What's in the Thunder arena's finish and sitework package?
The Flintco | Mortenson joint venture's bidder presentation, from its July 14, 2026 meeting, schedules Bid Package 7, interior finishes and sitework, to go out Nov. 11, 2026. Bids are set to be due Dec. 17, 2026, and the award is expected about Jan. 24, 2027.
Read together, the presentation and the joint venture's procurement page list 33 lines. Seven are floors: tile, soft flooring, epoxy, terrazzo, polished concrete, access flooring and athletic wood flooring.
The rest run from millwork, paint, interior glass, ceilings and signage to lockers, laundry and dock equipment, hydrotherapy pools, landscaping, pavers, fencing, paving and the final clean.
We found no press naming the package or its dates. These are the builder's schedule dates, and the package wasn't out as of Nov. 7, 2026.
Who's already on Continental Coliseum?
The joint venture's procurement page lists 28 packages awarded to 25 firms. It gives no award dates or values.
On Oct. 9, 2026, the city issued a commercial electrical permit for the arena to Oil Capital Electric, which holds the builder's main electrical package. Construction Dive reported on Oct. 16, 2026 that crews had poured the first of more than 18 elevated concrete decks, with Dolese Bros. supplying the concrete.
- Concrete. Lithko holds the deep foundations and structural concrete, and NAPCO the precast seating bowl.
- Steel and glass. W&W/AFCO Steel holds the structural steel, and Harmon the exterior glass and curtain wall.
- Systems. Waldinger holds plumbing and mechanical, Control Fire the fire protection, RFIP the structured cabling and CTI the audio visual work.
- Seats and screens. Irwin Seating Company holds the seating, and Daktronics the scoreboard and LED boards.
Bid Package 6, the core and shell interiors, had bids due Oct. 22, 2026, and no winners were posted on the procurement page when we checked on Nov. 7.
Who can bid on the Thunder's new arena?
Only prequalified subcontractors. The joint venture's procurement page says no proposals will be accepted from any subcontractor not prequalified for the project, and that bid documents go out through BuildingConnected after a nondisclosure agreement.
The builder's slides describe Oklahoma's Title 61 public bidding rules: sealed bids over $50,000, awarded to the lowest responsible bidder, with prequalification first, then 5% bid bonds. Bid Package 7's prequalification call went out Aug. 27, 2026, and we found no deadline for it.
A supplier doesn't need to be prequalified to sell to a firm that is. The firms already awarded are on the builder's list, and the finish package's winners are expected in late January 2027.
How do the ways into Continental Coliseum compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The joint venture's prequalification | Title 61 prequalification and TradeTapp, then sealed bids through BuildingConnected after an NDA | Subcontractors who want a trade package | Eligibility to bid the builder's packages | Bid Package 7's prequalification call went out Aug. 27, 2026, and we found no deadline |
| The joint venture's vendor form | A vendor interest form and a procurement contact form on flintcomortensonjv.com | Suppliers and firms new to the project | Your interest on file with the builder | It isn't a bid, and its vendor list says coming soon |
| Flintco's bid list | Flintco's trade partner form, which the Thunder's arena page links to | Firms that want Flintco's bid invitations | A place on Flintco's list | It isn't tied to this job's packages |
| Selling to a firm already on it | A call to a firm the builder lists as awarded, like Oil Capital Electric or Lithko | Suppliers and lower-tier subs | A conversation with a firm buying for the arena now | The list shows no values or what's already bought |
| The city's programs | Contractor registration and the Small, Local and Minority Owned Business Utilization Program | Local, small and minority-owned firms | Standing the builder's slides ask bidders to have | Registration alone isn't a bid |
Who should go after the Thunder arena, and who shouldn't?
| Flooring and tile contractors and suppliers | Bid Package 7 has 7 flooring lines, with bids scheduled to be due Dec. 17, 2026. |
|---|
| Finish trades: millwork, paint, ceilings, signage and specialties | The same package carries those lines, from lockers and partitions to final clean. |
|---|
| Electrical, concrete and steel suppliers | Those packages are awarded, so the buyer is the firm on the builder's list. |
|---|
| Firms that aren't prequalified and want an open public bid | This isn't the job for you yet: only prequalified firms can bid, and nothing is out today. |
|---|
What should you do next on the Thunder arena?
