What did Redmond issue for Microsoft Building 33 on Oct. 19?
On Oct. 19, 2026, the City of Redmond issued electrical permit ELEC-2026-07357 for Microsoft Building 33 at 16070 NE 36th St to Sequoyah Electric. It lists a valuation of $4,307,031 and describes the installation of 803 new light fixtures, 67 mechanical connections and general power receptacles, for 307 added circuits. On Nov. 10 the city's page showed no inspections on it yet.
It's the largest of 12 issued electrical permits Sequoyah holds on the building. Most carry the same Sequoyah job number, SEQ#101230. They include the removal and replacement of 1,658 light fixtures and lighting control on levels P2, P1, L1 and L2 (Sept. 24), a 50 kW and a 70 kW UPS (Sept. 17), and new breakers and feeders for three electric boilers (Aug. 10).
Sequoyah is based in Redmond, at 15135 NE 92nd St.
What is Microsoft building inside Building 33?
GLY Construction holds the two building permits. The core and shell permit, issued Sept. 10, 2026, covers demolition and alterations inside the building: a new level-2 slab opening, a new stair and escalator, new group restrooms and a rooftop "pop-up" with a long-span steel structure, across 63,627 sq ft. The interior tenant improvement permit, issued Nov. 3, 2026, covers 52,036 sq ft and lists a valuation of $22,400,000. NBBJ is the architect on both.
Much of the building's equipment is being replaced too. Auburn Mechanical's permits cover six custom air handlers, three electric boilers in place of two gas ones, a two-cell cooling tower and dozens of VAV boxes and fans. Its plumbing permit for the new multipurpose room lists 30 toilets, 8 urinals, 21 bath sinks and 2 grease interceptors.
Building 33 is the Microsoft Conference Center. It sits on NE 36th, at the edge of the area the city's page gives for Microsoft's East Campus refresh, though no source we found puts Building 33 in that program.
Who else is on Microsoft Building 33's permits?
Valley Electric replaced five medium-voltage switches and retrofitted ABB and Schneider breakers on the switchgear in September; the city finaled those permits on Sept. 22. Cosco Fire Protection holds the sprinkler permit for the level 1 and 2 work, and Siemens applied on Nov. 9, 2026 to modify the fire alarm system, 595 devices. Teknon Infrastructure Services and Cochran hold low-voltage cabling permits.
We couldn't find a news story on the renovation. The firms come from the city's permit records.
How do the ways into Building 33 compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The electrician on the permit | A call to Sequoyah Electric, on 12 issued electrical permits for Building 33 | Lighting, controls, wire, panel, UPS and gear reps | A conversation with the firm buying the building's fixtures and branch power | Its Building 33 project team isn't listed publicly, so start at the main office |
| The builder | A call to GLY Construction about the interior work issued Nov. 3 | Finish, specialty and any trade with no sub named | Who holds the scopes the permits don't name yet | GLY may already have most packages let |
| The mechanical and plumbing sub | A call to Auburn Mechanical, on 6 mechanical and 2 plumbing permits | HVAC equipment, controls, plumbing fixture and water heater reps | The firm buying the air handlers, VAVs, boilers and fixtures | Several of its permits were issued in July and August |
| The switchgear firm | A call to Valley Electric, which retrofitted the switchgear breakers | Switchgear, breaker and MV reps | Who services Microsoft's gear in this building | Those three permits are finaled, so that work is done |
Who should go after Building 33, and who shouldn't?
| Lighting and controls reps | Sequoyah's permits cover 803 new fixtures, 1,658 replaced fixtures, 335 more replaced and a new lighting control system. |
|---|
| Electrical distributors and gear reps | Sequoyah's permits include 27 panels, 26 feeders, three 1200AF breakers, 34 energy meters and two UPS units. |
|---|
| HVAC and plumbing reps | Auburn Mechanical holds permits for six air handlers, three electric boilers, a cooling tower, VAVs and the multipurpose room's fixtures. |
|---|
| Firms hoping to bid the electrical | The main electrical work already has a firm on the permits. Watch Microsoft's other Redmond buildings instead. |
|---|
What should you do next on Building 33?
