What's due Nov. 18 on the Northeast ECHS project?
S&P's public BuildingConnected page, "Northeast Early College High School GMP #3 Final", says "BID DATE: Wednesday November 18th, 2026 at 2 PM". Every package row on it reads 11/18/2026, 2:00 PM CST. Bids go by email to [email protected] on S&P's proposal form, priced by building, with 8 unit prices and 15 alternates.
The same date runs in S&P's notice in the Austin American-Statesman, published Nov. 1 and 8, 2026, which asks for qualified contractors and encourages MBE, SBE, WBE, AABE and HUB firms. Plans and specs are on BuildingConnected.
GMP #3 covers the athletics building addition and renovation, a new administration building, the existing administration building's renovation and expansion, a classroom renovation at the Old Mall (Area C), an existing restrooms renovation, the cafeteria and site work.
Which trades are in Northeast's GMP #3?
The page lists 98 rows. One is the plan room and some repeat a trade with an asterisk, which the page doesn't explain, so we count 75 trades. Here they are by family, in the page's own words.
- Electrical and low voltage: Electrical, Structured Cabling, Intercom & P/A, Audio Visual Systems, Voice Communications, Access Control, Intrusion Detection, CCTV, Fire Alarm System, ERRS.
- Mechanical and plumbing: HVAC (3 rows), Controls, Plumbing, Fire Sprinkler.
- Structure and envelope: Demolition, Abatement, Concrete, LWIC, Masonry, Structural Steel (fab and erect, fabrication, erection), Misc. Metals, Ornamental Metals, Rough Carpentry, Waterproofing, Insulation, Roofing, Metal Wall Panels, Fireproofing, Firestopping, Expansion Joints.
- Openings: Doors, Frames & Hardware, Door Labor, Overhead Doors, Glass & Glazing, Louvers, Skylights.
- Finishes: Drywall & Framing, Plaster, Acoustical, Tile, Resilient Flooring, Wood Flooring, Athletic Surfacing, Terrazzo, Resinous Flooring, Concrete Finishing, Painting.
- Specialties and equipment: display boards, signage, partitions, wall protection, fire protection specialties, lockers, canopies, flagpoles, appliances, food service, gym equipment, window treatments, casework, lab casework, special construction.
- Site: Earthwork, SWPPP, Termite Control, Asphalt, Unit Pavers, Stripes & Stops, Athletic Fields - Softball, Fences & Gates, Retaining Walls, Landscape & Irrigation, Site Utilities.
The page states no package values. The description's scope list adds detail a bidder will want: "Roofing (PVC & Standing Seam)", "Terrazzo Flooring", "Lab Equipment & Fume Hoods" and "Telescoping Stands, Fixed Bleachers, Grandstands".
Who's already on the Northeast ECHS permits?
Austin issued S&P building permits for the athletics building (Building C, 80,909 square feet on the permit) and Building A (16,576 square feet) on April 16, 2026. The athletics permit describes a "gut down renovation of existing athletic spaces" and an "Addition of substantial amount of area to the south and west of the existing athletics building."
The electrical permits under them went to Jomar Electrical Contractors on May 12, 2026. All four read Expired in the city's data as of Oct. 15, 2026, and we don't know whether Jomar's work is in GMP #3 or an earlier package. The district's March 2026 photos show the athletics building foundation.
On the fields, the city issued Cadence McShane Construction a $6.8 million permit on Nov. 4, 2026 at 7105 Berkman Dr for two dugouts, new lighting, batting cages and field turf, on the same appraisal-district parcel. BJ Electric Company holds the temporary permit for the sports light poles, and Hellas Construction pulled the conduit permit for the new sports complex in 2025. Those belong to the district's athletic field upgrades program, not GMP #3.
How big is the Northeast ECHS modernization?
Austin ISD's bond page gives a total project budget of $117,856,000 for Northeast ECHS and International High School, which share the campus. The district's FAQ says that figure "includes the budget for construction, as well as associated fees for services and materials."
The state accessibility registration lists "Additions to Existing Building" for an administration, academic and athletics building: 128,494 square feet, an estimated cost of $67,000,000, start April 15, 2025 and completion May 12, 2028. Perkins&Will is the design firm on it.
Community Impact reported the district will build a new competition gym and add locker rooms, fitness spaces and a weight room to the current gym. The district calls this phase 1 of 3 to 4, with later phases waiting on future bonds.
What's already underway on the campus?
The district's Q3 2026 update says central plant upgrades and mechanical-system improvements are underway, underground hydronic piping is going in for new heating and cooling, utility and drainage work continues, and roofing repairs and parapet-wall work are underway.
Next, it says, the team will finalize design packages and pricing for the Old Mall renovation and future campus work, and look at early access to part of the athletics building. We found no record naming the mechanical or roofing firm on that earlier work.
