Who's building Microsoft's data centers in Mecklenburg County, Virginia

Microsoft just filed for five more data center buildings on 316.7 acres in Mecklenburg County, Virginia, where it had invested nearly $2 billion by 2015.

By Porter Stanley. Updated .

Microsoft has filed for a new data center campus, LVL-16, near Boydton in Mecklenburg County, Virginia: five single-story buildings, a substation, water storage and stormwater ponds on about 316.7 acres, reported Nov. 20, 2026. No cost, size or builder is given for it yet. Microsoft is already building on at least six other sites in the county. On Nov. 4, 2026, HITT Contracting asked the state to move the stormwater permit for Microsoft's AVC19 auxiliary site in Clarksville into its name. Four builders hold state permits on Microsoft sites now: HITT, Skanska, Clayco and Weitz. Virginia's 2018 incentive award for one Microsoft expansion here lists $1,066,755,918 in expected capital investment. 10 firms are named on the job; the list below has all 10.

$1.07BExpected investment, one 2018 expansion (state award)
316.7Acres in the new LVL-16 filing
4Builders with state permits on Microsoft sites now
10Firms named on the job

Get all 10 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 10 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 10 firms on Microsoft's Mecklenburg data centers?

We list the 10 firms named on Microsoft's data center build-out in Mecklenburg County, Virginia, one row each, strongest tie first, with what each one does on the job and where its name comes from.

1Permit on the recordNov 4, 2026

HITT Contracting Inc.

Builder and state stormwater permit holder on Microsoft's AVC17 site in Clarksville, the AVC19 auxiliary site (its filing to take over the permit dated Nov. 4, 2026), LYH03 in Chase City, AVC01 in South Hill and the LVL site on Prison Rd, Boydton on Microsoft's data center build-out in Mecklenburg County, VA

Microsoft AVC19 auxiliary site, 11800 US Hwy 58, Clarksville; AVC17, 170 Commerce Dr, Clarksville; LYH03, 8975 Hwy 92, Chase City (Mecklenburg County), VA

State construction stormwater registration VAR10W912, Microsoft AVC19 Data Center Auxiliary Site, 12.75 acres: registered by Microsoft Mar. 24, 2026, HITT's transfer filing received Nov. 4, 2026; AVC17 registration modification (151.99 acres) filed Oct. 5, 2026; LYH03 covers 258.73 acres; no dollar value stated

Work: Builder and state stormwater permit holder on Microsoft's AVC17 site in Clarksville, the AVC19 auxiliary site (its filing to take over the permit dated Nov. 4, 2026), LYH03 in Chase City, AVC01 in South Hill and the LVL site on Prison Rd, Boydton

Who to call: HITT Contracting Inc.
HITT Contracting office line
(Falls Church, VA)
(703) 846-9000

The opportunity: State records: 'Microsoft AVC19 Data Center Auxiliary Site, 11800 US Hwy 58 Clarksville, HITT Contracting Inc, 12.75 acres, received 2026-11-04' (a transfer filing on the permit Microsoft registered in March 2026; construction parking). HITT took over AVC17 from Ames Construction in August 2024 and LYH03 in December 2025. Its permits also cover AVC01 (210 Tunstall Dr, South Hill) and the LVL site on Prison Rd. Permits VAR10W912, VAR10T165, VAR10S103, VAR10Q324, VAR10M336.

2Permit on the recordMay 29, 2026

Skanska USA Building Inc.

Builder and state stormwater permit holder on Microsoft's AVC09 site (American Industrial Dr, South Hill, 157 acres) and AVC43 site (260 Butts St, South Hill, 107 acres) on Microsoft's data center build-out in Mecklenburg County, VA

Microsoft AVC09, American Industrial Dr, and AVC43, 260 Butts St, South Hill (Mecklenburg County), VA

State construction stormwater registration VAR10Q189, AVC09 Data Center, 157.1 acres, changed May 29, 2026; AVC43 registration VAR10S447, 107.32 acres, changed Apr. 8, 2026; no dollar value stated

Work: Builder and state stormwater permit holder on Microsoft's AVC09 site (American Industrial Dr, South Hill, 157 acres) and AVC43 site (260 Butts St, South Hill, 107 acres)

Who to call: Skanska USA Building Inc.
Skanska USA Building office line
(Arlington, VA)
(202) 777-8600

The opportunity: State records: 'AVC09 Data Center, American Industrial Drive South Hill, Skanska USA Building Inc, 157.1 acres.' AVC43 moved from Glover Construction to Skanska on July 19, 2024. Durham, NC office: (919) 941-7900.

3Permit on the recordMay 6, 2026

Clayco Inc.

