Who is building Oolite Arts' new campus?
Skanska's public bid page for the job, posted Oct. 30, 2026, opens: "Skanska is pleased to announce we are the successful contractor selected for preconstruction services for this exciting project!" The listing is run by Skanska's Fort Lauderdale office.
The same page asks trade firms for "final price confirmation proposals for GMP award", so the guaranteed maximum price has not been set. Oolite Arts' own campus page names no builder, and we found no news story naming Skanska or any general contractor in 5 searches on Nov. 9, 2026.
Barozzi Veiga of Barcelona designed the campus, its first U.S. project. Architectural Record reported in 2022 that Charles H. Benson & Associates of Miami would be architect of record, and Cumming Group lists program and project management for Oolite Arts on an undated portfolio page.
What is in Skanska's Oolite Arts price round?
Skanska lists 36 rows, all due 5 PM Eastern (4 PM Central) on Monday, Nov. 16, 2026, with an expected start of Jan. 4, 2027. Leaving out its own distribution row and a supplier list that appears twice, that is 33 trade packages.
The last round was priced on Revision B drawings dated April 27, 2026. This one is priced on Revision C, dated Aug. 10, 2026, and Skanska asks each firm for a short note on what changed and to hold its price to the end of the year, roughly 60 days. The project holds 1,177 files.
Skanska first posted the job in June 2026 as a budget round, due Aug. 3, and said then that the documents had been submitted for permit.
- Concrete: Cast-in-place concrete, and a separate polished concrete package.
- Envelope: Masonry, stone veneer, stucco and EIFS, waterproofing, roofing, and the exterior glass, which the owner procures.
- Structure and metals: Structural steel and miscellaneous metals, and ornamental metals.
- Interiors: Framing and drywall, acoustical ceilings, wall tile, painting and wall coverings, millwork, doors and hardware, interior glass, specialties, signage, window treatments.
- Systems: Plumbing, HVAC with test and balance, electrical with fire alarm, low voltage, and an elevator.
- Site: Sitework and utilities, dewatering, site fences and gates, landscape and irrigation, temporary fencing, final cleaning and BIM coordination.
How much concrete is in the Oolite Arts campus?
No quantity is public. Architectural Record reported in April 2022 that the initial choice of raw concrete for the studios led Barozzi Veiga to envisage building the whole complex in bare concrete, both inside and out, with an insulated double wall.
Skanska's 2026 list carries a cast-in-place concrete package and a polished concrete package, and also stucco and stone veneer packages, so the Revision C drawings, not the 2022 description, set the scope to price.
The design groups eight clusters of five or six studios around an interior garden, with towers that work as solar chimneys, wind catchers and rainwater tanks, according to Oolite Arts and Architectural Record.
What does ATI hold on the Oolite Arts site?
Nothing yet. ATI's records hold no building permit, project or planning filing at 75 or 77 NW 72nd Street. Skanska's June page says the documents were submitted for permit, and ATI's records carry a permit once the city issues it.
ATI does hold Skanska's last Miami-Dade permit: a $120 million emergency department expansion at 1611 NW 12th Avenue, issued March 11, 2026.
How do the ways into the Oolite Arts campus compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| Price a package through Skanska | Join the package on Skanska's public plan room and send a final price by Nov. 16 | Concrete, finishes, MEP, sitework and specialty subs | A place in the GMP the builder takes to Oolite Arts | This round confirms prices on Revision C; firms from the last round are ahead |
| Sell to the subs pricing it | A quote to the concrete, glazing or MEP subs who price Skanska's packages | Ready-mix, rebar, tile, fixtures and equipment suppliers | A line in a sub's price | The bidders' names aren't public on the plan room |
| Skanska's supplier list | The Strategic Supply Chain Partners row on the same page | Material and equipment suppliers who sell to Skanska directly | A seat on the builder's own supplier list for the job | No scope or keyword is listed for it |
| Go to the owner for the glass | The exterior glass and glazing package, which the owner procures | Storefront and curtain wall makers and installers | A direct deal with Oolite Arts | Not stated whether it is still open or already bought |
| After the GMP award | Selling to the subs Skanska signs once the GMP is set | Suppliers who miss Nov. 16 | Buyout and purchases from a January 2027 start | Most prices are set by then |
Who should go after the Oolite Arts campus, and who shouldn't?
| Concrete subs and ready-mix, rebar and forming suppliers | Skanska lists a cast-in-place concrete package and a polished concrete package, and the 2022 design was bare concrete inside and out. |
|---|
| Storefront and curtain wall firms | The exterior glass is procured by the owner, so the door is Oolite Arts as well as the builder. |
|---|
| Finish, MEP and site subs in South Florida | All 33 packages are due Nov. 16, 2026, with a January 2027 start. |
|---|
| Firms that need a public, bonded government bid | This isn't one: it's a private nonprofit's job through a construction manager. |
|---|
What should you do next on the Oolite Arts campus?
