Who's building Meta's data center in Temple, Texas

Meta's $1.2 billion data center in Temple, Texas went live in July after Meta tore down a half-built version in 2023, and a $197 million third building is going up next door.

By Porter Stanley. Updated .

Meta is building a data center campus at 3101 Industrial Blvd in Temple, Bell County, Texas. Meta says the campus is an investment of more than $1.2 billion, and it went live on July 22, 2026 as Meta's first AI-optimized data center to come online. A third building, registered with the state at $197 million, is being added beside it. JE Dunn Construction is the general contractor. 15 firms are named on the job; the list below has all 15.

$1.2B+Meta's stated investment in Temple
$197MBuilding 3 state registration (Dec. 2025)
1,200Trade workers on site at peak
15Firms named on the job

Get all 15 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 15 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 15 firms on the Meta Temple data center?

We list the 15 firms named on Meta's Temple, Texas data center, one row each, strongest tie first, with what each one does on the job and where its name comes from.

1Permit on the recordNov 26, 2025

JE Dunn Construction Company

General contractor for the whole campus, from Buildings 1 and 2 and the admin building to the Building 3 foundation and building permits; it also holds the campus stormwater permit on Meta's Temple data center in Temple, Bell County, TX

Meta's Temple data center campus, 3101 Industrial Blvd and 2230-2310 Eberhardt Rd (Enterprise Park West), Temple (Bell County), TX

City permit FY-26-10-FOND for the Building 3 foundation and underground utilities, filed Nov. 2025; state stormwater coverage since March 15, 2022; Meta puts the campus at more than $1.2 billion

Work: General contractor for the whole campus, from Buildings 1 and 2 and the admin building to the Building 3 foundation and building permits; it also holds the campus stormwater permit

Who to call: JE Dunn Construction Company
JE Dunn Construction Austin office line
(Austin, TX)
(512) 329-9618

The opportunity: City of Temple permit FY-26-10-FOND at 2310 Eberhardt Rd: 'Foundation and underground utilities permit for a new data center.' General contractor: JE Dunn Construction Company. TCEQ stormwater authorization at State Loop 363 and Industrial Blvd, active since March 15, 2022. Named by Meta in 2023. JE Dunn's own page says 1,200 trade workers at peak.

2Latest recordOct 12, 2023

Rosendin

Electrical contractor for the data center building and site work, picked in 2022 and named again by Meta when work restarted in 2023 on Meta's Temple data center in Temple, Bell County, TX

Meta's Temple data center campus, 3101 Industrial Blvd and 2230-2310 Eberhardt Rd (Enterprise Park West), Temple (Bell County), TX

Named by Meta Oct. 12, 2023; its 2022 release tied it to the then $800 million data center

Work: Electrical contractor for the data center building and site work, picked in 2022 and named again by Meta when work restarted in 2023

Who to call: Rosendin
Rosendin headquarters line
(San Jose, CA)
(408) 286-2800

The opportunity: Meta's Oct. 12, 2023 post: 'Meta is excited to continue working with JE Dunn Construction on this project, and amazing local contractors Rosendin, Brandt Companies, Peabody General Contractors, Alamo Structural Steel, Perry and Perry Builders, CentiMark Corporation, and BakerTriangle.' Rosendin's June 2022 release: it 'will work with general contractor JE Dunn to build the $800-million data center building and site infrastructure.'

3Permit on the recordJan 15, 2026

HEI Civil (formerly Peabody General Contractors)

Underground utilities: fire lines and hydrants on the campus (2024, as Peabody), then a 1,440-foot dedicated fire line with two hydrants (Dec. 2025) and the Building 3 water meter (Jan. 2026), as HEI Civil on Meta's Temple data center in Temple, Bell County, TX

Meta's Temple data center campus, 3101 Industrial Blvd and 2230-2310 Eberhardt Rd (Enterprise Park West), Temple (Bell County), TX

City permits FY-24-5-UFL and FY-24-6-UFL (Sept. 2024), FY-26-2-UFL (Dec. 2025) and FY-26-37-WT (Jan. 2026); no value stated