- If you sell lighting, controls, wire, panels or UPS, call Sequoyah Electric's main office in Redmond and ask for the team on Microsoft Building 33.
- If you sell HVAC or plumbing equipment, call Auburn Mechanical's main line in Auburn.
- If you do finish or specialty work, call GLY Construction's Bellevue office and ask who holds your scope on the interior.
- Open the full list for every permit and firm on the building, with each company's line.
Questions people ask about Microsoft Building 33
Who is the electrician on Microsoft Building 33?
Sequoyah Electric. Redmond issued it 12 electrical permits on the building between June and October 2026, the largest a $4,307,031 permit on Oct. 19 for 803 new light fixtures and 307 added circuits.
Who is the general contractor on Microsoft Building 33?
GLY Construction. It is the contractor on both building permits, the core and shell permit issued Sept. 10, 2026 and the interior tenant improvement permit issued Nov. 3, 2026.
What is Microsoft Building 33?
It is the Microsoft Conference Center on the Redmond campus. Event pages list the Microsoft Conference Center at Building 33, 16070 NE 36th Way, and ENR has called building 33 the Microsoft Conference Center.
How much is the Building 33 renovation?
The interior tenant improvement permit lists a valuation of $22,400,000. The core and shell permit lists the same figure, so we don't add them. Microsoft hasn't published a cost.
Who does the HVAC and plumbing on Building 33?
Auburn Mechanical. It holds six mechanical permits, from six custom air handlers to three electric boilers and a cooling tower, and two plumbing permits.
Who designed the Building 33 renovation?
NBBJ is the architect and applicant on both building permits.
Who did the switchgear work on Building 33?
Valley Electric replaced five medium-voltage switches and retrofitted eight ABB and three Schneider breakers in September 2026. The city finaled all three permits on Sept. 22, 2026.
Is Building 33's electrical work still open to bid?
We found no public bid. The main electrical work already has a firm on the permits, Sequoyah Electric, so a supplier's way in is a call to Sequoyah. The fire alarm modification, 595 devices, was applied for by Siemens on Nov. 9, 2026 and isn't issued yet.
When will the Building 33 renovation be done?
We found no completion date. The interior permit was issued Nov. 3, 2026 and its listed expiry is Nov. 3, 2027, and on Nov. 10 the city showed no inspections yet on the $4.3 million electrical permit.
What are the risks for a supplier on Building 33?
The electrician and the mechanical sub may already have bought some equipment, since their earliest permits date from June to August 2026. The switchgear retrofits are finished. The newest work, the 803 new fixtures and the interior build-out, was permitted in October and November.
Is Building 33 part of Microsoft's campus refresh?
We found no source that says so. The City of Redmond's page places the East Campus refresh between 156th Avenue NE and NE 36th Way and between NE 31st Street and NE 36th Street; Building 33 sits on NE 36th, but no record ties it to that program.
How we built this list
We read every City of Redmond permit at 16070 NE 36th St on the city's public permit portal (each record's summary and contacts, read Nov. 10, 2026) and in ATI's records, the event pages and ENR coverage that identify Building 33 as the Microsoft Conference Center, the city's Microsoft campus refresh page, each firm's own website for its main line, and the same firms' other permits in Redmond, Seattle and Everett in ATI's records. A row is on the list only if a permit ties it to the building or to one of its firms. We left every person's name, phone and email off the list and used company lines. First published Nov. 11, 2026. We'll update this page when the fire alarm and exterior applications are issued and when new permits name firms on the building.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 10, 2026- City of Redmond permit portal, ELEC-2026-07357
- City of Redmond permit portal, BLDG-2026-04972
- City of Redmond permit portal, BLDG-2026-03141
- PyData Seattle 2023, venue: Microsoft Conference Center
- ENR, Contractor of the Year: GLY Construction, Aug. 9, 2016
- City of Redmond, Microsoft Redmond Campus Refresh
- Sequoyah Electric, Contact Us
- GLY Construction, Contact
- Auburn Mechanical, Contact