- Open Skanska's public plan room on BuildingConnected, find "Oolite Art Center - GMP Pricing for Award" and join your package.
- Price the Revision C drawings dated Aug. 10, 2026, and send a short note of what changed from Revision B if you priced the last round.
- Get your price in by 5 PM Eastern on Monday, Nov. 16, 2026, and hold it to the end of the year, as Skanska asks.
- If you sell storefront or curtain wall, call Oolite Arts at 305.674.8278 and ask who is buying the exterior glass.
Questions people ask about the Oolite Arts campus construction
Who is building the Oolite Arts campus in Miami?
Skanska. Its public bid page for "Oolite Art Center - GMP Pricing for Award", posted Oct. 30, 2026, says Skanska was selected for preconstruction services and is collecting final prices for the guaranteed-maximum-price award. The GMP itself had not been awarded when we checked on Nov. 9, 2026.
Is Skanska the general contractor on Oolite Arts?
Skanska is the builder picked for preconstruction, and it is pricing the job for a guaranteed maximum price. That is the usual step before a construction manager signs to build it, but we found no award yet and no news story naming Skanska.
When are the Oolite Arts trade prices due?
5 PM Eastern (4 PM Central) on Monday, Nov. 16, 2026, for every package on Skanska's page. Skanska asks bidders to hold prices to the end of the year, roughly 60 days.
What trade packages are on the Oolite Arts campus?
Skanska lists 33 trade packages, from cast-in-place concrete, masonry, stone veneer and structural steel to stucco, roofing, HVAC, plumbing, electrical, low voltage, elevators, sitework, dewatering and landscape, plus a supplier list. The exterior glass package is marked "Procured by Owner".
Is there concrete work on the Oolite Arts campus?
Yes. Skanska lists a cast-in-place concrete package and a separate polished concrete package. In 2022 the architect planned the whole complex in bare concrete, inside and out; the current Revision C drawings are the ones to price.
Who buys the exterior glass on Oolite Arts?
The owner. Skanska's package for exterior glass and glazing, covering storefronts and curtain wall, is labeled "Procured by Owner". The page does not say whether Oolite Arts has already bought it.
How much will the Oolite Arts campus cost?
Oolite announced a $30 million facility in 2019, and the Miami Herald, via WLRN, still called it "The ambitious $30 million building" in September 2023. We found no newer figure, and no contract value is public.
When does construction start on Oolite Arts' new campus?
Skanska's page lists an expected start of Jan. 4, 2027 and says the project is "still pushing to start in January of 2027". Oolite's own campus page says groundbreaking is scheduled for 2027 and the warehouses come down for construction in mid-2027.
How big is the Oolite Arts campus?
26,850 square feet, per Oolite Arts, with 21 artist studios, exhibition and theater spaces, a maker space, a print shop and classrooms. Skanska describes single-story cultural buildings on two lots, 75 and 77 NW 72nd Street.
Who designed the Oolite Arts campus?
Barozzi Veiga of Barcelona, its first U.S. project. Architectural Record reported in 2022 that Charles H. Benson & Associates of Miami would be architect of record.
How does a subcontractor get on the Oolite Arts job?
Through Skanska's public plan room on BuildingConnected, where each package can be joined, or through Skanska's Fort Lauderdale office. Prices are due Nov. 16, 2026. Firms that priced the earlier Revision B round are asked to confirm against Revision C.
Is the Oolite Arts campus a public bid?
No. Oolite Arts is a nonprofit, and this is a private construction manager's invitation on its own public plan room, not a government solicitation.
How we built this list
We read Skanska's public plan room page for the job and its own data (posting date, due date, the 36 package rows and their trade keywords), Skanska's June 2026 budget round for the same job, Oolite Arts' campus pages, Architectural Record's 2022 design report, the 2023 Miami Herald report carried by WLRN, a 2021 Florida YIMBY report and Cumming Group's portfolio page, and ran 5 news searches for a builder. ATI's own records hold no permit, project or filing at the site yet: Skanska's June page says the documents were submitted for permit, and ATI's permit records carry a permit once the city issues it. Each Skanska package is one row, the two Strategic Supply Chain rows are one row, and the four firms named on public records are one row each. We did not join the plan room or log in, so no bidder is named. First published Nov. 9, 2026. We'll update this page when the City of Miami issues the building permit, Skanska's GMP is awarded, or the start date moves.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 9, 2026- Skanska public plan room, "Oolite Art Center - GMP Pricing for Award", posted Oct. 30, 2026
- Oolite Arts, Our new home
- Oolite Arts, Massive Mural Commemorates Countdown to our New Campus
- Oolite Arts, ArtCenter/South Florida to Build New $30 Million Home
- Architectural Record, Barozzi Veiga Reveals Design for First U.S. Project, Apr. 12, 2022