What is being built to replace the Port Authority Bus Terminal?
The Port Authority Bus Terminal at 625 Eighth Avenue in Midtown Manhattan is the busiest bus terminal in the world, per the Port Authority More than 200,000 riders use it every day. The Port Authority of New York and New Jersey owns it and is replacing it while buses keep running.
Phase 1 builds 3.5 acres of decks over Dyer Avenue, a seven-level interim terminal between Ninth and Tenth Avenues, and new ramps to the Lincoln Tunnel. The interim terminal is 900,000 sq ft and holds 350 buses indoors. Phase 2 is a new main terminal of about 2.1 million sq ft on the old site. After that, the Dyer Avenue decks become 3.5 acres of public green space.
How much will the new Midtown Bus Terminal cost?
News coverage of the Port Authority's 2027 budget, released Nov. 12, 2026, calls it a $10 billion replacement. Some news reports now say about $11 billion. These are estimates, not money spent.
On June 26, 2025, the Port Authority board approved Phase 1 at a revised total of up to $4.8 billion, with construction up to $3.554 billion. Among its reasons, the board named the small number of proposers for a job this size. The board authorized a federal TIFIA loan in December 2024; the loan, about $1.89 billion, closed in January 2025. Phase 2 is not yet approved; on June 23, 2026 the board added $20 million to the $40.2 million for its planning, to bring the design within the capital plan budget.
How far along is the Midtown Bus Terminal replacement?
The deck-overs started in May 2025 and are due to finish in 2027. Crews placed the final concrete on the latest deck section on Oct. 24, 2026. The day before, Port Authority chairman Kevin O'Toole and executive director Kathryn Garcia toured the new decks and the torn-down ramp site where the storage building will rise.
Steel columns for the new ramps are the first part of the rebuild above ground. The ramp caissons go 50 to 60 feet deep. Bus reroutes for the Lincoln Tunnel ramp work began Oct. 15, 2026, and riders were warned of years of delays. The interim terminal is due in 2030, and news reports say the work will not be done until 2035.
Who is building the Midtown Bus Terminal?
Tutor Perini Corporation holds the biggest contract: a $1.871 billion guaranteed maximum price for the core and shell of the interim terminal and all of the new ramps, awarded June 26, 2025. MLJ Contracting is building the $271 million deck-overs, and AECOM Tishman manages that work.
A joint venture of STV and Turner was picked in May 2026 to manage Phase 1 construction through 2030. The Louis Berger/HNTB joint venture runs program management, WSP USA handles engineering, and Foster + Partners with Epstein is the architect.
Which trade firms are on the Midtown Bus Terminal, and what comes next?
Banker Steel won the structural steel package for the new ramps, 26,500 tons, with its subsidiary NYC Constructors as erector. JGM is making about 6,200 tons of plate girders, diaphragms and bracing for it, about 23% of the ramp steel by the math. Five Star Electric, a Tutor Perini company, won the GMP01 electrical package: temporary light, power and signals, power distribution, duct bank, grounding, fire alarm, lighting and more.
The board's 2025 approval says mechanical, electrical, plumbing, finishes and facades come later as separate packages, and any over $75 million goes to a board committee. We found no named concrete, foundation or mechanical subcontractor yet. The Port Authority's board votes on the 2027 budget on Dec. 17, 2026.
Who the Port Authority hired before
The Port Authority keeps going back to Tutor Perini: the same builder that is putting up the interim bus terminal is also building the new AirTrain at Newark, in a joint venture with O&G, and got a sole-source add-on there this June.
- Tutor Perini/O&G (joint venture): builder on Newark AirTrain replacement guideway and stations, plus the Terminal B AirTrain station core and shell ($132M add-on), Newark, NJ, 2026. Also on this job.
- Perfetto Contracting Co. Inc.: builder on Dyer Avenue and 30th Street intersection realignment and bus staging lot expansion at the Lincoln Tunnel ($13.6M), Manhattan, NY, 2026.
- HDR Engineering, Inc.: engineer on Lincoln Tunnel Helix structural rehabilitation and repaving, planning and design ($20.9M), Weehawken, NJ, 2026.
- VRH Construction Corporation: builder on Newark Terminal B baggage screening system replacement ($33.5M), Newark, NJ, 2026.
These are earlier or other jobs for the same owner. They are not counted in the 14 firms on this job.
How do the ways into the Midtown Bus Terminal replacement compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Midtown Bus Terminal replacement | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The packages still to come | A place on a team for the later mechanical, electrical, plumbing, finishes and facade packages | Trade contractors and their suppliers | A share of the $1.871 billion Tutor Perini contract | No dates or values published yet; the Port Authority does not publish awards below board level |
Who should go after the Midtown Bus Terminal replacement?
| Steel, crane and foundation suppliers | Tutor Perini's ramp foundations and 26,500 tons of ramp steel (Banker Steel, JGM, NYC Constructors). |
|---|
| Electrical, mechanical and plumbing firms | Five Star Electric's GMP01 package now, and the later mechanical, electrical, plumbing, finishes and facade packages under Tutor Perini. |
|---|
| Not a fit yet | Firms hoping to bid the new main terminal (Phase 2): it is still in design and not yet approved by the board. |
|---|
What should you do next on the Midtown Bus Terminal replacement?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the Midtown Bus Terminal replacement in Manhattan.
- Watch the Port Authority board's Dec. 17, 2026 budget vote and its later package awards under Tutor Perini.
