Who's building Meta's $50 billion Hyperion data center in Louisiana

Meta's $50 billion data center in Holly Ridge needs so much power that one Entergy gas plant for it just jumped $676 million, and protesters are fighting seven more.

By Porter Stanley. Updated .

Meta is building Hyperion, its largest multi-gigawatt AI training cluster, at its Richland Parish Data Center in Holly Ridge, Louisiana. After a July 2026 expansion Meta calls it an investment of more than $50 billion. Turner, DPR and Mortenson are the general contractors. Entergy is building three gas plants to power it, and on Nov. 19 its new cost report put one of them, Waterford 5, at $1.755 billion, up $676 million. Entergy wants seven more plants for the campus; protesters rallied against them on Nov. 18, three groups sued the state's Public Service Commission on Nov. 9, and the commission is expected to vote in December in Shreveport. 19 firms are named on the campus and its power work; the list below has all 19.

$50B+Meta investment after the July 2026 expansion
$1.755BEntergy's Waterford 5 plant, up $676M
7More gas plants Entergy wants for Meta
19Firms named on the job

Get all 19 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 19 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 19 firms on Meta's Hyperion data center?

We list the 19 firms named on Meta's Hyperion data center, one row each, with where each name comes from.

1Named by the companyDec 13, 2024

DPR Construction

General contractor building four data hall buildings and a network building, about 2 million sq ft of data space of the original 4 million sq ft build on Meta's Hyperion data center

Meta's Richland Parish Data Center (Hyperion), Holly Ridge, Richland Parish, Louisiana

Work: General contractor building four data hall buildings and a network building, about 2 million sq ft of data space of the original 4 million sq ft build

Who to call: DPR Construction
DPR Construction office line
(Redwood City, CA)
(650) 474-1450

The opportunity: DPR's scope of work will be approximately two million sq. ft. of data space on the four million sq.-ft. total build.

2Named by the companyNov 17, 2026

Mortenson (M. A. Mortenson Company)

General contractor for campus-wide work: site prep and grading, underground utilities, MV distribution and substations for onsite power, onsite water treatment, offsite wastewater treatment plant, admin/IBOS buildings, guard houses, outside plant fiber on Meta's Hyperion data center

Meta's Richland Parish Data Center (Hyperion), Holly Ridge, Richland Parish, Louisiana

Work: General contractor for campus-wide work: site prep and grading, underground utilities, MV distribution and substations for onsite power, onsite water treatment, offsite wastewater treatment plant, admin/IBOS buildings, guard houses, outside plant fiber

Who to call: Mortenson (M. A. Mortenson Company)
Mortenson (M. A. Mortenson Company) office line
(Minneapolis, MN)
(763) 522-2100

The opportunity: Mortenson is supporting development of the Richland Parish Data Center, one of the largest data center campuses in the world.

3Named by the companyJul 16, 2026

Turner Construction Company

One of three general contractors on Meta's Hyperion data center

Meta's Richland Parish Data Center (Hyperion), Holly Ridge, Richland Parish, Louisiana

Work: One of three general contractors

Who to call: Turner Construction Company
Turner Construction Company office line
(New York, NY)
(212) 229-6000

The opportunity: Turner is continuing its work with Meta as the company expands its Richland Parish data center in Louisiana.

What is Meta building in Richland Parish?

Meta's Richland Parish Data Center in Holly Ridge will house Hyperion, which Meta calls its largest multi-gigawatt AI training cluster. In July 2026 Meta expanded the plan to 5 gigawatts and nearly 10 million square feet and called it an investment of more than $50 billion in the region. The original campus, about 4 million square feet, carried about $27 billion in development costs, funded by a joint venture of Blue Owl Capital (80%) and Meta (20%).

Meta expects more than 7,500 jobs at peak construction. Turner says interior buildout is under way in the first buildings. Meta says it contracted more than $875 million with Louisiana businesses in the first year.

Why are Meta's power plants a fight?

