What is being built at the Vineland data center?
DataOne is building an AI data center campus for Nebius at 3963 S Lincoln Ave, the southeast corner of Lincoln and Sheridan Avenues in Vineland, Cumberland County, New Jersey. The site is about 106 acres. Nebius rents it to serve its capacity contract with Microsoft.
The first building, 129,622 sq ft, is up. The city's Aug. 5, 2026 Planning Board agenda lists a 587,980 sq ft two-story expansion, 293,990 sq ft a floor, "currently under construction." Together that is 717,602 sq ft.
The plan also shows nine fuel-cell power areas, a 92,466 sq ft chiller building, 161,896 sq ft of Megabay structures, an 8,660 sq ft LNG tank and filling station, a 6,750 sq ft water treatment plant and a 27-million-gallon reservoir. Nebius says the job brings about 1,000 construction jobs and about 200 permanent jobs.
How much is the Nebius Vineland data center?
No one has published a cost to build. Nebius's contract with Microsoft is $17.4 billion over five years, up to $19.4 billion, through 2031. That is what Microsoft pays Nebius for AI capacity, not what the buildings cost.
The biggest construction-side figure is power: a $1.7 billion investment in Bloom Energy fuel cells for Nebius, announced July 16, 2026, which reports tie to this site. Bloom's fees are reported at up to $2.6 billion over the term.
New Jersey's construction permit records show 22 permits at 3963 S Lincoln Ave from March 10 to Oct. 1, 2026. Their stated values add up to $63.0 million, the sum. Ten of them are $5,000,000 each, labeled "Alteration of storage building," issued Sept. 17 to 25. The newest, 26-1214, is a $3,000,000 new business building permit issued Oct. 1. The state feed names no contractor.
Why is the Vineland data center a fight?
Neighbors say the site is too loud. In a ruling reported Nov. 20, 2026, Superior Court Judge James Swift refused to dismiss their noise class action. He rejected the defense's argument that the case would need "mini trials" for each household. DataOne must now answer the claims, and both sides begin exchanging evidence.
The power has been a fight too. On Sept. 22, 2026, New Jersey fined DataOne $1.07 million over 62 Caterpillar gas generators, 1,982 kW each, about 123 MW, run without air permits, found in a July 29 investigation. The order gave it 45 days to apply for permits.
In August the city issued two stop-construction orders: one on Aug. 6 over the LNG tank, and one on Aug. 10 over Bloom fuel cells put in before approval. The Planning Board approved the expansion 8-1 near midnight on Aug. 17. On Oct. 13, the group Sustain SJ sued the city to overturn that approval (CUM-L-000727-26).
How far along is the Nebius Vineland data center?
The first building is running in part, and the expansion is rising. Bloom said in late October 2026 that its first fuel-cell power block at Vineland was ready for use. In its Nov. 12 letter, Nebius said Bloom power is online and scaling over the next few weeks as the site moves off the temporary generators.
Nebius now expects to have delivered more than half of the capacity it owes Microsoft by the end of 2026, with the rest in the second quarter of 2027.
Who is building the Nebius Vineland data center?
Nebius says the campus is a build-to-suit by DataOne, "with construction led by Vineland-based Northeast Precast." City inspectors listed Northeast Precast as the site's agent in at least 17 inspections from May 2025 to April 2026. NE Consulting Services drew the revised site plan, and AKRF handled noise and permitting for DataOne.
Kiely Family of Companies built the temporary gas supply for the generator fleet, about 4,500 feet of 12-inch steel pipe. Bloom Energy installs and runs the fuel-cell plant, and Cashman Preload Cryogenics made the LNG tank. South Jersey Gas supplies the gas, and in March 2026 Vineland Municipal Utilities and Atlantic City Electric were named for about 15% of the power, from the grid. 10 firms in all are on the list below.
Who Nebius hired before
On its Birmingham, Alabama data center, Nebius's permits went to a handful of big Southeast trade firms. None of them is named in Vineland yet, where DataOne builds for Nebius.
- Hoar Construction: general contractor on Nebius BHM01 AI data center, phase 2 shell ($2.04B permit), Birmingham, AL, 2026.
- Marathon Electrical Contractors: electrical on Nebius BHM01 ($315M electrical permit), Birmingham, AL, 2026.
- Batchelor & Kimball, Inc.: mechanical on Nebius BHM01 ($303.1M mechanical permit), Birmingham, AL, 2026.
- EPC Services Company: substation on Nebius BHM01 230-34.5 kV substation ($51.8M permit), Birmingham, AL, 2026.
These are earlier or other jobs for the same owner. They are not counted in the 10 firms on this job.
How do the ways into the Vineland data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Nebius data center at 3963 S Lincoln Ave in Vineland | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Vineland data center?
| Concrete, steel and site suppliers | Northeast Precast, the Vineland precast maker leading construction on a 587,980 sq ft expansion, and Cashman Preload Cryogenics on the LNG tank. |
|---|
| Gas, power and mechanical reps | Kiely on the gas lines, Bloom Energy on 328 MW of fuel cells, South Jersey Gas, Atlantic City Electric and Vineland Municipal Utilities, plus a 92,466 sq ft chiller building. |
|---|
| Engineering and permitting firms | NE Consulting Services on the site plan and AKRF on noise and the state air permits. |
|---|
What should you do next on the Vineland data center?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the DataOne data center for Nebius at Lincoln and Sheridan Avenues in Vineland.
Questions people ask about the Vineland data center
How much is the Nebius data center in Vineland?