Builder and state stormwater permit holder on Microsoft's LYH10 data center site on Highway 58 in Boydton (72 acres) on Microsoft's data center build-out in Mecklenburg County, VA

Microsoft LYH10, Highway 58, Boydton (Mecklenburg County), VA

State construction stormwater registration VAR10R556, LYH10 Data Center, 72.38 acres, changed May 6, 2026; no dollar value stated

Work: Builder and state stormwater permit holder on Microsoft's LYH10 data center site on Highway 58 in Boydton (72 acres)

Who to call: Clayco Inc.
Clayco office line
(St. Louis, MO)
(314) 429-5100

The opportunity: State records: 'LYH10 Data Center, Highway 58 Boydton, Clayco Inc, 72.38 acres.' The permit moved from Microsoft Corporation to Clayco on Oct. 11, 2023. Chicago office: 312-658-0747.

What is Microsoft building in Mecklenburg County, Virginia?

Microsoft has filed for a new data center campus called LVL-16 near Boydton. The plans show five single-story data center buildings, an electrical substation, water storage and stormwater ponds on about 316.7 acres. The site is north of Phillis Road, east of Rose Hill Road and south of the Tobacco Heritage Trail. The filing was reported on Nov. 20, 2026.

LVL-16 grows Microsoft's LVL campus off Ridge Road in Boydton, where Weitz is the builder. Microsoft has also filed federal permit plans for AVC22, three buildings on about 490 acres next to its AVC17 site in Clarksville. And on Sept. 29, 2026, Microsoft filed a state stormwater permit for a 370-acre site called CXE01.

How much is Microsoft spending in Mecklenburg County?

No cost has been given for LVL-16. Virginia's incentive record gives a figure for one earlier step: its 2018 Commonwealth's Development Opportunity Fund award to Microsoft in Mecklenburg lists $1,066,755,918 in expected capital investment and 108 jobs, with a $1.5 million state grant; the state announced it in January 2019 as Microsoft's sixth expansion in the county. That covers one expansion, not the new campus.

Expansions from 2010 through 2015 brought Microsoft's total investment in the county to nearly $2 billion. That was before the AVC, LYH and newer LVL campuses now being built.

Microsoft says building its new Virginia data centers will take about 5,190 construction jobs and 21.2 million hours. That is for the whole state, not Mecklenburg alone.

What is the newest filing on Microsoft's Mecklenburg sites?

On Nov. 4, 2026, HITT Contracting filed to take over the state construction stormwater permit for the 'Microsoft AVC19 Data Center Auxiliary Site' at 11800 US Hwy 58 in Clarksville. Microsoft registered the site in March 2026; it covers 12.75 acres of construction parking.

Other Microsoft sites had their state permits changed this year: AVC17 in October, AVC09 and LYH10 in May, AVC43 in April and the LVL campus in January. Weitz's own page shows a data center hall it is building in Boydton, for a client it does not name, due in March 2027.

Who is building Microsoft's data centers in Mecklenburg County?

Four builders hold state stormwater permits on Microsoft sites now. HITT Contracting has AVC17 in Clarksville and has filed to take over the AVC19 auxiliary site there, LYH03 in Chase City, AVC01 in South Hill and an LVL site on Prison Road. Skanska has AVC09 and AVC43 in South Hill. Clayco has LYH10 on Highway 58 in Boydton. Weitz has the LVL campus off Ridge Road, the one LVL-16 grows.

Timmons Group has worked as Microsoft's consulting engineers on the Clarksville site. Four firms worked earlier phases: Walbridge Aldinger on LVL until June 2025, Ames Construction on LYH03 and AVC17 until HITT took over, Glover Construction on AVC43 until July 2024, and Turner on Microsoft's first Herbert Drive campus until August 2024.

Who is bringing power to Microsoft's Mecklenburg campuses?

Dominion Energy built the Microsoft Hillcrest Substation in South Hill. It is now building two 18.3-mile 230 kV lines from Finneywood to a new Jeffress station, about $134.7 million in 2023 dollars, to serve a data center campus at Lakeside that could reach 240 MW.

Dominion's filing does not name the customer: the local electric co-op asked for the hookup for one of its data center customers. Microsoft's AVC17 site is in Lakeside Commerce Park, but no record we read ties the lines to Microsoft by name. 10 firms in all are on the list below.

How do the ways into Microsoft's Mecklenburg data centers compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on Microsoft's Mecklenburg County data centersEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the four builders holding permits now
The new LVL-16 campusWatching for its builder on the state stormwater permitBuilders and site, concrete and power subcontractorsAn early call on five new data center buildingsNo builder, cost or size named yet

Who should go after Microsoft's Mecklenburg data centers?

