What is Microsoft building in West Des Moines?
Ginger West and Ginger East are two of Microsoft's data center campuses in West Des Moines, Iowa. Ginger West is at 11100 Booneville Rd, and Ginger East is at 1475 SE Maffitt Lake Rd. Three new buildings are going up now: DSM 44 and DSM 45 at Ginger West, and DSM 18 at Ginger East.
Older buildings on the same campuses, DSM 42 and DSM 43 at Ginger West and DSM 16 and DSM 17 at Ginger East, are finished or finishing. They are not part of this page's numbers.
How far along are Microsoft's West Des Moines data centers?
The city issued the DSM 44 building permit on Jan. 15, 2026, DSM 18 on March 19 and DSM 45 on April 8. Trade permits for electrical, pipes and site utilities followed through September. Microsoft says Ginger West is estimated to be finished by summer 2028 and Ginger East by mid-2028.
The newest issued permit is a Sept. 29, 2026 permit to Veit & Company for temporary sewer and water at Ginger East. Applications for EV chargers at both campuses were filed Nov. 4, 2026 and are not issued yet.
What is being bought on Microsoft's West Des Moines data centers?
The city's building permits for the three buildings add up to $1.575 billion, the sum: $385 million for DSM 44 (244,676 sq ft), $590 million for DSM 45 (194,962 sq ft) and $600 million for DSM 18 (191,080 sq ft). Each value is for a whole building, not one firm's share. Microsoft has not given a dollar figure on its own pages.
Two of the new buildings are smaller but pricier than the old ones, and DSM 44 is the same size at a higher value. DSM 42 and DSM 43 were 244,676 sq ft each on $374.5 million permits. Iowa DNR's air permit for Ginger West covers 126 diesel backup generators with Cummins engines, and West Des Moines Water Works says Microsoft has invested $25 million in its water system.
Who is building Microsoft's West Des Moines data centers?
Turner Construction is Microsoft's general contractor at Ginger West, and the contractor on the DSM 44 and DSM 45 building permits. The Weitz Company is the general contractor at Ginger East, and the contractor on the $600 million DSM 18 permit. Microsoft's own page calls it Weitz Construction.
Burns & McDonnell is the architect on all three building permits. Civil Design Advantage is the applicant on all three and the engineer on the DSM 18 permit.
Which trade firms are on Microsoft's West Des Moines data centers?
The city's trade permits name the firms doing the work. Baker Electric holds the electrical permits on DSM 44 and DSM 45, and EPI Power holds the one on DSM 18. The Waldinger Corporation has the DSM 18 chilled water permit and a plumbing permit at Ginger West.
McAninch Corp. has the site utilities permits at Ginger West, and Veit & Company has them at Ginger East. Cummins makes the generator engines in Ginger West's air permit. 10 firms in all are on the list below.
How do the ways into Microsoft's West Des Moines data centers compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Microsoft's West Des Moines data centers | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after Microsoft's West Des Moines data centers?
| Electrical distributors and gear reps | Baker Electric on DSM 44 and DSM 45, and EPI Power on DSM 18, on building permits worth up to $600 million each. |
|---|
| Mechanical, HVAC and plumbing reps | The Waldinger Corporation on the DSM 18 chilled water system and the Ginger West plumbing. |
|---|
| Site work, pipe and generator suppliers | McAninch Corp. and Veit & Company on site utilities; Cummins engines in the 126 permitted backup generators. |
|---|
What should you do next on Microsoft's West Des Moines data centers?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Microsoft's Ginger West or Ginger East data center in West Des Moines.
Questions people ask about Microsoft's West Des Moines data centers
How much are Microsoft's West Des Moines data centers?
Microsoft has not given a dollar figure on its own pages. The three buildings now under construction carry city building permits of $385 million (DSM 44), $590 million (DSM 45) and $600 million (DSM 18). That is $1.575 billion, the sum. Each value is for a whole building, not one firm's share.
