Who's building Micron's megafab in Clay, New York

Micron's $100 billion megafab in Clay, New York has moved into vertical construction, even as two lawsuits try to void its permits.

By Porter Stanley. Updated .

Micron is building a memory chip megafab at White Pine Commerce Park in Clay, Onondaga County, New York. Micron calls it a $100 billion complex: up to four fabs built over 20-plus years, not one contract. First concrete for the first fab went in on July 9, 2026, and about $675 million has gone to New York firms so far. Bechtel is building the first fab, Gilbane runs the site work and Jacobs leads the design. 18 firms are named on the job; the list below has all 18.

$100BMicron's planned investment, up to four fabs over 20+ years
$675MGone to New York firms so far (July 2026)
1,400Acres in White Pine Commerce Park
18Firms named on the job

Get all 18 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 18 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 18 firms on the Micron New York megafab?

We list the 18 firms named on Micron's New York megafab in Clay, one row each, strongest tie first, with what each one does on the job and where its name comes from.

1Latest recordJun 10, 2026

Bechtel

Engineering, procurement and construction (EPC) partner for the first New York fab on Micron's New York megafab in Clay, Onondaga County, NY

Micron's New York megafab, White Pine Commerce Park, 5171 Route 31, Clay (Onondaga County), NY

Named EPC partner June 10, 2026; no contract value published

Work: Engineering, procurement and construction (EPC) partner for the first New York fab

Who to call: Bechtel
Bechtel main line
(Reston, VA headquarters)
(571) 392-6300

The opportunity: Bechtel's own release: 'Micron Selects Bechtel as Construction Partner for Historic New York Semiconductor Project.' Micron's July 9, 2026 release names Bechtel for 'the engineering, procurement and construction for the first New York fab.'

2Latest recordJul 9, 2026

Gilbane Building Company

Preconstruction and site infrastructure contractor for 680 acres of the 1,400-acre site; it runs the site trade packages below on Micron's New York megafab in Clay, Onondaga County, NY

Micron's New York megafab, White Pine Commerce Park, 5171 Route 31, Clay (Onondaga County), NY

Named July 9, 2026; no contract value published

Work: Preconstruction and site infrastructure contractor for 680 acres of the 1,400-acre site; it runs the site trade packages below

Who to call: Gilbane Building Company
Gilbane headquarters line
(Providence, RI headquarters; no Syracuse line on its site)
(401) 456-5800

The opportunity: Micron's July 9, 2026 release names 'Gilbane Building Company, the preconstruction and site infrastructure contractor.' Gilbane's Micron page: Micron 'selected Gilbane to lead the preconstruction and site enabling works for 680 acres of its landmark 1,400-acre site in Clay, New York.' Gilbane posts its awarded packages and open bids on that page.

3Latest recordJul 9, 2026

Jacobs

Architectural and engineering design partner on Micron's New York megafab in Clay, Onondaga County, NY

Micron's New York megafab, White Pine Commerce Park, 5171 Route 31, Clay (Onondaga County), NY

Named July 9, 2026; no contract value published

Work: Architectural and engineering design partner

Who to call: Jacobs
Jacobs headquarters line
(Dallas, TX headquarters)
(214) 638-0145

The opportunity: Micron's July 9, 2026 release names 'Jacobs, the architectural and engineering design partner.'

What is Micron building in Clay, New York?

Micron is building a memory chip megafab at White Pine Commerce Park, 5171 Route 31, in the town of Clay, north of Syracuse in Onondaga County. The park is 1,400 acres. Micron plans up to four fabs there, built over the next 20-plus years.

The first fab is the one being built now. Gilbane's site work covers 680 of the 1,400 acres. Micron says the build will bring 50,000 jobs in New York, including 9,000 direct Micron jobs.

How much is the Micron New York megafab?

Micron calls it a $100 billion memory manufacturing complex. That is the plan for all four fabs over 20-plus years, and much of it is equipment, so it is not the value of one building contract.

On July 9, 2026, Micron said about $675 million had gone to New York contractors, suppliers and subcontractors, more than half of everything awarded so far. Micron's annual report lists up to $6.1 billion in federal CHIPS Act funding, shared with two planned fabs in Boise, Idaho, and up to $5.5 billion from New York State under a non-binding term sheet.

How far along is the Micron New York megafab?

Micron broke ground on Jan. 16, 2026.

First concrete for the first fab went in on July 9, 2026, more than a quarter ahead of plan, Micron says. Micron's annual report, filed Oct. 9, 2026, calls that pour "the transition from site preparation into vertical construction". Micron expects first wafer output in calendar 2030.

