What is Nucor building in West Virginia?
Nucor is building a sheet steel mill on W.Va. 2 in Apple Grove, in Mason County, West Virginia. It sits on about 1,700 acres along W.Va. 2 and the Ohio River.
The mill is made to turn out 3 million tons of sheet steel a year. It has a melt shop with two electric arc furnaces, a hot mill, a pickle line, a cold mill and two galvanizing lines, one for cars and one for building products. It is Nucor's single largest investment in its history.
How much is the Nucor West Virginia steel mill?
Nucor calls it a $4 billion investment on its own project page. That figure is Nucor's and includes the equipment.
When Nucor picked West Virginia in January 2022, it said the mill would cost about $2.7 billion. By June 2025 news reports put it at $3.1 billion. In June 2026, Nucor said it was spending about $950 million on the mill in 2026 alone.
Why was the Nucor incentive package a fight?
In January 2022, West Virginia passed a package worth about $1.7 billion for the mill: a tax credit worth more than $1.35 billion plus $315 million in cash. Watchdog groups called it a "handout" and said it would help nearby Ohio and Kentucky too.
In December 2024 the state added $75 million more, taking state funding to $390 million. The state Democratic Party's chair called it a "blank check."
How far along is the Nucor West Virginia mill?
The mill is in its last stage of building and in start-up. The melt shop made its first steel in September 2026, Nucor said in its third quarter report on Oct. 27. The pickle line began sending coils to other Nucor plants in October.
Nucor expects the first hot mill coils by December 2026, with the ramp up running into 2027. Work at the site stopped on Monday, Aug. 10, 2026, after a written threat, and the FBI was told. About 2,800 people were working on the construction then.
Who is building the Nucor West Virginia mill?
Nucor names no single general contractor. Its project page lists 16 contractor partners by trade. Lexicon puts up the buildings and the big machines, and East and Westbrook does industrial and commercial building.
Three firms do process electrical: G.A. West, MMR and Nitro Construction Services. Three do process piping: The Systems Group, Thompson Construction Group and United Group Services. Beaver Excavating and Goettle drive piles, Kanawha Stone preps the site, and ABC, CMP and Concrete Supply Co. pour and supply the concrete.
SMS group supplies the melt shop and its two arc furnaces. Amherst Madison does the river work, Terracon tests and inspects, CV Engineering handles construction engineering, and Appalachian Power is building a new substation next door. 19 firms in all are on the list below.
Who Nucor hired before
Several firms on the West Virginia list have worked for Nucor before. G.A. West, MMR, Lexicon, The Systems Group and SMS group all worked on Nucor projects in Kentucky or South Carolina.
- G.A. West & Co.: steel erection and equipment installation on new galvanizing line at Nucor Steel Berkeley, Huger, SC, 2025-2026. Also on this job.
- MMR Group: electrical on melt shop electrical, Nucor Steel Brandenburg plate mill, Brandenburg, KY, 2022. Also on this job.
- Lexicon, Inc.: steel buildings and heavy mechanical on Nucor Steel Kentucky plate mill (melt shop, plate and roll mill buildings), Brandenburg, KY, undated project page. Also on this job.
- The Systems Group (Systems Contracting): process piping on Nucor's Brandenburg plate mill and Gallatin sheet mill expansion, Brandenburg and Ghent, KY, 2022. Also on this job.
- SMS group: mill equipment on $176 million galvanizing line at Nucor Steel Gallatin, Ghent, KY, 2017 (award). Also on this job.
These are earlier or other jobs for the same owner. They are not counted in the 19 firms on this job.
How do the ways into the Nucor West Virginia mill compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Nucor's West Virginia mill in Apple Grove | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell; the mill is in start-up, so start-up and finish work is what is left |
Who should go after the Nucor West Virginia mill?
| Electrical distributors and gear reps | Three process electrical firms, G.A. West, MMR and Nitro Construction Services, on a mill that runs two electric arc furnaces, plus Appalachian Power's new 345-kV substation next door. |
|---|
| Pipe, valve and mechanical reps | The Systems Group across the melt shop, Thompson Construction Group and United Group Services on process piping, and Lexicon on the heavy mechanical work. |
|---|
| Concrete, steel and site suppliers | Beaver Excavating and Goettle on piles, Kanawha Stone on site prep, ABC, CMP and Concrete Supply Co. on concrete, and Amherst Madison on the river side. |
|---|
What should you do next on the Nucor West Virginia mill?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the Nucor Steel West Virginia mill in Apple Grove, Mason County.
Questions people ask about the Nucor West Virginia mill
How much is the Nucor West Virginia steel mill?