Site, concrete and steel suppliersHITT, Skanska, Clayco and Weitz on sites from 72 to 280 acres, with the 316.7-acre LVL-16 campus next in line.
Electrical and power gear repsDominion's two 18.3-mile 230 kV lines, about $134.7 million, for a data center campus at Lakeside, and the builders fitting out data center halls like Weitz's 48 MW Boydton hall.
Engineering, survey and testing firmsTimmons Group, Microsoft's consulting engineers in Clarksville, and the builders filing new site permits.

What should you do next on Microsoft's Mecklenburg data centers?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on Microsoft's data center sites in Mecklenburg County, Virginia (Boydton, South Hill or Clarksville).
  3. Watch for the state stormwater permit on LVL-16, which will name its builder.

Questions people ask about Microsoft's Mecklenburg data centers

How much is Microsoft spending on data centers in Mecklenburg County?

No cost has been given for the new LVL-16 campus. Virginia's 2018 incentive award for one Microsoft expansion here lists $1,066,755,918 in expected capital investment. Expansions through 2015 brought Microsoft's total investment in the county to nearly $2 billion.

Is the new LVL-16 campus a $1 billion project?

We don't know. The $1,066,755,918 is the expected investment on Virginia's 2018 award for one earlier expansion. The LVL-16 filing gives no cost, size or power figure.

Who is building Microsoft's data centers in Mecklenburg County?

Four builders hold state stormwater permits on Microsoft sites now: HITT Contracting, Skanska, Clayco and Weitz. 10 firms are named on the job, listed above.

What is Microsoft's LVL-16 data center?

LVL-16 is Microsoft's new campus filing near Boydton: five single-story data center buildings, an electrical substation, water storage and stormwater ponds on about 316.7 acres. It grows Microsoft's LVL campus, where Weitz is the builder.

Where is the LVL-16 campus?

North of Phillis Road, east of Rose Hill Road and south of the Tobacco Heritage Trail, near Boydton in Mecklenburg County, Virginia.

What is the Microsoft AVC19 site in Clarksville?

Microsoft registered the 'Microsoft AVC19 Data Center Auxiliary Site' at 11800 US Hwy 58 in Clarksville with the state in March 2026: 12.75 acres of construction parking. On Nov. 4, 2026, HITT Contracting filed to take over its stormwater permit.

Where are Microsoft's data centers in Mecklenburg County?

In Boydton (the LVL campus off Ridge Road, LYH10 on Highway 58 and the first campus on Herbert Drive), South Hill (AVC09, AVC43 and AVC01), Clarksville (AVC17 and AVC19) and Chase City (LYH03).

Who builds the power lines for Microsoft in Mecklenburg County?

Dominion Energy. It built the Microsoft Hillcrest Substation in South Hill and is building two 18.3-mile 230 kV lines, about $134.7 million, for a 240 MW data center campus at Lakeside, where Microsoft's AVC17 site is; the filing names no customer.

How many construction jobs will Microsoft's Virginia data centers need?

Microsoft says about 5,190 construction jobs and 21.2 million hours for its new Virginia data centers. That is statewide, not Mecklenburg alone.

When will Microsoft's Boydton data center open?

Weitz's own page shows a 48 MW, 245,000 sq ft data center in Boydton, for a client it does not name, due in March 2027. Weitz holds the state permit on Microsoft's LVL campus in Boydton. No date is given for LVL-16.

What happens next on Microsoft's Mecklenburg data centers?

LVL-16 is at the permit stage, with no builder named. Watch for its state stormwater permit, which names the builder. We'll update this page when a new filing or firm appears.

How we built this list

We read Virginia DEQ's public construction stormwater permits (VAR10) for Mecklenburg County on Nov. 20, 2026, and kept each firm the state names as permit holder on a Microsoft site, with the date of its newest filing. We also read the LVL-16 filing news, Virginia's incentive record, Dominion's state utility filing, Weitz's project page, Microsoft's Virginia fact sheet and local news. The LVL-16 filing names only Microsoft, so the list covers Microsoft's whole active build-out in the county. Four firms (Walbridge Aldinger, Ames, Glover, Turner) are earlier phases, with their dates. Dominion is on the list for the Microsoft Hillcrest Substation, which state records name; its Lakeside lines name no customer. The two electric co-ops behind the Lakeside hookup are left out, because no record we read ties them to a Microsoft site. Left out: Microsoft itself (the owner), Mecklenburg County (offsite road and water work), firms on a finished 2014-2016 job, design firms not tied to this county, job postings with no named site, other power projects in the county, and a wetland bank. The $1,066,755,918 is one 2018 expansion's expected investment, not the LVL-16 cost. Phones are each firm's own office line from its own site; Clayco, Walbridge, Glover and Turner are head or main offices, Dominion's is a customer line, Timmons' line is its Richmond head office line as its own site lists it, and Ames' site blocked our reads, so we give its website only. First published Nov. 20, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 10 firms, free

All 10 firms on Microsoft's Mecklenburg data centers

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.