Two lawsuits, filed Jan. 16 and July 31, 2026 by Neighbors for a Better Micron and Jobs to Move America, ask a court to void the site's permits, per the same report. Construction goes on.

Who is building the Micron New York megafab?

Micron named three main partners on July 9, 2026. Bechtel handles engineering, procurement and construction for the first fab; Micron picked it in June. Gilbane Building Company leads preconstruction and site work on 680 acres. Jacobs is the architectural and engineering design partner.

Which trade firms are on the Micron New York megafab?

Gilbane posts the site packages it has awarded. Its Sept. 1, 2026 list names a Petillo and Vinagro joint venture on mass excavation, Baker Concrete Construction on a retaining wall, Heidelberg Materials on aggregate processing, Northern Asphalt on the concrete batch plants and Supreme Industries on clearing.

Under the ground, Upstate Pipe and Civil has the water lines and a Miller Bros. and Hewitt Young Electric joint venture has the electrical. Northline Utilities has temporary power, McFarland Johnson inspects stormwater and Ravi Engineering surveys. Site services go to Atlas Fence, Nadler Modular, Herc Rentals, EarthCam and Signal. 18 firms in all are on the list below.

How do the ways into the Micron New York megafab compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on Micron's New York megafab in ClayEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell
Gilbane's open site packagesA bid on a package Gilbane posts on its Micron in New York pageSite, civil, electrical and service firmsA package on the site workGilbane chooses; a bid is not an award

Who should go after the Micron New York megafab?

Concrete, aggregate and site suppliersThe Petillo and Vinagro joint venture on mass excavation, Baker on the retaining wall, Heidelberg Materials on aggregate and Northern Asphalt on the batch plants, with the first fab now past site prep.
Electrical, power and utility repsThe Miller Bros. and Hewitt Young Electric joint venture on underground electrical, Northline Utilities on temporary power and Upstate Pipe and Civil on the water lines.
Builders, engineers and big subcontractorsBechtel on the first fab, Gilbane on site work and Jacobs on design, on a park planned for up to four fabs.

What should you do next on the Micron New York megafab?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on Micron's megafab at White Pine Commerce Park in Clay, New York.

Questions people ask about the Micron New York megafab

How much is the Micron New York megafab?

Micron calls it a $100 billion investment for up to four fabs over 20-plus years. Much of that is equipment, so it is not one building contract. About $675 million had gone to New York firms by July 9, 2026.

Where is the Micron megafab in New York?

It is at White Pine Commerce Park, 5171 Route 31, in Clay, Onondaga County, north of Syracuse. The park is 1,400 acres.

Who is building the Micron fab in Clay, NY?

Bechtel handles engineering, procurement and construction for the first fab. Gilbane leads preconstruction and site work, and Jacobs is the design partner. 18 firms are named on the job, listed above.

When did construction start on the Micron New York fab?

Micron broke ground on Jan. 16, 2026 and poured first concrete for the first fab on July 9, 2026, more than a quarter ahead of plan, Micron says.

When will the Micron New York fab open?

Micron expects first wafer output from the first fab in calendar 2030, per its annual report filed Oct. 9, 2026.

Are there lawsuits against the Micron New York project?

Yes. Two lawsuits, filed Jan. 16 and July 31, 2026, ask a court to void the site's permits, per Micron's annual report. Construction goes on.

How many fabs will Micron build in New York?

Up to four, built over the next 20-plus years. The first is under construction now.

How many jobs will the Micron New York megafab create?

Micron says 50,000 jobs in New York, including 9,000 direct Micron jobs.

How do subcontractors get work on the Micron New York site?

Gilbane posts its awarded packages and open bids for the site work on its Micron in New York page. A supplier can also call the firms already on the job, listed above.

How we built this list

We read Micron's Jan. 16 and July 9, 2026 releases, Micron's fiscal 2026 annual report (filed Oct. 9, 2026), Bechtel's June 10, 2026 release, and Gilbane's Micron in New York page and its Sept. 1, 2026 contractor list, all on Nov. 20, 2026. We kept each firm Micron, Bechtel or Gilbane names on this site. Bechtel, Gilbane and Jacobs come from Micron's release; the trade firms come from the packages Gilbane lists as awarded. Record dates are the date of the record that names each firm. The $100 billion is Micron's planned investment over 20-plus years, not a contract value, and no package value is published. Left out: Micron itself, public agencies and the union council, firms Gilbane lists only as bidders, firms named only in passing with no stated role, and a guard shack firm with no website or main line. Phones are each firm's own main or office line from its own site; most are head offices, not Syracuse. Heidelberg Materials' and Herc Rentals' sites did not show a main line, so we give their websites only. First published Nov. 20, 2026. We'll update this page when a new permit, award or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports