What is Microsoft building in Mount Pleasant?
Microsoft calls Fairwater, in Mount Pleasant, the world's most powerful AI datacenter. Its first building fulfilled Microsoft's initial $3.3 billion pledge and was finished and fully operational by June 2026. In September 2025 Microsoft committed $4 billion more for a second datacenter of similar size next door, bringing its Wisconsin investment to more than $7 billion; that building is in foundations and steel and is due in 2028.
Microsoft says it expects to spend $4.7 billion locally on construction in Wisconsin from 2024 to 2028, and that it has bought directly from 29 Wisconsin businesses, which it has not named.
Who gets what?
No one has published the campus's trade split. By the math on Turner & Townsend's data center cost index, about $1.9 billion of the second building's $4 billion is electrical work and about $1.3 billion is pipes, heat and air.
Which firms are on the job?
Walsh Construction is the general contractor on the Fairwater buildings and Kiewit on Microsoft's MKE16/17 site at County Roads KR and H. Dewberry Engineers filed the Area II site plan, and Stantec prepared Microsoft's state air permit applications. We Energies built the substation on the first parcel and works with American Transmission Co. on the power. The air permits name the equipment makers: Cummins and Caterpillar generators, Clarke fire pump engines and MIRATECH emissions controls. FODS supplied the site's trackout mats. No page we could open names an electrical, mechanical or steel subcontractor. 11 firms in all are on the list below.
How do the ways into Microsoft's Fairwater campus compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Microsoft's Fairwater campus | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after Microsoft's Fairwater campus?
| Electrical distributors and gear reps | Walsh's second building and Kiewit's MKE16/17, with We Energies and ATC on the power. |
|---|
| Generator and power equipment reps | Cummins, Caterpillar and MIRATECH units across the campus. |
|---|
| Fire protection suppliers | Clarke fire pump engines on the campus's water fire pumps. |
|---|
What should you do next on Microsoft's Fairwater campus?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Microsoft's Fairwater campus.
Questions people ask about Microsoft's Fairwater campus
How much is Microsoft's Fairwater datacenter?
$3.3 billion for the first building plus $4 billion for the second, more than $7 billion, per Microsoft.
Who is building Microsoft's Mount Pleasant datacenter?
Walsh Construction on the Fairwater buildings and Kiewit on the MKE16/17 site. 11 firms are named in all, listed above.
Is Fairwater finished?
The first building was fully operational by June 2026; the second is due in 2028.
How we built this list
We read Microsoft's announcements and project update page, the Racine County EDC's plan commission notes, Urban Milwaukee and Wisconsin DNR's air permit applications, and kept each firm a page or filing names on this campus (read Nov. 17, 2026). Equipment makers are named from the air permits. The trade split is the math on Turner & Townsend's published data center shares, applied to the second building. Phones are each firm's own office line. First published Nov. 17, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.