Entergy's new quarterly cost report, made public on Nov. 19, 2026, puts its Waterford 5 plant at $1.755 billion. That is $676 million, or 63%, more than the $1.079 billion Entergy first estimated. An earlier report blamed the ground: the site must be built up several feet above grade. The full three-plant package for Meta is now $4.3625 billion, up from $3.956 billion, even though the two-plant Franklin Farms station fell to $2.244 billion and the Mount Olive-Sarepta 500 kV line fell to $363.5 million.

Now Entergy wants seven more gas plants for the campus. On Nov. 18, protesters rallied at the Public Service Commission against them. One said: "Let the richest company that's ever existed pay their own way." On Nov. 9, three groups sued the commission over the fast-track rule Entergy will use, saying it was adopted without telling the public what was changing. An environmental group says Entergy declined to accept a cap on construction costs at October hearings.

Entergy is also in court in Lincoln Parish for land rights for its 500 kV line, saying the Meta power lines serve a public purpose. The commission is expected to vote on the seven plants at its December meeting in Shreveport.

Who gets what?

No one has published the campus's trade split. By the math on a published industry split of data center costs, about $13 billion of the original campus's $27 billion is electrical work and about $8.9 billion is pipes, heat and air. Meta's $50 billion figure covers the expanded campus and its region-wide spending.

Which firms are on the job?

Turner Construction, DPR Construction and Mortenson are the general contractors, DPR and Turner on the data center buildings and Mortenson on campus-wide site, utility and power work. DPR names US Engineering and Faith Technologies as its mechanical and electrical trade partners, and Meta's own update links posts by local firms Copeland Electric and LEMOINE among the Louisiana businesses doing electric, paving, utility work and more for the campus. Entergy Louisiana is building the power: TIC and Sargent & Lundy's joint venture with Mitsubishi Power Americas on the new plants, Energy Transfer's ETC Tiger Pipeline on the gas line to Franklin Farms, Ampirical Solutions on the Smalling substation, and Chain Electric, Hunt, Guillot & Associates and RC Boring on the line upgrades. Mammoth Industries and Corporate Mobile Housing build crew housing, and Mayo Tours runs the worker buses: it says its fleet grew from 40 coaches to 102 and most of its drivers on site now earn over $80,000 a year, in a region where the median income is $42,000 (Meta, July 2026). 19 firms in all are on the list below.

What records name this job?

The seven-plant request is Louisiana Public Service Commission docket U-37882. EPA construction stormwater notices cover Project Cypress, the campus (LAR10Q665, June 17, 2026), Mortenson's civil work (LAR10Q893, Aug. 20, 2026) and Entergy's Smalling substation lines (LAR10Q848, June 24, 2026). Energy Transfer's ETC Tiger Pipeline filed for its Franklin Farms gas line at FERC on July 1, 2026 (docket CP26-549), estimated at $137,388,622. Richland Parish has no online permit search we could find.

Who Entergy hired before

Entergy keeps hiring the same plant team. TIC, Sargent & Lundy and Mitsubishi Power, the group building Franklin Farms for Meta, were also hired to build Entergy Texas's Orange County plant, and TIC is building Entergy Mississippi's Delta Blues plant.

  • Mitsubishi Power Americas, Sargent & Lundy and TIC: EPC consortium on Orange County Advanced Power Station (1,215 MW), Bridge City, TX, 2023. Also on this job.
  • TIC: plant builder on Delta Blues Advanced Power Station (754 MW), Greenville, MS, 2024-2028. Also on this job.
  • TSL Power Partners (TIC + Sargent & Lundy) with Mitsubishi Power Americas: EPC on Entergy's Jefferson, Vicksburg, Traceview, Legend and Lonestar power stations, AR, MS, TX, 2026. Also on this job.

These are earlier or other jobs for the same owner. They are not counted in the 19 firms on this job.

How do the ways into Meta's Hyperion data center compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on Meta's Hyperion data centerEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell

Who should go after Meta's Hyperion data center?

Electrical distributors and gear repsFaith Technologies with DPR, and Entergy's substation and line work.
Mechanical, chiller and pipe repsUS Engineering with DPR on the data center buildings.
Site, concrete and steel suppliersMortenson's campus-wide site prep, grading and underground utilities.
Power plant, pipe and valve suppliersTIC, Sargent & Lundy and Mitsubishi Power on Entergy's plants, and Energy Transfer's new gas line to Franklin Farms.