How do the ways into the Northeast ECHS project compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| S&P's Nov. 18 trade bid | A bid on one of 75 GMP #3 trades, on S&P's proposal form, emailed to [email protected] | Electrical, mechanical, envelope, finish and site subs | A price in S&P's guaranteed maximum price for the district | Due 2 p.m. Central Nov. 18, 2026; no package values are posted |
| The electrician on the permit | A call to Jomar Electrical Contractors, named on the athletics building's electrical permits | Electrical distributors, lighting and gear reps | A conversation with a firm already on the job's paperwork | The permits read Expired, and Jomar may not be on GMP #3 |
| The field builder | A call to Cadence McShane about the $6.8 million dugout, lighting and turf permit | Fencing, turf, lighting and site suppliers | Work on a permit issued Nov. 4, 2026 | A separate district program, not GMP #3 |
| The architect's spec | A call to Perkins&Will's Austin studio about your product | Manufacturers' reps | An approved-equal or a spot in later phases | GMP #3 is already out on its documents |
Who should go after the Northeast ECHS project, and who shouldn't?
| Electrical and low-voltage contractors | 10 of the 75 trades are electrical, cabling, AV, security and fire alarm, all due Nov. 18, 2026. |
|---|
| Electrical distributors and gear reps | The athletics building's electrical permits name Jomar Electrical Contractors, and the field lighting names BJ Electric. |
|---|
| Mechanical, envelope and finish subs | HVAC, controls, roofing, glazing, terrazzo, wood athletic flooring and more each have a package on the same date. |
|---|
| Firms that can't price by Nov. 18 | This round closes in a week. Watch for the district's future campus work and later phases, which have no date. |
|---|
What should you do next on the Northeast ECHS project?
- Open S&P's BuildingConnected page for Northeast Early College High School GMP #3 Final and join your package.
- Price on S&P's proposal form, broken out by building, and email it to [email protected] before 2 p.m. Central on Nov. 18, 2026.
- If you sell electrical gear, call the electricians bidding 26A and the one on the athletics building's permit.
- Open the full list for every package and the firms already on the record around the campus.
Questions people ask about the Northeast ECHS modernization
Who is building Northeast Early College High School's modernization?
Satterfield & Pontikes Construction (S&P) is the construction manager at risk. Austin ISD's bond page lists "Construction: S&P Construction, Inc.", and S&P's own bid page for GMP #3 says "S&P, the CMAR, invites you to bid" the project.
Who is the architect on the Northeast ECHS project?
Perkins&Will is the architect and engineer, from its Austin studio on Comal Street, per the district's bond page and the state accessibility registration. Vanir|STV is the district's program manager.
When are GMP #3 bids due at Northeast Early College High School?
2 p.m. Central on Wednesday, Nov. 18, 2026. S&P's bid page reads "BID DATE: Wednesday November 18th, 2026 at 2 PM", and its notice in the Austin American-Statesman says bids are due by email to [email protected].
What's in GMP #3?
The athletics building addition and renovation, a new administration building, the existing administration building's renovation and expansion, a classroom renovation at the Old Mall (Area C), restroom renovations, the cafeteria and site work, with 8 unit prices and 15 alternates. S&P's page lists 98 package rows, which we count as 75 trades.
How much does the Northeast ECHS modernization cost?
The district's total project budget is $117,856,000, which its FAQ says covers construction plus fees for services and materials. The state accessibility registration estimates construction at $67,000,000 for 128,494 square feet.
How does a subcontractor bid on Northeast ECHS?
Join the package on S&P's public BuildingConnected page, use S&P's proposal form with prices broken out by building, and email it to [email protected] before 2 p.m. on Nov. 18, 2026. The notice asks for qualified contractors and encourages MBE, SBE, WBE, AABE and HUB firms.
Who is the electrician on the Northeast athletics building?
Austin's permit records name Jomar Electrical Contractors on the electrical permits for the athletics building and Building A, issued May 12, 2026 under S&P's building permits. We don't know whether that work is in GMP #3 or an earlier package, and GMP #3 lists its own electrical package.
Is Northeast Early College High School getting a new building?
It's a phased modernization, phase 1 of 3 to 4: a new competition gym and additions to the athletics building, a new administration building and renovations, set to open in 2028. Later phases depend on future bonds.
How we built this list
We read S&P's public BuildingConnected page for GMP #3 (all 98 package rows), S&P's notice in the Austin American-Statesman, Austin ISD's bond page, FAQ, 2022 project sheet, athletic field upgrades page and Feb. 2025 community meeting deck, the state accessibility registration, every City of Austin permit at 7104 and 7105 Berkman Dr in the city's open data, and coverage by Community Impact and S&P. We grouped repeated package rows into 75 trades. A row is on the list only if a record ties it to the campus. We left every person's name, phone and email off the list. First published Nov. 10, 2026. We'll update this page if S&P moves the bid date, when the district posts GMP #3's award, or when new permits name firms on the campus.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 10, 2026- Satterfield & Pontikes, Northeast Early College High School GMP #3 Final (BuildingConnected)
- Austin American-Statesman legal notice, Northeast ECHS GMP #3
- Austin ISD 2022 Bond, Northeast ECHS / International High School
- Austin ISD, Northeast ECHS and International HS 2022 Bond FAQs
- Austin ISD, Community Meeting 3 presentation, Feb. 5, 2025
- Austin ISD, High School Athletic Field Upgrades
- TDLR, AISD Northeast ECHS & International School, TABS2025006256
- City of Austin, Issued Construction Permits (open data)
- Community Impact, Austin ISD breaks ground on modernization of Northeast Early College, International high schools, May 16, 2025
- Satterfield & Pontikes, S&P joins Austin ISD at Groundbreaking, May 20, 2025