Who is building Microsoft's data centers in West Des Moines?
Turner Construction is Microsoft's general contractor at Ginger West, on DSM 44 and DSM 45. The Weitz Company is the general contractor at Ginger East, on DSM 18. 10 firms are named on the job, listed above.
Where are Microsoft's West Des Moines data centers?
Ginger West is at 11100 Booneville Rd and Ginger East is at 1475 SE Maffitt Lake Rd, both in West Des Moines, Iowa.
What is the biggest permit on Microsoft's West Des Moines campuses?
DSM 18 at Ginger East. The city issued its building permit, COMM-067689-2025, on March 19, 2026, valued at $600 million for a 191,080 sq ft building. The Weitz Company is the contractor.
When will Microsoft's West Des Moines data centers be finished?
Microsoft says Ginger West is estimated to be finished by summer 2028 and Ginger East by mid-2028.
How many backup generators does Ginger West have?
Iowa DNR's Title V air permit for Ginger West, signed April 10, 2026, covers 126 diesel backup generators with Cummins engines. The permit covers the whole campus, not only the new buildings.
Who does the electrical work on Microsoft's West Des Moines data centers?
Baker Electric holds the electrical permits on DSM 44 and DSM 45 at Ginger West. EPI Power holds the electrical permit on DSM 18 at Ginger East, with Weitz as contractor.
Who does the mechanical and plumbing work?
The Waldinger Corporation holds the permit for the DSM 18 chilled water system at Ginger East, issued May 22, 2026, and a plumbing permit at Ginger West, issued June 22, 2026.
Why are the new buildings permitted at more than the old ones?
The city's permits show higher values on the new buildings: DSM 44 is the same 244,676 sq ft as the older ones on a $385 million permit, and DSM 45 is 194,962 sq ft on a $590 million permit. DSM 42 and DSM 43 were 244,676 sq ft each on $374.5 million permits. The older buildings are not in our $1.575 billion sum.
Does Microsoft pay for water in West Des Moines?
West Des Moines Water Works says Microsoft has invested $25 million in its water system.
What is the newest permit on Microsoft's West Des Moines campuses?
On Sept. 29, 2026, the city issued Veit & Company a permit for temporary sewer and water at Ginger East. Applications for EV chargers at both campuses were filed Nov. 4, 2026 and are not issued yet.
What happens next on Microsoft's West Des Moines data centers?
DSM 44, DSM 45 and DSM 18 are under construction, with trade permits still coming in. Microsoft estimates both campuses will be finished in 2028. We'll update this page when a new permit or firm appears.
How we built this list
We read the City of West Des Moines' public EnerGov permit records on Nov. 19, 2026, searching 11100 Booneville Rd, 1475 SE Maffitt Lake Rd, Microsoft and the building numbers, and read the summaries and contacts on 33 permits. We also read Microsoft's Ginger West and Ginger East pages, Iowa DNR's Title V air permit for Ginger West, Business Record and West Des Moines Water Works, and kept each firm a permit or Microsoft names on these campuses. A permit's value is for the whole building, not one firm's share; trade permits show no value on the public record; and the $1.575 billion is the sum of three building permits. Left out: a design firm on pending EV-charger applications (not issued), the power utility and an equipment rental firm, which no record ties to these campuses, and individuals on the permits. Phones are each firm's own office line; Burns & McDonnell's is its Kansas City main line, and we found no office line on Cummins' site. First published Nov. 19, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 19, 2026- Microsoft Local: Ginger West datacenter construction update (read Nov. 19, 2026)
- Microsoft Local: Ginger East datacenter construction update (read Nov. 19, 2026)
- City of West Des Moines Citizen Self Service permit records (EnerGov), read Nov. 19, 2026
- Business Record: projects issued building permits in April (May 13, 2026)
- Iowa DNR Title V operating permit 26-TV-003, Ginger West Data Center (April 10, 2026)
- West Des Moines Water Works: Just the Facts, Data Centers & Water (June 1, 2026)