Who did Prince William County name on NTT's VA12 permits?
The county issued building permit BLD2026-05831, "NEW DATA CENTER", to Clune Construction Company on Sept. 24, 2026, with a value of $276,835,025 and 580,724 sq ft. The project name is "NTT Global Data Centers BLD 3".
Dynalectric Company is the contractor on electrical permit ELE2027-00061, issued Oct. 12, 2026 with a value of $20,000,000, and on ELE2027-01809, "NTT VA12 LV ELECTRICAL PERMIT; LINK TO BLD2026-05831", issued Oct. 13, 2026.
W.E. Bowers & Associates is the contractor on mechanical permit MEC2027-00005 and plumbing permit PLB2027-00522, both issued Oct. 30, 2026. Those two permits repeat the building's $276,835,025, so the figure is the project's, not the trade's.
What is already permitted on NTT's VA12 site?
Clune holds an $8,850,000 permit for "Electrical Yard Foundations (generator pads)", issued Sept. 24, 2026. Hatzel & Buehler holds the temporary generator setup, issued Sept. 29, and Laurita Excavating the matching fuel tank permit, issued Oct. 1.
That temporary yard lists 6 temporary generators, a fuel tank, 2 transformers, switchgear and a medium-voltage breaker. Clune's trailer compound on the same parcel was permitted Aug. 12, 2026.
Is NTT's VA12 part of Amazon's Gainesville campus?
No. Amazon Data Services owns the Project Gainesville and Gainesville West parcels on Wellington Road, Deacon Falls Drive and Skylark View Way. NTT Global Data Centers VA10 LLC owns the Grove Hill Boulevard parcels about 2 miles west, by the county's land records.
One firm works on both: Dynalectric holds temporary power permits for construction trailers on Amazon's Gainesville buildings and on NTT's VA11.
What is on the rest of NTT's Gainesville campus?
NTT DATA's page for VA11, at 7251 Grove Hill Blvd across the street, says "VA11 will deliver 96MW of critical IT load and over 300,000 square feet of IT space" and that it is "Opening in early 2027". Converge Digest reported on March 7, 2026 that a hyperscale cloud provider reserved more than 90MW at VA11. No tenant is named for VA12.
The county's VA11 permits name Dynalectric for trailer and field generator power, with trailers labelled for W.E. Bowers and Clune, and Hatzel & Buehler for a temporary generator yard with 8 generators, 5 transformers and 2 medium-voltage switchgear. Building 1 (VA10) lists Holder Construction as contractor.
How do the ways into NTT's VA12 data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The electrician on the permit | A call to Dynalectric Company's office, (703) 742-3500 | Switchgear, wire, lighting, busway and gear reps | A conversation with the firm on VA12's electrical permits | No supplier list is public, and some gear may be ordered |
| The HVAC and plumbing contractor | A call to W.E. Bowers & Associates' main office, (301) 419-2488 | HVAC equipment, controls, piping and plumbing supply reps | A conversation with the firm on the mechanical and plumbing permits | The permits carry the building's value, not the trade's |
| The general contractor | A call to Clune Construction's Washington DC office, (703) 962-1814 | Trades not yet on the record: fire protection, envelope, roofing, concrete, steel | A way onto Clune's list for the job | No bid date or package list is public |
| The same firms' other jobs | Dynalectric on NTT's VA7 and AWS IAD 181 and 182; W.E. Bowers on Yondr, Sentinel and Cologix | Reps who want more than one job from one call | Several live Northern Virginia jobs per firm | Each is its own job with its own buyer |
Who should go after NTT's VA12 data center, and who shouldn't?
| Electrical distributors and gear reps | Dynalectric is named on VA12's electrical permits, valued at $20,000,000, issued Oct. 12 and 13, 2026. |
|---|
| HVAC and plumbing suppliers | W.E. Bowers holds VA12's mechanical and plumbing permits, issued Oct. 30, 2026. |
|---|
| Trade contractors not yet named | Clune is the builder; fire protection, envelope and other trades have no firm on the record yet. |
|---|
| Not for: anyone wanting a public bid | We found no public bid or due date. It is private work reached through the named firms. |
|---|
What should you do next on NTT's VA12 data center?
- Call Dynalectric's office at (703) 742-3500 about NTT's VA12 at 7250 Grove Hill Blvd, Gainesville.
- If you sell HVAC or plumbing, call W.E. Bowers' main office at (301) 419-2488.
