a $76.2 million shell permit for Buildings 1 and 2. The permits cover shells, foundations and site work, not the data halls or equipment.
Who is building the Ahwatukee data center?
Clune Construction is the contractor of record on the city's shell and foundation permits, and Clayco is named as the permit professional. 13 firms are named on the job, listed above.
Where is the Ahwatukee data center?
It is at 4801 E Thistle Landing Dr, at 48th Street and Thistle Landing Drive, in the Ahwatukee Foothills of Phoenix, Maricopa County, Arizona, on the site of four old call center buildings.
Who owns the Ahwatukee data center?
Menlo Digital, part of Menlo Equities. The owners on city records are ME PHX Tech Campus LLC and Thistle Income Partners LLC.
How big is the Ahwatukee data center?
Five two-story buildings of 204,480 sq ft each, 1,022,400 sq ft on about 38 acres, with a 257 MW power feed from Salt River Project and 180 MW of IT load.
When will the Ahwatukee data center open?
Menlo lists the substation and shell for 2026 Q4 and the first data hall delivery for 2027 Q1.
Why are residents suing over the Ahwatukee data center?
On Nov. 20, 2026, the Ahwatukee Community Alliance filed an $11 million notice of claim against Phoenix, the step before a lawsuit: $1 million for lost home values and $10 million for ongoing nuisance. Residents want a judge to halt construction.
How many generators will the Ahwatukee data center have?
The plans call for 120 diesel backup generators, per Ahwatukee Foothills News, and Maricopa County made Menlo resubmit its air permits for all five buildings.
What is the newest permit on the Ahwatukee data center?
Phoenix issued Kerns Plumbing a private fireline permit, CFB 26010992, on Oct. 27, 2026.
What happens next on the Ahwatukee data center?
The $7.5 million substation permit is still waiting to be issued, and electrical and mechanical work comes with the data halls. We'll update this page when a new permit or firm appears.
How we built this list
We read the City of Phoenix's public permit reports and permit map layer for project 23-1632 and 4801 to 4811 E Thistle Landing Dr on Nov. 22, 2026, the city's CitizenServe right-of-way permits, and the drawings in the city's March 18, 2026 hearing packet. We also read Menlo Digital's MD-PHX1 page, KTAR, Cronkite News, Ahwatukee Foothills News and Dezeen, and kept each firm a city record or the news names on this campus. Record dates are each permit's issue date or the hearing date. The $141 million is the sum of the stated values on issued city permits, not Menlo's spend. Left out: the owner, its zoning lawyers, firms on other Thistle Landing addresses, a 2025 repair in the old call center buildings, a telecom firm whose nearby conduit permit does not name the campus, and the opponents' own consultants. Phones are each firm's own main or office line from its own site, except Kerns, RCI and Dickens, whose lines are the contractor phone on the city permit; Clayco's is its St. Louis office line and Sundt's its Tempe headquarters line. We found no website for Dickens Quality Demolition. First published Nov. 22, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 22, 2026- Menlo Digital: MD-PHX1 Phoenix (read Nov. 22, 2026)
- City of Phoenix permit report BLDS 26008875 (Buildings 1 and 2 core and shell)
- City of Phoenix permit report BLD 26008627 (Building 5 core and shell)
- City of Phoenix permit report BLD 26007595 (Buildings 1 and 2 foundation)
- City of Phoenix permit report BLD T969689 (substation, not issued)
- City of Phoenix permit report CFB 26010992 (fireline)
- City of Phoenix Planning_Permit map layer, project 23-1632
- City of Phoenix CitizenServe right-of-way permits
- City of Phoenix hearing packet PHO-3-26--Z-127-96-6 (March 18, 2026)
- KTAR: Ahwatukee data center notice of claim (Nov. 20, 2026)
- Cronkite News: Ahwatukee data center resident concerns (Nov. 16, 2026)
- Ahwatukee Foothills News: Data center foes confront 2 Phoenix officials (Aug. 26, 2026)
- Ahwatukee Foothills News: Phoenix data center assurances fail to sway foes (Sept. 23, 2026)
- Dezeen: Gensler's Thistle Data Center Campus in Phoenix (May 21, 2026)
- Menlo Digital: topping out of MD-VA1
- Southland Concrete: Menlo Equities project
- BKF: 888/894 Ross Drive Data Center