Work: Underground utilities: fire lines and hydrants on the campus (2024, as Peabody), then a 1,440-foot dedicated fire line with two hydrants (Dec. 2025) and the Building 3 water meter (Jan. 2026), as HEI Civil

Who to call: HEI Civil (formerly Peabody General Contractors)
HEI Civil Texas office line
(Austin, TX)
(512) 389-1005

The opportunity: Permit FY-26-37-WT at 3101 Industrial Blvd Bldg E: 'To install a 6" domestic water meter for building E.' Permit FY-26-2-UFL: 'Trench and Place ~1440 LF of 10" PVC pipe ... and 2 EA fire hydrant assemblies for dedicated fire line.' Peabody General Contractors filed the 2024 fire line permits and was named by Meta in 2023; Peabody was renamed HEI Civil in January 2025.

What is Meta building in Temple, Texas?

Meta is building a data center campus at 3101 Industrial Blvd and on Eberhardt Rd, in Enterprise Park West near Loop 363 in Temple, Bell County, Texas. State filings call it Project Pasca. Most list Polmer LLC as owner, and the warehouse filing gives Polmer's address as 1 Meta Way in Menlo Park, Meta's home base.

JE Dunn says the campus has three buildings on 386 acres, with over 750,000 sq ft. State filings also cover a warehouse, a construction admin building and a guardhouse. Meta says it is its first AI-optimized data center to come online.

How much is the Meta Temple data center?

Meta says the campus is an investment of more than $1.2 billion in Temple. In 2022 and 2023 it gave $800 million. The $1.2 billion is Meta's own total, not a contract value.

The five state filings for the campus add up to about $1.09 billion, the sum. The biggest is $880 million for the main data center, filed in April 2022. Building 3 is $197 million. The rest are a $9.8 million warehouse, a $500,000 guardhouse and a $300,000 construction admin building. Each is the estimated cost given to the state, not Meta's full spend.

How far along is the Meta Temple data center?

The first part is done. Meta said on July 22, 2026 that the campus is online. At peak, 1,200 skilled trade workers were on site, and the data center now supports almost 100 operational roles, per Meta.

It did not go in a straight line. Meta paused work in December 2022, tore down the half-built building in 2023 and started over in October 2023 on a new design built for AI.

Building 3 is the work still open. It is a 145,177 sq ft single-story data center, registered with the state on Dec. 15, 2025 at $197 million, with an estimated end date of Sept. 30, 2026. Its foundation permit was filed in November 2025, its sprinkler permit was issued early in 2026, and its fire alarm and storm shelter permits were in city review in April and May 2026. We found no word that it is done.

Who is building the Meta Temple data center?

JE Dunn Construction is the general contractor. City permits name it on Building 3, and it has held the campus's state stormwater permit since March 2022. Burns & McDonnell is the design firm on the $880 million main filing, and Corgan Associates, a design firm, filed Building 3's city permits.

Meta named JE Dunn and seven local firms in 2023: Rosendin, Brandt Companies, Peabody General Contractors, Alamo Structural Steel, Perry and Perry Builders, CentiMark and BakerTriangle. Meta did not say what each one does, so for most of them the trade on our list comes from the firm's line of work.

Which trade firms are on the Meta Temple data center?

City permits show who does what on site. Firetron has the fire alarms for Building 1 and Building 3. Western States Fire Protection has the sprinklers, including nine pre-action systems in Building 3. HEI Civil, which used to be Peabody, has the fire lines, hydrants and water taps.

Oncor planned the campus power with Meta, and a state record shows it started work on a substation next to the site in 2024. 15 firms in all are on the list below.

Is there a fight over the Meta Temple data center?

Yes. Temple Stands Together is a local group against data centers in the city. Its president said Meta has "a very powerful marketing engine," and that the group "found a lot of holes in their promises."

How do the ways into the Meta Temple data center compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on Meta's Temple data centerEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell

Who should go after the Meta Temple data center?

