What is Meta building in Kuna, Idaho?
Meta is building a data center campus at 6990 W. Kuna Mora Road in Kuna, Ada County, Idaho. Kuna's 2022 design drawings call the job Project Peregrine. Meta's project company on the city filings is Brisbie LLC.
Meta broke ground in 2022. In late 2022 Meta paused the job to redesign it for AI, and in 2023 Kuna approved a new site plan with two data center buildings. The press now puts the campus at 750,000 sq ft, with two large server buildings online. The largest is 350,000 sq ft.
How much is the Meta Kuna data center?
Meta says the campus is an investment of more than $1.2 billion in Kuna. That is the owner's total, including equipment, not a contract value.
In February 2022, Meta awarded Hensel Phelps an $800 million data center contract on the Kuna campus. No building permit values are public: Kuna's permits have no public search.
Meta also paid the City of Kuna an $8.4 million fee up front in 2022. The city treasurer said at a June 16, 2026 council meeting that the city asked for it over time, and Meta chose to pay it all at once.
How far along is the Meta Kuna data center?
Meta said the Kuna data center was online on Sept. 3, 2026, four years after it broke ground. Meta says the job supported 1,600 skilled trade workers at peak. About 100 people will work there full time.
Meta is not done. On July 22, 2025, Kuna's Planning and Zoning Commission approved Meta's plan for two more buildings on 40 added acres at 14375 S. Cole Road. Each is a quick-build membrane building of 135,000 sq ft, 150 feet by 900 feet and 50 feet tall. That makes the campus 282.7 acres. A local news headline on Oct. 15, 2026 said two more buildings are under construction.
Who is building the Meta Kuna data center?
Hensel Phelps is the general contractor. Its scope also covered the campus water and wastewater treatment plant, site utilities, roads and paving. Trade press also names Engineered Structures Inc. (ESI) of Meridian as a contractor on the campus, without saying what it builds.
On the design side, HDR is first on the title block of the 2022 drawings. Parametrix is the civil engineer and represented Meta's project company on the 2022, 2023 and 2025 Kuna design reviews. TEECOM did the technology and security design, O2 the landscape, and Peoples Associates Structural Engineers the structure.
Which trade firms are on the Meta Kuna data center?
No electrical, mechanical or plumbing permits for the campus are public, so the trade firms come from their own project pages. Ralph L. Wadsworth Construction (RLW) says it was a key earthwork and utilities subcontractor. Alpha Power Group lists electrical construction, logistics and material management on two data centers near Boise, on a page titled Kuna Data Center.
Idaho Power serves the campus under a special power agreement the state approved in 2023. Concrete Construction Supply says it supplies the contractors on the job. 11 firms in all are on the list below.
How do the ways into the Meta Kuna data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Meta's Kuna data center | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The expansion buildings | A call to Hensel Phelps or the other firms about the two 135,000 sq ft buildings on Cole Road | Builders, site and specialty subcontractors | A way onto the next work on the campus | No public contract or permit for the expansion yet |
Who should go after the Meta Kuna data center?
| Site, concrete and underground suppliers | RLW, the earthwork and utilities subcontractor, and Concrete Construction Supply, a supplier to the contractors, on a campus that keeps growing. |
|---|
| Electrical distributors and gear reps | Alpha Power Group on electrical construction and material management, and Idaho Power on the campus power service. |
|---|
| Builders and specialty subcontractors | Hensel Phelps and ESI, with two more 135,000 sq ft buildings planned on 40 added acres. |
|---|
What should you do next on the Meta Kuna data center?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Meta's Kuna data center on Kuna-Mora Road.
- Ask about the two expansion buildings on S. Cole Road, the next work on the campus.
Questions people ask about the Meta Kuna data center
How much is the Meta Kuna data center?
Meta says it is investing more than $1.2 billion in Kuna. That is the owner's total, not a contract value, and it is up from the $800 million data center contract Meta awarded Hensel Phelps in 2022.
Who built the Meta data center in Kuna, Idaho?
Hensel Phelps is the general contractor. Trade press also names Engineered Structures Inc. (ESI) of Meridian as a contractor on the campus. 11 firms are named on the job, listed above.