No one has published a cost to build. The campus serves Nebius's $17.4 billion AI capacity contract with Microsoft, which is a customer deal, not a building cost. A $1.7 billion fuel-cell power project for Nebius was announced July 16, 2026. The 22 state construction permits at the site add up to $63.0 million, the sum.
Who is building the Nebius data center in Vineland?
DataOne builds it for Nebius, and Nebius says Vineland-based Northeast Precast leads construction. Bloom Energy runs the fuel-cell power plant. 10 firms are named on the job, listed above.
Where is the Nebius Vineland data center?
At 3963 S Lincoln Ave, the southeast corner of Lincoln and Sheridan Avenues, Block 7503, Lots 35.01 and 33.01, in Vineland, Cumberland County, New Jersey, on about 106 acres.
How big is the Nebius Vineland data center?
The first building is 129,622 sq ft. The expansion is a 587,980 sq ft two-story building now under construction. Together that is 717,602 sq ft, with a 92,466 sq ft chiller building and a 27-million-gallon reservoir.
Why is the Vineland data center being sued?
Neighbors filed a noise class action. In a ruling reported Nov. 20, 2026, Judge James Swift refused to dismiss it, so both sides now exchange evidence. A local group, Sustain SJ, also sued the city on Oct. 13 to overturn the expansion's approval (CUM-L-000727-26).
Why was DataOne fined in Vineland?
On Sept. 22, 2026, New Jersey fined DataOne $1.07 million over 62 Caterpillar gas generators, about 123 MW, run without air permits. The order gave it 45 days to apply for permits.
How will the Vineland data center get power?
Mostly from Bloom Energy fuel cells on site, about 250 MW guaranteed and 328 MW installed, run on natural gas from South Jersey Gas. A March 2026 plan put about 15% on the grid, through Vineland Municipal Utilities and Atlantic City Electric.
When will the Nebius Vineland data center be done?
Nebius says it expects more than half of the Microsoft capacity delivered by the end of 2026, with the last pieces in the second quarter of 2027.
How many jobs will the Vineland data center create?
Nebius says about 1,000 construction jobs and about 200 permanent jobs on site.
What is the newest permit on the Vineland data center?
State permit 26-1214, a $3,000,000 new business building permit at 3963 S Lincoln Ave, issued Oct. 1, 2026.
How we built this list
We read Nebius's Vineland page and its Q3 2026 shareholder letter, the City of Vineland's Planning Board agenda and notice, New Jersey's construction permit records for 3963 S Lincoln Ave (through ATI's copy of the state feed), a citizen-suit notice filed Oct. 21, 2026, Kiely's case study, and news reports from WHYY, WVIA, ENR, South Jersey Climate News, The Vineland Voice, Blockspace and Hunterbrook, read Nov. 22, 2026. We kept each firm a record or the news names on this campus. Record dates are the date of the record or hearing that names the firm. The $63.0 million is the sum of the stated values on 22 state permits, not DataOne's spend; four more permits at 4081 S Lincoln Ave, next door, are not counted. Left out: the owner and its in-house construction arm (DataOne), the tenant (Nebius), the end customer (Microsoft), lawyers, lenders and investors, the board's own reviewers, the opponents' experts, a planner who testified as an individual, the fuel-cell project's developer and a generator rental firm that only one analyst report ties to the site, and a gas engine plan that was withdrawn. Phones are each firm's own main or office line from its own site; Cashman's is the Preload International line, and AKRF's is its New York head office. We read no phone from the sites of NE Consulting Services, Caterpillar or Atlantic City Electric, so we give their websites only. First published Nov. 22, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 22, 2026- Nebius: Vineland, NJ page (read Nov. 22, 2026)
- Yahoo Finance: Nebius secures $17.4bn agreement with Microsoft (Sept. 2025)
- Nebius Q3 2026 shareholder letter (Nov. 12, 2026)
- WHYY: Vineland data center noise lawsuit (updated Nov. 20, 2026)
- WVIA: Fight over Vineland data center noise stays alive (Nov. 21, 2026)
- ENR: NJ fines data center $1M over 123 MW of unpermitted generation (Sept. 23, 2026)
- ENR: Inside the Vineland data center power dispute (Sept. 23, 2026)
- City of Vineland Planning Board agenda, special meeting Aug. 5, 2026 (revised)
- City of Vineland Planning Board notice (March 2026)
- New Jersey DCA construction permit data
- WHYY: Vineland Planning Board approves data center plan (Aug. 18, 2026)
- WHYY: Vineland data center hearing on power generation (Aug. 6, 2026)
- WHYY: Data center in Vineland, New Jersey (Mar. 25, 2026)
- South Jersey Climate News: What exactly is DataOne building in Vineland?
- South Jersey Climate News: Sustain SJ sues Vineland over DataOne approval (Oct. 14, 2026)
- The Vineland Voice: Planning Board grants approval of DataOne application (Aug. 2026)
- The Vineland Voice: DataOne's six-hour Planning Board meeting (Aug. 2026)
- Sustain SJ notice of intent to sue DataOne (Oct. 21, 2026)
- Kiely Family of Companies: Vineland Data Center AI Campus
- Blockspace: Bloom Energy readies Nebius power (Oct. 2026)
- Hunterbrook: Vineland (Aug. 13, 2026)
- IDF and Oaktree: $1.7 billion investment in Bloom Energy fuel cells for Nebius (July 16, 2026)
- Nebius and Bloom Energy partner to power AI infrastructure build-out (May 20, 2026)
- City of Birmingham permit BLD2026-00724
- City of Birmingham permit ELE2026-00878
- City of Birmingham permit MEC2026-00852
- City of Birmingham permit BLD2026-00780