Where does Meta's $14 billion in El Paso go?
Meta broke ground in El Paso in October 2025 on a $1.5 billion AI data center; in March 2026 it said the site would grow to 1 gigawatt and its investment to more than $10 billion, and in July 2026 Meta and BlackRock put total development costs for the buildings and long-lived power, cooling and connectivity infrastructure at approximately $14 billion. Meta expects to begin bringing the capacity online in 2028.
No one has published Meta's own split, so we used a typical one: Dgtl Infra breaks the cost of building a greenfield data center into land and building shell (15 to 20 percent), electrical systems (40 to 45 percent), HVAC, mechanical and cooling (15 to 20 percent) and building fit-out (20 to 25 percent). At the low end of each range, that is about $5.6 billion for electrical, $2.1 billion for cooling, $2.1 billion for the building shells (Meta's $14 billion does not list land, so we put the whole land-and-shell share on the shells, a rough figure) and $2.8 billion for fit-out.
Why are El Paso residents fighting it?
Residents have raised worries about the water and power the campus will use, and the fight is neighbors and local groups, not the city: in June 2026 residents and organizations asked the city council to end Meta's agreement, and it voted 5-3 to keep it; two weeks later the council voted to begin negotiating a community benefits agreement with Meta. El Paso Water says Meta's service is capped at 2.5 million gallons a day, with average use estimated at about 480,000 gallons a day; Meta says it will restore 200 percent of the water the data center consumes to local watersheds.
Who gets what?
Electrical, about $5.6 billion by the math: 4 electrical contractors on the permits (CEC Facilities Group, LLC, Power Quality Service, Prime Controls, LP, Rosendin Electric, Inc.).
Cooling, air and pipe, about $2.1 billion: 3 mechanical and plumbing firms (Cerris Systems (formerly MMC Contractors), King's Enterprises LLC, Professional Piping Systems, LLC (PPS)).
Building shells, about $2.1 billion: the 2 general contractors, Hensel Phelps and J. E. Dunn.
Fit-out, about $2.8 billion: 2 firms on the permits so far (Diversified Interiors of El Paso, Inc., J.B. Installers Inc.). Also on the permits: power and energy work (Faith Technologies, Inc. (holds a general contractor license here), Enchanted Rock (Enchanted Rock Holdings LLC)), site work (Ralph L. Wadsworth Construction Company, LLC, VEMAC LLC), fire protection (Western States Fire Protection), designers and engineers, and suppliers.
Which firms are on the permits?
We read every City of El Paso building record on Stan Roberts Sr Ave since June 2025 and kept the 158 that are on Meta's campus. They name 22 firms: the 2 general contractors, 4 electrical, 3 mechanical and plumbing, 2 fit-out, 2 power and energy, 2 site work, 1 fire protection, 4 design and engineering firms and 2 suppliers. The list below holds the 12 of them buying now.
Hensel Phelps is the contractor on 44 records, from the data center buildings' underground and structure to the water tanks and generators; J. E. Dunn is on 21, from the site work and substations to the switchgear buildings. Rosendin holds the most electrical permits and Cerris Systems the most mechanical and plumbing. Stantec is the applicant on the data center buildings.
How do the ways into Meta's El Paso campus compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the permits | A call to the firm's office, asking for the Meta El Paso team | Every supplier, distributor and sales rep | A conversation with a firm already working on the campus | Start with the firms with the newest permits |
Who should go after Meta's El Paso campus?
| Electrical distributors and gear reps | About $5.6 billion of electrical work by the math, with 4 electrical firms on the permits. |
|---|
| HVAC, plumbing and pipe reps | About $2.1 billion of cooling by the math, with 3 mechanical and plumbing firms on the permits. |
|---|
| Concrete, steel, tank and building material reps | The two general contractors, Hensel Phelps and J. E. Dunn, and water storage tanks of 8 million gallons on the permits. |
|---|
What should you do next on Meta El Paso?
- Pick the firms whose permits match what you sell, and call them this week.
- Ask for the team on Meta's El Paso data center.
Questions people ask about Meta's El Paso data center
How much is Meta's El Paso data center?
Meta and BlackRock put total development costs at approximately $14 billion for the buildings and long-lived power, cooling and connectivity infrastructure (July 2026). Meta's figure was more than $10 billion in March 2026 and $1.5 billion at the October 2025 groundbreaking.
Who is building Meta's El Paso data center?
Meta names J. E. Dunn and Hensel Phelps as general contractors. In all, the City of El Paso's records name 22 firms, including Rosendin Electric, Cerris Systems and Stantec. The full list is above.
How much water will Meta's El Paso data center use?
El Paso Water says Meta's service is capped at 2.5 million gallons a day, with average use estimated at about 480,000 gallons a day over a year. One permit on the campus is for 8-million-gallon water storage tanks.
How we built this list
We searched the City of El Paso's Accela building records on Stan Roberts Sr Ave month by month from June 2025 and read every record page (197 records) on Nov. 13, 2026, then kept the 158 at 6901 or 7001 Stan Roberts Sr Ave or naming the campus ('**META**', 'TXE', 'Seafox'); El Paso Electric's and the city's own work elsewhere on the street is left out. Many of the campus records repeat one $289 million job value, so we use them for who does the work, not for dollars; the dollar split is the math on Meta's $14 billion and Dgtl Infra's typical data center split (the low end of each range). Firms are the contractors and applicants named on each record, each counted once under its El Paso license; a third-party inspection firm is left out. The Fire module's records need an account and were not read. Phones come from each firm's own website or its trade association's page; where only the permit or a business listing gave one, the row says so. First published Nov. 13, 2026. We'll update this page as El Paso issues new permits on Meta's campus.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 13, 2026- Meta: Meta Announces New Strategic Venture With BlackRock to Develop Data Center in El Paso (July 28, 2026)
- Meta Data Centers: Big things are happening, El Paso! (March 26, 2026)
- Meta: Breaking Ground on Our New AI-Optimized Data Center in El Paso (Oct. 2025)
- City of El Paso Accela (building permits)
- Dgtl Infra: How Much Does it Cost to Build a Data Center?
- Spectrum News: Meta data center in East El Paso concerns local residents (Dec. 1, 2025)
- KVIA: Residents, organizations seek to end Meta data center contract (June 9, 2026)
- KVIA: Council to begin negotiating a community benefits agreement (June 23, 2026)
- KVIA: City says it can't 'simply cancel' agreement with Meta (June 2, 2026)
- El Paso Water: Meta water service questions and answers