Questions people ask about the Midtown Bus Terminal replacement
How much will the new Port Authority Bus Terminal cost?
News coverage of the Port Authority's 2027 budget calls it a $10 billion replacement; some news reports say about $11 billion. Phase 1 is approved at up to $4.8 billion. These are estimates, not money spent.
Who is building the new Midtown Bus Terminal?
Tutor Perini Corporation holds the biggest contract, $1.871 billion, for the interim terminal and all new ramps. MLJ Contracting builds the deck-overs over Dyer Avenue. 14 firms are named on the job, listed above.
Who is the construction manager on the Midtown Bus Terminal?
A joint venture of STV and Turner manages Phase 1 construction, picked in May 2026, through 2030. AECOM Tishman manages the Dyer Avenue deck-overs.
When will the new Midtown Bus Terminal open?
The interim terminal is due in 2030, and news reports say the work will not be done until 2035. The deck-overs are due to finish in 2027.
Is the Port Authority Bus Terminal still open during construction?
Yes. Over 200,000 riders a day keep using the old terminal. Bus reroutes for the Lincoln Tunnel ramp work started Oct. 15, 2026, and riders were warned of years of delays.
What is being built in Phase 1?
3.5 acres of decks over Dyer Avenue, a seven-level, 900,000 sq ft interim terminal for 350 buses between Ninth and Tenth Avenues, and new ramps to the Lincoln Tunnel.
Who is making the steel for the new bus terminal ramps?
Banker Steel has the 26,500-ton structural steel package for the helix of new ramps. JGM makes about 6,200 tons of it, and NYC Constructors erects it.
Who is doing the electrical work on the Midtown Bus Terminal?
Five Star Electric, a Tutor Perini company, won the GMP01 electrical package in February 2026: temporary light, power and signals, power distribution, duct bank, grounding, fire alarm, lighting and more.
How can subcontractors get on the Midtown Bus Terminal?
Call the firms already on the job, starting with Tutor Perini. The board says mechanical, electrical, plumbing, finishes and facades come later as separate packages under Tutor Perini's contract.
Who designed the new Midtown Bus Terminal?
Foster + Partners with Epstein is the architect, WSP USA is the engineer, and the Louis Berger/HNTB joint venture runs program management. The board funded more Phase 2 design on June 23, 2026.
What are the risks on the Midtown Bus Terminal project?
Cost: Phase 1 was raised to $4.8 billion and the board noted few proposers for a job this size. Phase 2, the main terminal, is not yet approved and its design is being trimmed to fit the budget.
What happens next on the Midtown Bus Terminal?
Public comments on the Port Authority's 2027 budget close Dec. 15, 2026, and the board votes Dec. 17. Deck work finishes in 2027. We'll update this page when a new contract or firm appears.
How we built this list
We read the Port Authority board's public agendas of June 26, 2025 and June 23, 2026, news coverage of the Port Authority's 2027 budget, other news reports, Turner's and Tutor Perini's releases, and the firms' own project pages, all on Nov. 23, 2026. We kept each firm a public record names on this project. STV and Turner are listed apart, as partners in one joint venture. Contract values for joint ventures are for the whole team. Left out: the owner, the federal lender, a team that proposed but did not win, roof-repair permits on the old terminal, firms named only on 2015 planning, and a crane company seen only in site photos. NYC building records do not cover Port Authority work, and the Port Authority does not publish awards below board level, so we found no concrete, foundation or mechanical subcontractor yet. Phones are each firm's own main or office line from its own site; Tutor Perini, Banker Steel and Epstein are head offices. We found no main line on AECOM Tishman's, WSP's, Foster + Partners' or HNTB's sites, so we give their websites only. First published Nov. 23, 2026. We'll update this page when a new contract, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 23, 2026- Construction Dive: Port Authority proposes $10.3B budget for NYC-area projects (Nov. 17, 2026)
- Construction Owners: Port Authority proposes $10.3B 2027 budget (what it funds at the bus terminal)
- ENR: $11B makeover of Manhattan bus terminal advances with concrete deck installation (Oct. 26, 2026)
- amNY: Midtown Bus Terminal traffic delays starting (Oct. 14, 2026)
- Port Authority Board public agenda (June 23, 2026)
- Turner Construction: STV-Turner selected for first phase of Midtown Bus Terminal replacement (May 18, 2026)
- ENR: STV-Turner JV to oversee Midtown Manhattan bus terminal Phase 1 work (May 20, 2026)
- Banker Steel: New project award, the Midtown Bus Terminal replacement (March 31, 2026)
- Five Star Electric: Midtown Bus Terminal Redevelopment Program GMP01 (Feb. 27, 2026)
- JGM: Midtown Manhattan Bus Terminal helix ramp with Banker Steel
- Port Authority Board public agenda (June 26, 2025)
- Tutor Perini: $1.871 billion staging and storage facility and ramp structure award (June 30, 2025)
- Tutor Perini: subcontractor page for the staging and storage facility and ramps
- ENR: Port Authority picks contractors for first phase of $10B NYC bus terminal replacement (July 30, 2024)
- AKRF: Port Authority Bus Terminal replacement project page
- New York Construction Report: U.S. DOT announces $1.89 billion loan for the Midtown Bus Terminal (Jan. 17, 2025)
- Port Authority Flickr: Dyer Avenue deck-over site visit photos (Oct. 23, 2026)