What should you do next on Meta's Hyperion data center?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on Meta's Hyperion data center.

Questions people ask about Meta's Hyperion data center

How much is Meta's Hyperion data center?

More than $50 billion after the July 2026 expansion, per Meta; the original campus's development cost was about $27 billion.

How much do Entergy's power plants for Meta cost?

Entergy's three-plant package is now $4.3625 billion. Its Waterford 5 plant alone rose $676 million, or 63%, to $1.755 billion (reported Nov. 19, 2026).

Why are people protesting Meta's gas plants?

Entergy wants seven more gas plants for the campus. Protesters rallied at the Public Service Commission on Nov. 18, three groups sued the commission on Nov. 9, and the commission is expected to vote in December in Shreveport.

How much do workers make on Meta's Hyperion site?

Mayo Tours, which runs the worker buses, says most of its drivers on site now earn over $80,000 a year, in a region where the median income is $42,000 (Meta, July 2026).

Who is building Meta's Louisiana data center?

Turner Construction, DPR Construction and Mortenson. 19 firms are named in all, listed above.

Where is Meta's Hyperion data center?

Holly Ridge, near Rayville, in Richland Parish, Louisiana.

How we built this list

We read Meta's and Blue Owl's announcements, DPR, Mortenson and Turner, Entergy and TIC, Entergy's quarterly cost report as reported by WWNO, Red River Radio, the Shreveport-Bossier City Advocate, ENR, Fortune, a FERC notice and EPA stormwater notices, and kept each firm a page names on this campus or its power work, marked as such (read Nov. 22, 2026). The trade split is the math on Turner & Townsend's published data center shares, applied to the original campus's $27 billion. Phones are each firm's own office line. First published Nov. 17, 2026. Updated Nov. 22, 2026: Entergy's new cost report, the protest and lawsuit over seven more gas plants, the records, and four more firms. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

Sources, checked Nov. 22, 2026
  1. Meta Data Centers: deepening our investment in Richland Parish (July 13, 2026)
  2. Meta Newsroom: Meta and Blue Owl to develop Hyperion (Oct. 21, 2025)
  3. Meta Newsroom: teachers and local businesses win as Meta expands its Louisiana data center (July 13, 2026)
  4. ACS Group: Turner on the expanded Meta data center (July 16, 2026)
  5. DPR Construction: Louisiana data center press release (Dec. 13, 2024)
  6. Shreveport-Bossier City Advocate: Entergy substation first step in Meta's massive need for power (June 27, 2025)
  7. ENR: $27B Meta data center pushes Louisiana toward massive power expansion (April 2, 2026)
  8. Fortune: Meta's Hyperion data center in Louisiana (March 26, 2026)
  9. WWNO (Gulf States Newsroom): Entergy's Meta gas plant costs soar as utility seeks approval for seven more (Nov. 19, 2026)
  10. Red River Radio: protesters oppose construction of 7 gas plants for Meta data center (Nov. 19, 2026)
  11. WWNO: Entergy says Meta power lines serve public purpose in Lincoln Parish land-rights lawsuit (Nov. 12, 2026)
  12. Meta Newsroom: one year in, $875 million in contracts (Dec. 19, 2025)
  13. TIC: Entergy Program
  14. Federal Register: FERC docket CP26-549, ETC Tiger Pipeline Franklin Farms Project (July 16, 2026)
  15. EPA ECHO: stormwater notice LAR10Q893
  16. DPR Construction: Meta Richland Parish Data Center
  17. Mortenson: Richland Parish Data Center
  18. Entergy Louisiana: infrastructure upgrades in Richland Parish (April 22, 2025)
  19. Corporate Mobile Housing: Meta data center, Holly Ridge
  20. ConstructConnect: data center construction input costs (Sept. 2, 2026)
  21. Entergy: EPC consortium to build Entergy Texas' new power station (Mar 3, 2023)
  22. Entergy Mississippi: Delta Blues Advanced Power Station

More project reports

All project reports
Get all 19 firms, free

All 19 firms on Meta's Hyperion data center

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.