Nucor calls it a $4 billion investment. When Nucor picked West Virginia in January 2022, it said the mill would cost about $2.7 billion. The $4 billion is Nucor's own figure and includes the equipment.
Where is the Nucor steel mill in West Virginia?
It is on W.Va. 2 in Apple Grove, Mason County, West Virginia, on about 1,700 acres along W.Va. 2 and the Ohio River.
What will the Nucor West Virginia mill make?
Sheet steel, about 3 million tons a year. The plant has a melt shop with two electric arc furnaces, a hot mill, a pickle line, a cold mill and galvanizing lines. It is Nucor's single largest investment in its history.
Is the Nucor West Virginia mill open yet?
Not fully. The melt shop made its first steel in September 2026, and the pickle line began sending coils to other Nucor plants in October. Nucor expects the first hot mill coils by December 2026.
Who is building the Nucor steel mill in West Virginia?
Nucor has no single general contractor on its list. It names 16 contractor partners on its own project page, from pile drivers to three process electrical firms. 19 firms are named on the job in all, listed above.
How much did West Virginia give Nucor?
In January 2022 the state passed a package worth about $1.7 billion: a tax credit worth more than $1.35 billion plus $315 million in cash. In December 2024 it added $75 million more, taking state funding to $390 million.
Why was the Nucor incentive package controversial?
Watchdog groups called the $1.7 billion a "handout" in January 2022. In December 2024, when the state added $75 million, the state Democratic Party's chair called it a "blank check."
Why was the Nucor job site closed in August 2026?
Work at the site stopped on Monday, Aug. 10, 2026, after a written threat, and the FBI was told about it. About 2,800 people were working on the construction then.
How many people are building the Nucor mill?
Nucor says 2,000+ craft professionals. A local news report in August 2026 put it at about 2,800 people in construction. About 800 people will work at the plant when it runs.
What happens next on the Nucor West Virginia mill?
Nucor expects the first hot mill coils by December 2026, with the ramp up running into 2027. We'll update this page when a new record or firm appears.
How we built this list
We read Nucor's West Virginia project page and its Contractor Partners list, Nucor's January 2022 release, trade reports on the melt shop and piping orders, Nucor's third quarter results as reported Oct. 27, 2026, the utility's own story, a firm's own project page, and local news on the cost, the incentives and the August closure, all on Nov. 21, 2026. We kept each firm a public record names on this mill: 16 from Nucor's own list, plus the melt shop supplier, an engineering firm and the power company. Nucor's list is undated, so those rows carry the date we read it. The $4 billion is Nucor's own figure and includes equipment; no contract values are published. Left out: Nucor itself (the owner), the state and federal agencies that gave money, a security firm hired after the threat that no record names, and the press. We found no design firm of record in public. Phones are each firm's own main or office line from its own site; most are head offices, not West Virginia. We found no main line on the sites of CMP Concrete or SMS group, so we give their websites only. Appalachian Power's number is its customer line. First published Nov. 21, 2026. We'll update this page when a new record, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 21, 2026- Nucor Steel West Virginia project page, with its Contractor Partners list (read Nov. 21, 2026)
- Nucor news release: Nucor selects West Virginia for new sheet mill (Jan. 12, 2022)
- AIST: Commissioning underway at new Nucor mill (June 16, 2026)
- AIST: SMS wins melt shop order for Nucor's West Virginia mill (Mar. 25, 2022)
- AIST: The Systems Group order from Nucor sheet mill (Apr. 11, 2023)
- MarketBeat via Yahoo Finance: What Nucor said on its Q3 earnings call (Oct. 27, 2026)
- WV Gazette-Mail: Nucor on track to finish WV mill this year (June 18, 2026)
- WV Press: Nucor's $3.1B steel mill on track for 2027 (June 27, 2025)
- West Virginia Center on Budget and Policy: watchdog groups on the $1.7 billion for Nucor (Jan. 14, 2022)
- The Intermountain: WV Dems oppose 'blank check' for Nucor (Dec. 24, 2024)
- Parkersburg News and Sentinel: Nucor Steel site closed Monday due to written threat (Aug. 11, 2026)
- AEP: Nucor Makes Generational Impact (Sept. 25, 2025)
- CV Engineering: Nucor Steel West Virginia Flat Rolling Mill Facility
- G.A. West, 'Nucor Steel - Huger, South Carolina' project page
- MMR Group, 'MMR Receives ABC Awards of Excellence, Merit', 2023-12-18
- Lexicon, 'Nucor Steel Kentucky' project page
- Manufacturing Today, 'The Systems Group' profile, 2022-07-25
- AIST, 'Nucor Awards Galvanizing Line Contract to SMS group', 2017-07-20