When did the Meta Kuna data center open?
Meta said the Kuna data center was online on Sept. 3, 2026, four years after it broke ground in 2022.
Is Meta building more in Kuna?
Yes. In July 2025 Kuna approved Meta's plan for two more buildings of 135,000 sq ft each on 40 added acres. A local news headline on Oct. 15, 2026 said two more buildings are under construction.
What is Project Peregrine?
Project Peregrine is the name on Kuna's 2022 design review drawings for Meta's campus. Meta's project company on the city filings is Brisbie LLC.
Where is the Meta Kuna data center?
It is at 6990 W. Kuna Mora Road in Kuna, Ada County, Idaho, at the corner of Kuna-Mora Road and Cole Road. The expansion is at 14375 S. Cole Road.
How many workers built the Meta Kuna data center?
Meta says the job supported 1,600 skilled trade workers at peak construction. About 100 people will work there full time.
What fee did Meta pay Kuna?
Meta paid the City of Kuna an $8.4 million fee up front in 2022. The city asked to be paid over time, and Meta chose to pay it all at once, the city treasurer said at a June 16, 2026 council meeting.
Who powers the Meta Kuna data center?
Idaho Power serves the campus under a special Energy Services Agreement that the Idaho Public Utilities Commission approved on May 11, 2023.
What happens next on the Meta Kuna data center?
The two 135,000 sq ft expansion buildings are the next work on the campus. We'll update this page when a new filing or firm appears.
How we built this list
We read Meta's Sept. 3, 2026 launch post, Hensel Phelps's 2022 award release and trade partner flyer, Kuna's Planning and Zoning packets for 2022, 2023 and 2025 and the Commission's July 22, 2025 decision on the expansion, a June 2026 Kuna council meeting, the Idaho PUC order on the power agreement, news reports and each firm's own project page, all on Nov. 20, 2026. We kept each firm a public record or its own page ties to this campus. Kuna's building permits have no public search and state trade permits are searchable only by number, so no electrical, mechanical or plumbing contractor of record could be found; the trade firms come from their own project pages. ESI is a trade press tie only. The $1.2 billion is Meta's own total, not a contract value; in January 2026 a Meta spokesperson called $800 million still accurate for its total in the region, and an outside satellite-based model gives a much larger figure we do not use. The Oct. 15, 2026 news story on the two new buildings was read as a headline only. Left out: Meta and its project companies, public bodies, the land seller, a solar developer whose plants supply power off site and list no phone, a design consultant with no phone or website, firms named only in online chatter, and individuals. Phones are each firm's own line from its own site, except O2's, which is printed on its own drawings; Hensel Phelps, PASE, RLW and ESI are headquarters lines, and Idaho Power's is its customer service line. First published Nov. 20, 2026. We'll update this page when a new filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 20, 2026- Meta Data Centers: Kuna, we are online! (Sept. 3, 2026)
- Hensel Phelps: Meta awards Hensel Phelps Kuna data center (Feb. 24, 2022)
- Hensel Phelps Kuna Data Center trade partner outreach flyer (2022)
- City of Kuna P&Z packet, Mar. 22, 2022, case 22-04-DR (Project Peregrine)
- City of Kuna P&Z packet, May 23, 2023, 22-04-DR modification
- City of Kuna P&Z packet, July 22, 2025, case 25-24-DR (expansion)
- City of Kuna P&Z packet, Aug. 12, 2025: July 22, 2025 minutes and decision approving 25-24-DR
- City of Kuna City Council minutes, June 16, 2026
- Idaho PUC case IPC-E-21-42, Final Order No. 35777 (May 11, 2023)
- Idaho Statesman via East Idaho News (Sept. 4, 2026)
- BoiseDev headline (Oct. 15, 2026; headline read only)
- DatacenterDynamics: Meta's Kuna, Idaho data center paused in AI redesign
- ConstructionOwners.com (Jan. 8, 2026)
- RLW project page: Meta - Kuna Data Center Campus
- Alpha Power Group project page: Kuna Data Center
- Concrete Construction Supply: From Meta to Micron (Oct. 6, 2026)