What is O'Hare's New Concourse E?
The New Concourse E is a new two-level concourse at Chicago O'Hare International Airport. It will stretch more than 1,000 feet and hold 24 gates when both phases are done. It sits west of the New Concourse D, and passengers will reach it mainly through an underground tunnel from Concourse D. City permits call it the Satellite 2 Concourse.
The Chicago Department of Aviation owns the job. Mayor Brandon Johnson broke ground on Nov. 17, 2026, with United Airlines and American Airlines. The plans include about 21,000 sq ft of shops and restaurants.
Concourse E is one piece of the city's wider O'Hare rebuild. Our earlier report covers the whole program: /the-index/ohare-expansion-who-gets-paid.
How much will O'Hare's Concourse E cost?
The city puts Concourse E at $917 million, built in two phases. The first phase is $640 million for 14 new gates and about 315,000 sq ft of passenger space, due in 2030. The second phase is $277 million and adds 10 more gates, by 2034.
The same city release gives a bigger number, $1.455 billion. That is not Concourse E. It is the guaranteed maximum price for Concourse D, set in June 2026 and $21 million below its first budget.
Who is building O'Hare's Concourse E?
The city says Concourse E brings back the same design and construction teams as Concourse D. Construction is led by the AECOM Hunt Clayco Bowa joint venture. AECOM Hunt, Clayco and Bowa Construction all have Chicago offices, and Bowa joined the team in July 2020.
The city has not said what the joint venture is paid, or each partner's share. The $917 million is the budget for the whole concourse.
Which permits are out for O'Hare's Concourse E?
On Oct. 1, 2026, the city issued a $5.7 million permit for the caissons of the Satellite 2 Concourse, the deep foundations that go in first. It names Hunt Construction Group as general contractor and McHugh Concrete Construction as a masonry contractor.
On March 16, 2026, the city issued a $220 million permit for the confined-space portions of the consolidated tunnel between the future Global Terminal and the future Satellite 2 Concourse; it also covers building systems for Satellite 1, which is Concourse D. It names Gurtz Electric for electrical, F.E. Moran for plumbing, Helm Mechanical for ventilation and refrigeration, and A.L.L. Masonry and McHugh for concrete work. Those firms are on the tunnel, not yet on a Concourse E building permit. We found no other Concourse E trade permits yet.
Who designed O'Hare's Concourse E?
Skidmore, Owings & Merrill (SOM) leads the design, working with Ross Barney Architects, Juan Gabriel Moreno Architects (JGMA) and Arup. The same team designed Concourse D.
Arup is the lead mechanical, electrical and plumbing engineer and IT engineer for Concourses D and E. Milhouse Engineering and Construction, a local minority business, helps with that engineering. 13 firms in all are on the list below.
How do the ways into O'Hare's Concourse E compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on O'Hare's New Concourse E | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The trade work still to come | A place on a trade package for the concourse building, through the construction team | Subcontractors and their suppliers | A share of a $917 million concourse | No trade permits beyond the caissons yet, so timing is not set |
Who should go after O'Hare's Concourse E?
| Electrical, mechanical and plumbing reps | Arup writes the MEP design for Concourses D and E with Milhouse; Gurtz Electric, F.E. Moran and Helm Mechanical are on the $220 million tunnel permit. |
|---|
| Concrete, steel and site suppliers | McHugh Concrete on the $5.7 million caissons permit, and A.L.L. Masonry and McHugh on the tunnel. |
|---|
| Subcontractors chasing trade packages | The AECOM Hunt Clayco Bowa joint venture runs construction on the $917 million job, and only the caissons are on a permit so far. |
|---|
What should you do next on O'Hare's Concourse E?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the New Concourse E (Satellite 2) at O'Hare.
- Watch for new city permits on the Satellite 2 Concourse, which will name the trade firms.
Questions people ask about O'Hare's Concourse E
How much will O'Hare's Concourse E cost?
The city puts it at $917 million: $640 million for the first phase of 14 gates, due in 2030, and $277 million for a second phase of 10 more gates, by 2034.
Who is building O'Hare's Concourse E?
The AECOM Hunt Clayco Bowa joint venture leads construction, the same team building Concourse D. The city's Department of Aviation owns the job. 13 firms are named on the job, listed above.
Who designed O'Hare's Concourse E?
Skidmore, Owings & Merrill (SOM), working with Ross Barney Architects, Juan Gabriel Moreno Architects (JGMA) and Arup. Arup is the lead mechanical, electrical and plumbing engineer.
When will O'Hare's Concourse E open?
The first 14 gates are due in 2030. The last 10 gates come in a second phase, by 2034.
How many gates will Concourse E have?
24 gates when both phases are done: 14 in the first phase and 10 in the second. The first phase also adds about 315,000 sq ft of passenger space.
Is Concourse E the $1.455 billion project?
No. $1.455 billion is the guaranteed maximum price for Concourse D, set in June 2026 and $21 million below its first budget. Concourse E is $917 million.
What is the Satellite 2 Concourse at O'Hare?
It is the name city permits use for Concourse E. A $5.7 million caissons permit for it was issued Oct. 1, 2026, and a $220 million permit for the shared tunnel that reaches it on March 16, 2026. The caissons permit itself reads 'Satellite 2 Concourse (Concourse E)'.
How can subcontractors get on O'Hare's Concourse E?
Call the firms already on the job, starting with the AECOM Hunt Clayco Bowa joint venture, which runs construction, and Arup for mechanical and electrical design. Only the caissons are on a permit so far, so most trade work is still to come.
What happens next on O'Hare's Concourse E?
Work starts on the first phase after the Nov. 17, 2026 groundbreaking. Watch for new city permits naming trade firms on the Satellite 2 Concourse. We'll update this page when a new permit or firm appears.
How we built this list
We read the City of Chicago's Nov. 17, 2026 groundbreaking release, the city's building permit records for the Concourse E caissons (101079761) and the tunnel to it (101076890), Arup's project page for Concourses D and E, AECOM's 2020 release on the joint venture, and news reports, all on Nov. 20, 2026. We kept each firm a public record names on Concourse E itself, plus firms on the tunnel permit and on Arup's D and E page, and we say which is which on each row. The $917 million is the city's budget for the whole concourse, not one firm's share. Left out: the city and its program manager, a permit expediter, the city's plan reviewer, people named on the permits, the airlines, the Global Terminal's designer, a masonry firm on the caissons permit and an IT consulting firm on Arup's page, because we found no phone or website for either. Phones are each firm's own office line from its own site; SOM's, Milhouse's and A.L.L. Masonry's are from business listings, and Clayco's is its Chicago headquarters line. First published Nov. 20, 2026. We'll update this page when a new permit, contract or firm appears.