What's the form you need to bid on Meta's Lebanon data center?
Mortenson runs a Trade Partners form on the project's website, lebanondatacenter.com. It asks for your company, the work or materials you offer, the project size you're most competitive at, any small, local, minority-owned or woman-owned certification, and your experience.
The form lists carpentry and framing, concrete and foundation, construction labor, drywall, electrical, erosion control, heavy equipment, HVAC, plumbing and piping, roofing and surveying.
Mortenson's national program page says trade partners have to complete its prequalification form, run through TradeTapp, to be eligible to bid or contract work.
What's being bought around Meta's Lebanon campus?
- Temporary power. Indiana issued Life Cycle Power a permit on Sept. 25, 2026 for up to 65 Caterpillar G3516H gas generators on the site. The operator was reported expecting about 32, running through the end of 2027.
- Standby equipment. A second permit covers 12 diesel emergency generators, 2 fire pumps and 12 belly tanks of 7,185 gallons each.
- Grid work. Wabash Valley Power Alliance plans 42 miles of transmission and 3 substations for the area.
- Road. Indiana's State Road 32 realignment beside the campus runs about 4 miles with 3 roundabouts.
- Water. Lebanon Utilities' program serves growth in the LEAP district. A final state permit on Oct. 26, 2026 covers 33,200 feet of 30-inch ductile iron pipe, and its board tentatively picked Reynolds Construction for Phase 2 in April. Nothing we found says Meta pays for this job.
We found no named firm for concrete, rebar, structural steel, mechanical, HVAC, plumbing, roofing, drywall or fire protection on the campus. That doesn't mean those trades are unbought.
How do the ways into Meta's Lebanon job compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| Mortenson's trade partner form | A form on the project's website | Trades and vendors new to the job | Mortenson says it's in touch if there's a good fit | It isn't a bid invitation |
| Mortenson's prequalification | A form run through TradeTapp | Firms ready to bid or contract with Mortenson | Its program page says it's required to be eligible | It covers Mortenson generally, and a local FAQ says most packages need no advance prequalification |
| Turner's Indiana page | A page to register interest in trade packages | Trades and related services | Your interest on file with Turner | It lists no packages or dates |
| Selling to a named firm | A call to Faith Technologies or Life Cycle Power | Suppliers and specialty subs | A direct conversation with a firm named on the job | Neither publishes a supplier page for this job |
| The public water and road jobs | Utility and state work around the campus | Pipe, tank, paving and civil firms | Named firms and real quantities | No source says Meta pays for them |
Who should go after this job, and who shouldn't?
| Trade contractors | Start with Mortenson's form and Turner's page. |
|---|
| Electrical and low-voltage firms | Faith Technologies says it's executing millions of labor hours there. |
|---|
| Pipe, valve and pump suppliers | The water jobs have the clearest quantities, including 33,200 feet of 30-inch ductile iron pipe. |
|---|
| Firms that need a public bid date | This isn't the job for you yet, because we found none for the campus. |
|---|
What should you do next on Meta's Lebanon job?
- Fill out Mortenson's form if your trade is listed.
- Register on Turner's Indiana page.
- Finish Mortenson's prequalification if you're ready to bid its work.
- Open the full list and call the firms named for your trade.
Questions people ask about Meta's Lebanon data center
Who is building Meta's Lebanon data center?
Meta picked Mortenson and Turner. Faith Technologies is named as a collaborator by Mortenson and on the project's website.
Who is the general contractor on Meta's Lebanon data center?
Trade press calls Mortenson the general contractor, and Turner describes itself as one of the contractors. We found no source on how the campus is split between them.
How do subcontractors get on it?
Mortenson's trade partner form is on the project's website, and Turner has an Indiana page to register interest in trade packages. Mortenson's program page requires prequalification through TradeTapp to be eligible to bid or contract work. None of this guarantees an invitation.
When is it bidding?
We found no public bid date for the campus. Private packages aren't published.
Who is doing the electrical?
Faith Technologies says it's executing millions of labor hours there, and that it's building 2 warehouse hubs and near-site manufacturing.
How is the site powered before the grid connection?
Life Cycle Power holds a state permit for up to 65 natural gas generators, and it was reported expecting about 32, running through the end of 2027. Permanent power comes through Boone Power and Wabash Valley Power Alliance.
Is Meta paying for the roads and water?
Meta says it will put more than $120 million into water and other public projects, reported as $45 million for roads and $75 million for water. We found no source assigning that money to a specific job.
What are the risks of chasing this job?
We found no public bid date, the packages are private, and a form doesn't guarantee a call. Some trades may already be bought, and we can't see that from public records.
What happens after I fill out Mortenson's form?
Mortenson says it will be in touch if there's a good fit. It gives no timeline.
How much is Meta spending in Lebanon?
Indiana says Meta will invest more than $10 billion over several phases, in a project of up to 6 phases.
What new data centers are being built in Indiana?
Meta's Lebanon campus is one, at more than $10 billion in the LEAP district in Boone County. This page covers that campus.
When will it be finished?
Meta's release gives no finish date. First buildings are reported operational by 2027, and the state describes up to 6 phases.
How we built this list
We read Meta's and the state's announcements, state permits, utility board minutes, and each builder's own pages. A row is on the list only if a source ties it to the campus or the LEAP district around it. We left out hiring pages and work with no stated tie, and we mark each row by how firm it is. A row with no bid date is never marked open. First published Nov. 4, 2026. We'll update this page when a new permit, firm or bid date appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 4, 2026- Indiana Economic Development Corp., Feb. 11, 2026
- Meta, February 2026
- Lebanon Data Center, Trade Partners
- Mortenson, Trade Partner Program
- Turner, Indiana Opportunities
- Construction Dive
- ENR
- Faith Technologies
- Indiana DEM permit 50087
- Indiana DEM permit 50034
- IndyStar, via Yahoo
- Indiana DEM permit WS-13173
- Indiana Finance Authority
- Lebanon Utilities minutes, Apr. 8, 2026
- Central Indiana Grid Expansion
- Boone Power