- If your trade isn't named yet, call Clune Construction's Washington DC office at (703) 962-1814.
- Open the full list for the campus's other named firms and the same firms' other jobs.
Questions people ask about NTT's VA12 data center in Gainesville
Who owns the data center at 7250 Grove Hill Blvd in Gainesville, Virginia?
NTT DATA. Every Prince William County permit at the address names the owner NTT Global Data Centers VA10 LLC, and the county's parcel records list the same company. The building permit's project name is "NTT Global Data Centers BLD 3", and the low-voltage electrical permit calls the building "NTT VA12".
Is NTT's VA12 the same as Amazon's Gainesville data center campus?
No. Amazon Data Services' Gainesville campus is on Wellington Road and Deacon Falls Drive, about 2 miles east. NTT's campus is on Grove Hill Boulevard off John Marshall Highway. They share a ZIP code and a county, not an owner.
Who is the general contractor on NTT's VA12 data center?
Clune Construction Company. Prince William County issued it building permit BLD2026-05831, a new data center valued at $276,835,025 with 580,724 sq ft, on Sept. 24, 2026.
Who is the electrical contractor on NTT's VA12 data center?
Dynalectric Company. The county issued it the new-structure electrical permit ELE2027-00061, valued at $20,000,000, on Oct. 12, 2026, and the VA12 low-voltage electrical permit ELE2027-01809 on Oct. 13, 2026. Its Washington DC area office line is (703) 742-3500.
Who is the HVAC and plumbing contractor on NTT's VA12 data center?
W.E. Bowers & Associates. The county issued it the mechanical permit MEC2027-00005 and the plumbing permit PLB2027-00522 on Oct. 30, 2026. Its main office line is (301) 419-2488.
How much is NTT's VA12 data center worth?
The building permit lists $276,835,025. That is the county's permit value for the building, not NTT's total investment, which also covers land and equipment. The electrical permit lists $20,000,000 of its own.
How big is NTT's VA12 data center?
The building permit lists 580,724 sq ft. The electrical and plumbing permits list 620,283 sq ft, and datacenterHawk lists 557,780 sq ft and 96MW. NTT has not published VA12's size itself.
When will NTT's VA12 data center open?
NTT has not said. Baxtel lists 2028 as VA12's planned year. NTT says VA11, the building across Grove Hill Blvd, opens in early 2027.
Is NTT's VA12 data center out to bid?
We found no public bid. It is private work. Trades not yet on the record go through Clune, and gear and material for the electrical work go through Dynalectric.
What else is NTT building in Gainesville?
NTT DATA calls Gainesville its second Northern Virginia data center campus. In 2022 NTT bought 103 acres there from Lerner Enterprises for $257.4 million and planned four two-story buildings and 336MW. VA11 is next door, and the county's records also show building 1 (VA10), built by Holder Construction.
What are the risks for a seller on NTT's VA12?
The electrical permits went out in October, so some gear may already be ordered, and the permits don't list suppliers. The values on the mechanical and plumbing permits repeat the building's total, so they don't size those trades.
How we built this list
We read every Prince William County permit at 7250 to 7309 Grove Hill Blvd in ATI's copy of the county's public permit data and on the county's public EnerGov portal (case summaries and contact lists), the county's parcel records, NTT DATA's VA11 page, Baxtel and datacenterHawk's VA12 listings, and coverage by Data Center Frontier, Commercial Observer and Converge Digest. The same firms' other jobs come from ATI's copies of Prince William and Loudoun County permits. Company phone numbers come from each firm's own website. A row is on the list only if a record ties it to the campus or to the named firm. We left every person's name, phone and email off the list. First published Nov. 10, 2026. We'll update this page when new permits name firms on VA12, or if NTT announces VA12's tenant or opening date.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 10, 2026- Prince William County, building permit BLD2026-05831
- Prince William County, electrical permit ELE2027-00061
- Prince William County, electrical permit ELE2027-01809 (NTT VA12 LV)
- Prince William County, mechanical permit MEC2027-00005
- Prince William County, plumbing permit PLB2027-00522
- Prince William County parcel records
- NTT DATA, VA11 Data Center
- Baxtel, NTT VA12
- datacenterHawk, NTT VA12
- Data Center Frontier, June 14, 2022
- Commercial Observer, June 16, 2022
- Converge Digest, March 7, 2026
- Dynalectric
- W.E. Bowers & Associates
- Clune Construction