What is Nebius building in Birmingham?
Nebius, an AI cloud company, is building a 300-megawatt data center it calls BHM01 off Lakeshore Parkway in Birmingham (BirminghamWatch). It sits on 75 acres at 201 Milan Parkway, where the old Regions Lakeshore Operations Center stood (Nebius). Green Circle Demolition took that building down under a city permit issued Jan. 7, 2026.
There are two buildings. Phase 1, which the permits call "First Light", is about 131,609 square feet on its master permit. Phase 2 is a two story steel building of 367,056 square feet, 75 feet high (City of Birmingham). Nebius says first power-up is planned for late 2026 with build-out through 2028, and on Nov. 12 it told shareholders it expects Alabama to deploy capacity in 2027 (Nebius Q3 letter).
It is moving fast. A drone video from Oct. 18 showed the first building's slab poured, a steel spine and pipe rack up, and a row of transformers set (AAIG). The city issued the mechanical permit on Nov. 12 and the fire sprinkler permit for First Light on Nov. 17 (City of Birmingham).
How much is the Nebius data center worth?
Nebius has not given a number. It says the first phase is "a multi-billion-dollar investment" (Nebius). The hard numbers are on the city's permits. Hoar Construction's phase 2 shell permit states $2,043,840,211, and the phase 1 master permit states $844.25 million (City of Birmingham).
All 21 city permits on the site add up to about $3.67 billion. Some of that may count the same work twice, because a master permit and the trade permits under it can overlap. The trade permits are big on their own: $315 million for electrical work (Marathon) and $303.1 million for mechanical work (Batchelor & Kimball).
The $35.9 billion you may see is not a building cost. It is the Industrial Development Board's projection of what Nebius will invest at the site over 30 years, equipment included (WBRC/FOX10). Nebius has not published a trade split, so the city's own electrical and mechanical permits above are the best guide.
Why are people suing over the Nebius data center?
On May 29, 2026 Birmingham's Industrial Development Board voted 6-0 for $3.234 billion in tax breaks over 30 years (BirminghamWatch). In June, two plaintiffs filed a new lawsuit against Lakeshore Data Center, Hoar Construction, Nebius and the city over the project (BirminghamWatch, June 29, 2026).
The city council passed a moratorium on new data centers on March 3, 2026, but it did not cover Nebius, which had asked for its permit on Jan. 7 and was already in the permit process (BirminghamWatch). The work has gone on through the fight: the city has issued permits on the site from January to this week.
Which firms are on the job?
Hoar Construction of Birmingham is the general contractor on the demolition, foundation, steel, both building shells and 55 acres of underground utilities (City of Birmingham). Marathon Electrical Contractors of Irondale holds the $315 million electrical permit and the fire alarm work. Batchelor & Kimball of Conyers, Georgia, holds the $303.1 million mechanical permit, and ART Plumbing of Smyrna, Georgia, the $11.9 million plumbing permit.
EPC Services Company builds the 230-34.5 kV substation on site under a $51.8 million permit. CS Beatty Construction does site work and the Sand Ridge switching substation pad, and B & H Contracting is putting in fire hydrants and water taps. CHA Fire Protection holds the sprinkler permit issued Nov. 17, Fiber Tech Industries bored in fiber, Alabama Power will own the new power stations, and Affiliated Engineers did the sound study (Nebius).
12 firms in all are named on the list below, each with its main office line.
How do the ways into the Nebius Birmingham data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Nebius Birmingham data center | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Nebius Birmingham data center?
| Electrical distributors and gear reps | Marathon Electrical's $315 million electrical permit, EPC Services' on-site substation and the transformers already set in the yard. |
|---|
| Mechanical, HVAC and plumbing reps | Batchelor & Kimball's $303.1 million permit for all mechanical equipment and piping, issued Nov. 12, and ART Plumbing's plumbing work. |
|---|
| Fire protection, site and utility suppliers | CHA Fire Protection's sprinklers, Marathon's fire alarm system, and the site and water work by CS Beatty and B & H Contracting. |
|---|
What should you do next on the Nebius Birmingham data center?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the Nebius Birmingham data center.
Questions people ask about the Nebius Birmingham data center
How much is the Nebius data center in Birmingham?
Nebius calls the first phase a multi-billion-dollar investment but gives no number. The city's phase 2 shell permit states $2.04 billion, and all 21 city permits add up to about $3.67 billion, though some may overlap.
Who is building the Nebius data center in Birmingham?
Hoar Construction of Birmingham is the general contractor. 12 firms are named in all, listed above.
Where is the Nebius data center in Birmingham?
At 201 Milan Parkway, off Lakeshore Parkway in the Oxmoor area of Birmingham, Jefferson County, Alabama, on the old Regions Lakeshore Operations Center site.
Is the Nebius data center a $35.9 billion project?
No. $35.9 billion is the Industrial Development Board's projection of what Nebius will invest over 30 years (WBRC/FOX10), not the cost to build.
Who is the mechanical contractor on the Nebius data center?
Batchelor & Kimball, Inc. The city issued it a $303.1 million permit for all mechanical equipment and piping on Nov. 12, 2026.
Why is the Nebius data center being sued?
Two plaintiffs sued Lakeshore Data Center, Hoar Construction, Nebius and the city of Birmingham in June 2026 (BirminghamWatch), after the IDB approved $3.234 billion in tax breaks.
How we built this list
We read every City of Birmingham permit record we found on the Nebius site, about 28 once zoning letters are left out, from January 6 to November 17, 2026 (the dollar sum below covers the 21 we read first), on each record's own public page, and kept the contractor and contract value each one states. We added EPA stormwater notices for the site, Nebius's Birmingham page and Q3 shareholder letter, and the news. DPR Construction spoke for the project at a March zoning hearing, but no source states its role and no permit names it, so it is left out; so is Core Logic, named only on a driveway permit with no contractor. The permit values may overlap between the master permit and its trade permits, so we do not add them up as a cost. We give the trade money from the city's own trade permits rather than a typical split. Phones are each firm's own office line where it publishes one; for CS Beatty, B & H Contracting and Fiber Tech the line comes from a directory or the permit. First published Nov. 18, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 18, 2026- Nebius: Birmingham, AL project page (read Nov. 17, 2026)
- Nebius Q3 2026 shareholder letter (Nov. 12, 2026)
- BirminghamWatch: New lawsuit against Nebius data center challenges validity of regs and decisions (June 29, 2026)
- BirminghamWatch: Battle against Oxmoor Valley data center fizzles, but residents left with concerns (April 24, 2026)
- WBRC/FOX10: Birmingham mayor says city didn't give Nebius data center tax breaks (June 27, 2026)
- AAIG Research: technical series on the Nebius Birmingham build, citing Fred Britt's Oct. 18 drone video (Nov. 11, 2026)
- City of Birmingham permit BLD2026-00724: phase 2 shell, Hoar Construction, $2,043,840,211 (issued April 27, 2026)
- City of Birmingham permit BLD2026-00036: phase 1 master permit, Hoar Construction, $844,250,000 (issued April 27, 2026)
- City of Birmingham permit ELE2026-00878: electrical, Marathon Electrical Contractors, $315,000,000 (issued April 28, 2026)
- City of Birmingham permit BLD2026-00780: 230-34.5 kV substation, EPC Services Company, $51,846,788 (issued June 3, 2026)
- City of Birmingham permit search (MEC2026-00852 mechanical, Batchelor & Kimball, issued Nov. 12, 2026; FPT2026-00380 sprinklers, issued Nov. 17, 2026)