Who's building Nucor's steel mill in West Virginia

Apple Grove, West Virginia's $4 billion Nucor mill made its first steel in September, after a $1.7 billion state deal critics called a "handout."

By Porter Stanley. Updated .

Nucor is building a sheet steel mill on W.Va. 2 in Apple Grove, Mason County, West Virginia, made to turn out 3 million tons a year. Nucor now calls it a $4 billion investment; it said about $2.7 billion when it picked the site in 2022. The melt shop made its first steel in September 2026, and the first hot mill coils are due by December. Nucor names 16 contractor partners and no single general contractor. 19 firms are named on the job; the list below has all 19.

$4BNucor's stated investment (about $2.7B in 2022)
3M tonsSheet steel a year at full output
Sept. 2026First steel from the melt shop
19Firms named on the job

Get all 19 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 19 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 19 firms on the Nucor West Virginia mill?

We list the 19 firms named on Nucor's West Virginia steel mill, one row each, strongest tie first, with what each one does on the job and where its name comes from.

1Latest recordNov 21, 2026

Lexicon, Inc.

Puts up the mill buildings and installs the heavy mechanical work on Nucor's West Virginia steel mill in Apple Grove, Mason County, WV

Nucor Steel West Virginia sheet mill, W.Va. 2, Apple Grove (Mason County), WV

One of 16 contractor partners Nucor lists on its project page (read Nov. 21, 2026); no contract value is published

Work: Puts up the mill buildings and installs the heavy mechanical work

Who to call: Lexicon, Inc.
Lexicon office line
(Little Rock, AR)
(501) 490-4200

The opportunity: Nucor's project page, Contractor Partners section, lists 'Lexicon: Building Erection & Mechanical Installation' and links to the firm's own page for the job. The list is undated; we read it Nov. 21, 2026. The phone is the Little Rock headquarters line.

2Latest recordNov 21, 2026

East and Westbrook Construction

Industrial and commercial construction on the mill site on Nucor's West Virginia steel mill in Apple Grove, Mason County, WV

Nucor Steel West Virginia sheet mill, W.Va. 2, Apple Grove (Mason County), WV

One of 16 contractor partners Nucor lists on its project page (read Nov. 21, 2026); no contract value is published

Work: Industrial and commercial construction on the mill site

Who to call: East and Westbrook Construction
East and Westbrook Construction office line
(502) 222-0303

The opportunity: Nucor's project page, Contractor Partners section, lists 'East and Westbrook: Industrial & Commercial Construction' and links to the firm's own page for the job. The list is undated; we read it Nov. 21, 2026. The firm runs its own West Virginia hiring page for the job.

3Latest recordMar 25, 2022

SMS group

Supplies the whole melt shop: two DC electric arc furnaces of 190 metric tons each, two twin ladle furnaces, two vacuum tank degassers, and the melt shop's electrical and automation on Nucor's West Virginia steel mill in Apple Grove, Mason County, WV

Nucor Steel West Virginia sheet mill, W.Va. 2, Apple Grove (Mason County), WV

Melt shop order announced March 25, 2022; no contract value is published

Work: Supplies the whole melt shop: two DC electric arc furnaces of 190 metric tons each, two twin ladle furnaces, two vacuum tank degassers, and the melt shop's electrical and automation

Who to call: SMS group
SMS group website https://www.sms-group.com (no U.S. main line verified on its own site)

The opportunity: A March 25, 2022 trade report: the scope of supply includes two direct current electric arc furnaces, each with a capacity of 190 metric tons, plus two twin ladle furnaces and two vacuum tank degassers. SMS group is a supplier of equipment, not a site contractor.

What is Nucor building in West Virginia?

Nucor is building a sheet steel mill on W.Va. 2 in Apple Grove, in Mason County, West Virginia. It sits on about 1,700 acres along W.Va. 2 and the Ohio River.

The mill is made to turn out 3 million tons of sheet steel a year. It has a melt shop with two electric arc furnaces, a hot mill, a pickle line, a cold mill and two galvanizing lines, one for cars and one for building products. It is Nucor's single largest investment in its history.

How much is the Nucor West Virginia steel mill?

Nucor calls it a $4 billion investment on its own project page. That figure is Nucor's and includes the equipment.

When Nucor picked West Virginia in January 2022, it said the mill would cost about $2.7 billion. By June 2025 news reports put it at $3.1 billion. In June 2026, Nucor said it was spending about $950 million on the mill in 2026 alone.

Why was the Nucor incentive package a fight?

In January 2022, West Virginia passed a package worth about $1.7 billion for the mill: a tax credit worth more than $1.35 billion plus $315 million in cash. Watchdog groups called it a "handout" and said it would help nearby Ohio and Kentucky too.

In December 2024 the state added $75 million more, taking state funding to $390 million. The state Democratic Party's chair called it a "blank check."

How far along is the Nucor West Virginia mill?

The mill is in its last stage of building and in start-up. The melt shop made its first steel in September 2026, Nucor said in its third quarter report on Oct. 27. The pickle line began sending coils to other Nucor plants in October.

Nucor expects the first hot mill coils by December 2026, with the ramp up running into 2027. Work at the site stopped on Monday, Aug. 10, 2026, after a written threat, and the FBI was told. About 2,800 people were working on the construction then.

Who is building the Nucor West Virginia mill?

Nucor names no single general contractor. Its project page lists 16 contractor partners by trade. Lexicon puts up the buildings and the big machines, and East and Westbrook does industrial and commercial building.