- Ask the joint venture through its procurement contact form whether you can still prequalify for Bid Package 7.
- Fill out the joint venture's vendor form and Flintco's trade partner form.
- Register with the City of Oklahoma City, and note any small, local or minority-owned status.
- Open the full list and call the firm already awarded your trade.
Questions people ask about the Thunder's new arena
Who is building the Thunder's new arena?
The Flintco | Mortenson joint venture, a team of Flintco and Mortenson, is the construction manager at risk. The Oklahoma City Council hired it on March 11, 2025, and the City of Oklahoma City owns the arena.
Who owns Continental Coliseum?
The City of Oklahoma City. Its building permits for the arena name the city as owner and the OKC MAPS Project Office as applicant. The Thunder are the tenant, and Continental Resources holds a 15-year naming rights deal.
How much does Continental Coliseum cost?
The budget is at least $900 million. The Thunder list $900 million in sales tax funds, plus $78 million in MAPS 4 funding and $50 million from the Thunder ownership group. Neither the builder nor the city has published a value for any trade package.
When will Continental Coliseum open?
The Thunder say it's scheduled to open by late summer 2028, in time for the 2028-29 season. Ground was broken on March 26, 2026.
How do subcontractors get on the Thunder arena?
Through the joint venture's prequalification. Its procurement page says no proposals will be accepted from a subcontractor not prequalified for the project, and bid documents go out through BuildingConnected after a nondisclosure agreement. The builder's slides also call for registration with the city.
When are the Thunder arena's finish bids due?
The builder's schedule sets Bid Package 7, interior finishes and sitework, to go out Nov. 11, 2026, with bids due Dec. 17, 2026 and the award expected about Jan. 24, 2027. Those are schedule dates, and the package wasn't out as of Nov. 7.
What flooring is in the Thunder arena's next package?
Bid Package 7 has 7 flooring lines: tile, soft flooring, epoxy, terrazzo, polished concrete, access flooring and athletic wood flooring. The builder's slides list the athletic wood line, and its procurement page lists the other 6.
Who has the electrical on the Thunder arena?
The builder's procurement page lists the main electrical package as awarded to OCE, and the city issued Oil Capital Electric an electrical permit for the arena on Oct. 9, 2026. Prime Electric held the early electrical package.
Can any contractor bid the Thunder arena's finish package?
No. Only prequalified firms can bid. The prequalification call for Bid Package 7 went out Aug. 27, 2026, and we found no deadline for it, so a firm that isn't prequalified should ask the joint venture whether it can still get in.
What are the risks of chasing this job?
The bid dates are the builder's schedule and can move, only prequalified firms can bid, and no package value is published. Bid Package 6 bids were due Oct. 22, 2026, and no winners were posted when we checked.
Who designed Continental Coliseum?
The Thunder say the city selected MANICA Architecture as the design architect in 2024, with TVS as the architect of record.
What happens next at Continental Coliseum?
After Bid Package 7, the builder's slides show steel erection starting in early 2027, curtain wall in the second quarter of 2027, and scoreboard and seating installation in the second quarter of 2028.
How we built this list
We read the joint venture's procurement page, all 6 pages of it, and its bidder presentation, the city's permit records for 125 W Reno Ave, the Thunder's arena page and releases, the city's call to artists, and press coverage. A row is on the list only if a record ties it to the arena. Bid Package 7 has 33 lines when the slides and the procurement page are read together: each lists 32, and each has 1 the other doesn't. Its dates are the builder's schedule, so no row is marked open, and a row whose due date has passed says so. First published Nov. 8, 2026. We'll update this page when the finish package goes out, a winner is posted or a new permit appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 8, 2026- Flintco | Mortenson JV, procurement
- Flintco | Mortenson JV, bidder presentation, July 14, 2026
- Flintco | Mortenson JV, vendors
- Flintco, trade partners
- Oklahoma City Thunder, Continental Coliseum
- City of Oklahoma City permits, BLDC-2026-05810
- City of Oklahoma City permits, ELEC-2026-08075
- City of Oklahoma City, call to artists, terrazzo floor
- Construction Dive, Oct. 16, 2026
- KOKH, Dec. 30, 2025
- News9, Oct. 8, 2026
- Oil Capital Electric