Electrical distributors and gear repsRosendin, the electrical contractor since 2022, and Oncor on the campus power, with a $197 million third building still going in.
Fire, mechanical and plumbing repsFiretron on fire alarms, Western States Fire Protection on nine pre-action systems in Building 3, and Southland (Brandt), a mechanical and plumbing firm.
Concrete, steel and site suppliersJE Dunn, HEI Civil on fire lines and water taps, and Alamo Structural Steel.

What should you do next on the Meta Temple data center?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on Meta's Temple data center, Building 3, on Industrial Blvd in Temple.

Questions people ask about the Meta Temple data center

How much is the Meta Temple data center?

Meta says the campus is an investment of more than $1.2 billion in Temple (July 22, 2026), up from the $800 million it gave in 2022 and 2023. The five state filings for the campus add up to about $1.09 billion, the sum, including $197 million for Building 3.

Who is building the Meta data center in Temple, Texas?

JE Dunn Construction is the general contractor for the whole campus, including Building 3. Meta also named Rosendin, Brandt, Peabody, Alamo Structural Steel, CentiMark and BakerTriangle, and city permits name more. 15 firms are on the list above.

Is the Meta Temple data center open?

Yes. Meta said on July 22, 2026 that the campus is online and is its first AI-optimized data center to come online. A third building is being added beside it.

What is Building 3 at the Meta Temple data center?

A 145,177 sq ft single-story data center, registered with the state on Dec. 15, 2025 at $197 million, with an estimated end date of Sept. 30, 2026. The state record still read 'Project Registered' when we checked on Nov. 20, 2026, and we found no word that it is done.

Why did Meta tear down its first Temple data center?

Meta paused work in December 2022 and tore down the half-built building in 2023, then restarted in October 2023 on a new design built for AI. JE Dunn stayed on as the builder.

Where is the Meta Temple data center?

At 3101 Industrial Blvd and 2230-2310 Eberhardt Rd in Enterprise Park West, near Loop 363, in Temple, Bell County, Texas.

How big is the Meta Temple data center?

JE Dunn says it is a three-building campus on 386 acres with over 750,000 sq ft. Building 3 alone is 145,177 sq ft.

How many people worked on the Meta Temple data center?

Meta says 1,200 skilled trade workers were on site at peak, and the data center now supports almost 100 operational roles.

Do people in Temple oppose the Meta data center?

Some do. Temple Stands Together, a local group against data centers, says Meta has "a very powerful marketing engine," and that it "found a lot of holes in their promises."

What happens next on the Meta Temple data center?

Building 3 is the open work. Its fire alarm and storm shelter permits were in city review in April and May 2026. We'll update this page when a new permit or firm appears.

How we built this list

We read Meta's Temple posts (Oct. 12, 2023, July 22, 2026 and its Building Texas page), JE Dunn's project page, the state's TDLR building registrations for the campus, TCEQ's stormwater records for Bell County, 123 City of Temple weekly permit reports from March 2024 to November 2026, and news reports, on Nov. 20, 2026. We kept each firm a public record names on this campus. Meta's 2023 post names seven firms with no scope, so for Brandt, Alamo, CentiMark and BakerTriangle the trade comes from the firm's line of work. The $1.09 billion is the sum of five state registrations, not Meta's spend. Left out: Meta and Polmer LLC (the owner), city and county partners, state accessibility reviewers, a separate data center by another developer across Eberhardt Rd, other Temple data centers, a fiber permit that does not name Meta, and two firms Meta named for which we found no website of their own (Perry and Perry Builders, and the guardhouse designer Merriman Pitt / Anderson). Phones are each firm's own line from its own site; JE Dunn's is its Austin office, and Rosendin, CentiMark, Southland, Cushing Terrell and Oncor are head or main lines, not Temple. Western States' line comes from a search index of its site, which blocked our read. We found no main line on the sites of Burns & McDonnell, Corgan, HED and ASI Signage, so we give their websites only. First published Nov. 20, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 15 firms, free

All 15 firms on the Meta Temple data center

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.