Three firms do process electrical: G.A. West, MMR and Nitro Construction Services. Three do process piping: The Systems Group, Thompson Construction Group and United Group Services. Beaver Excavating and Goettle drive piles, Kanawha Stone preps the site, and ABC, CMP and Concrete Supply Co. pour and supply the concrete.

SMS group supplies the melt shop and its two arc furnaces. Amherst Madison does the river work, Terracon tests and inspects, CV Engineering handles construction engineering, and Appalachian Power is building a new substation next door. 19 firms in all are on the list below.

Who Nucor hired before

Several firms on the West Virginia list have worked for Nucor before. G.A. West, MMR, Lexicon, The Systems Group and SMS group all worked on Nucor projects in Kentucky or South Carolina.

  • G.A. West & Co.: steel erection and equipment installation on new galvanizing line at Nucor Steel Berkeley, Huger, SC, 2025-2026. Also on this job.
  • MMR Group: electrical on melt shop electrical, Nucor Steel Brandenburg plate mill, Brandenburg, KY, 2022. Also on this job.
  • Lexicon, Inc.: steel buildings and heavy mechanical on Nucor Steel Kentucky plate mill (melt shop, plate and roll mill buildings), Brandenburg, KY, undated project page. Also on this job.
  • The Systems Group (Systems Contracting): process piping on Nucor's Brandenburg plate mill and Gallatin sheet mill expansion, Brandenburg and Ghent, KY, 2022. Also on this job.
  • SMS group: mill equipment on $176 million galvanizing line at Nucor Steel Gallatin, Ghent, KY, 2017 (award). Also on this job.

These are earlier or other jobs for the same owner. They are not counted in the 19 firms on this job.

How do the ways into the Nucor West Virginia mill compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on Nucor's West Virginia mill in Apple GroveEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell; the mill is in start-up, so start-up and finish work is what is left

Who should go after the Nucor West Virginia mill?

Electrical distributors and gear repsThree process electrical firms, G.A. West, MMR and Nitro Construction Services, on a mill that runs two electric arc furnaces, plus Appalachian Power's new 345-kV substation next door.
Pipe, valve and mechanical repsThe Systems Group across the melt shop, Thompson Construction Group and United Group Services on process piping, and Lexicon on the heavy mechanical work.
Concrete, steel and site suppliersBeaver Excavating and Goettle on piles, Kanawha Stone on site prep, ABC, CMP and Concrete Supply Co. on concrete, and Amherst Madison on the river side.

What should you do next on the Nucor West Virginia mill?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on the Nucor Steel West Virginia mill in Apple Grove, Mason County.

Questions people ask about the Nucor West Virginia mill

How much is the Nucor West Virginia steel mill?

Nucor calls it a $4 billion investment. When Nucor picked West Virginia in January 2022, it said the mill would cost about $2.7 billion. The $4 billion is Nucor's own figure and includes the equipment.

Where is the Nucor steel mill in West Virginia?

It is on W.Va. 2 in Apple Grove, Mason County, West Virginia, on about 1,700 acres along W.Va. 2 and the Ohio River.

What will the Nucor West Virginia mill make?

Sheet steel, about 3 million tons a year. The plant has a melt shop with two electric arc furnaces, a hot mill, a pickle line, a cold mill and galvanizing lines. It is Nucor's single largest investment in its history.

Is the Nucor West Virginia mill open yet?

Not fully. The melt shop made its first steel in September 2026, and the pickle line began sending coils to other Nucor plants in October. Nucor expects the first hot mill coils by December 2026.

Who is building the Nucor steel mill in West Virginia?

Nucor has no single general contractor on its list. It names 16 contractor partners on its own project page, from pile drivers to three process electrical firms. 19 firms are named on the job in all, listed above.

How much did West Virginia give Nucor?

In January 2022 the state passed a package worth about $1.7 billion: a tax credit worth more than $1.35 billion plus $315 million in cash. In December 2024 it added $75 million more, taking state funding to $390 million.

Why was the Nucor incentive package controversial?

Watchdog groups called the $1.7 billion a "handout" in January 2022. In December 2024, when the state added $75 million, the state Democratic Party's chair called it a "blank check."

Why was the Nucor job site closed in August 2026?

Work at the site stopped on Monday, Aug. 10, 2026, after a written threat, and the FBI was told about it. About 2,800 people were working on the construction then.

How many people are building the Nucor mill?

Nucor says 2,000+ craft professionals. A local news report in August 2026 put it at about 2,800 people in construction. About 800 people will work at the plant when it runs.

What happens next on the Nucor West Virginia mill?

Nucor expects the first hot mill coils by December 2026, with the ramp up running into 2027. We'll update this page when a new record or firm appears.

How we built this list

We read Nucor's West Virginia project page and its Contractor Partners list, Nucor's January 2022 release, trade reports on the melt shop and piping orders, Nucor's third quarter results as reported Oct. 27, 2026, the utility's own story, a firm's own project page, and local news on the cost, the incentives and the August closure, all on Nov. 21, 2026. We kept each firm a public record names on this mill: 16 from Nucor's own list, plus the melt shop supplier, an engineering firm and the power company. Nucor's list is undated, so those rows carry the date we read it. The $4 billion is Nucor's own figure and includes equipment; no contract values are published. Left out: Nucor itself (the owner), the state and federal agencies that gave money, a security firm hired after the threat that no record names, and the press. We found no design firm of record in public. Phones are each firm's own main or office line from its own site; most are head offices, not West Virginia. We found no main line on the sites of CMP Concrete or SMS group, so we give their websites only. Appalachian Power's number is its customer line. First published Nov. 21, 2026. We'll update this page when a new record, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 19 firms, free

All 19 firms on the Nucor West Virginia mill

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.