What's due Nov. 20 on the Panthers' stadium renovation?
Clark/D.A. Everett's bid portal says all trade packages for RP5, its fifth bid round after early release packages 1 to 4, are issued, and all bids are due no later than Nov. 20, 2026. Its RP5 pre-bid slides put the time at 2 pm.
The builder held RP5's online pre-bid meetings by group: structural and finishes on Oct. 19, 2026, then skin and MEPF, tech and kitchen equipment on Oct. 22. Ten firms signed in online to the finishes meeting, among them Master Millwork, QuestMark Flooring and Charlotte Paint Company.
The same slides set MEPF bids due Oct. 23 and an LED videoboard bid due Nov. 13. The finish lines inside RP5 are shown only as pictures in the slides, so ask the builder for the exact list before you price.
Who is on the builder's bidder list for the Panthers' stadium?
The builder publishes a prime bidder list for the renovation with 50 trade headings and 377 firm entries. Merged for spelling, that's about 238 different firms. The list has no date, and the builder's slides call it continuously updated.
The press has named the builder and the owner's program manager. We found no coverage naming the trade firms on the list.
- Finishes. 15 firms under ceilings, 14 under drywall and carpentry, 8 under flooring and tile, 8 under tile and 9 under painting: 36 different firms in all.
- Envelope. 13 firms under exterior glass and glazing, 16 under waterproofing and 7 under metal panels.
- Systems. 10 under mechanical, 7 under electrical, 5 under plumbing and 8 under fire suppression.
- Stadium items. 8 under LED videoboards, 3 under stadium seating and 4 elevator makers.
Sixteen firms carry an X in the list's ERP 1 partner column, 20 marks in all, among them Daktronics on LED videoboards and Hussey Seating Company on stadium seating. The list doesn't define the column, so we don't read it as a new award.
Who can bid on the Bank of America Stadium renovation?
Only prequalified prime subcontractors. The builder's portal says prequalification runs through TradeTapp on BuildingConnected, starting with its prequalification initiation form, and that the project team then compiles a list of qualified bidders.
The form asks for bonding capacity, a Charlotte-area office and small business certifications, and lets a firm check the trades it wants to bid, from drywall and painting to scoreboards and stadium seating.
The city is paying $650 million, and WSOC reported the City Council required that 27% of that taxpayer money, $179 million, go to diverse-owned firms. WSOC reported that representatives from 350 companies came to the builder's contractor kickoff at the stadium in January 2026.
What has the county permitted at Bank of America Stadium?
On Oct. 29, 2026, Mecklenburg County issued commercial building permit COM-GBLD-26-001116 at 800 S Mint St to Clark Construction Group, LLC for a retaining wall, concrete finishing and pile installation, with a $250,000 cost of construction. A matching site works record was filed the same day.
Earlier county records at the address include low voltage, fire alarm and access control permits from August and September 2026, and a Sept. 10 electrical permit for installing a videowall and clocks in the lower level. WSOC reported on July 23, 2026 that a back-of-house phase on electrical, plumbing and HVAC systems began the month before, with fan-facing work planned from 2027 to 2030.
How do the ways into the Bank of America Stadium renovation compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The builder's prequalification | A prequalification initiation form, then TradeTapp through BuildingConnected, then the project team's review | Subcontractors who want to bid a trade package as a prime | Invitations to bid the builder's packages | All prime subcontractors must be prequalified, and we found no prequalification deadline |
| Selling to the firms on the bidder list | A call to a firm the builder lists under your trade, like its 15 ceiling or 14 drywall bidders | Suppliers, manufacturers' reps and lower-tier subs | A conversation with a firm pricing stadium work before Nov. 20 | The list names bidders, not winners, and gives no values |
| The builder's bid inbox | [email protected], the project's address for questions about the work | Firms with a question about a package or the schedule | An answer from the purchasing team | Pre-bid questions for RP5 were due Oct. 22, 2026 |
| The city's Charlotte Business INClusion program | The City of Charlotte's certification for small, minority and woman owned firms, linked from the builder's resources page | Small, minority and woman owned firms in the Charlotte region | Standing for the city's $179 million diverse-owned requirement | Certification isn't a bid |
| The owner's design team | CAA ICON, the program manager, and HOK, named with the builder | Product reps who get specified | A chance to get a product in the drawings | Neither firm's role in specifying is stated, and RP5's packages are already issued |
Who should go after the Panthers' stadium renovation, and who shouldn't?
| Ceiling, drywall, flooring, tile and paint suppliers | The builder's list names 36 firms under those headings, and finish bids are due Nov. 20, 2026. |
|---|
| Prequalified finish, structural and envelope subcontractors | RP5 bids are due no later than Nov. 20 by 2 pm, through BuildingConnected. |
|---|
| LED display and AV firms | The RP5 slides set an LED videoboard bid due Nov. 13, 2026. |
|---|
| Firms that want an open public bid with no prequalification | This isn't the job for you: it's a private stadium, and only prequalified primes can bid. |
|---|
What should you do next on the Panthers' stadium renovation?
- Open the full list and find your trade's heading on the builder's bidder list.
- Call the firms under that heading this week, before the Nov. 20 deadline.
- If you want to bid as a prime, start the builder's prequalification on its bid portal.
- If you're a small, minority or woman owned firm, look at the city's Charlotte Business INClusion certification.
Questions people ask about the Bank of America Stadium renovation
Who is building the Bank of America Stadium renovation?
Clark/D.A. Everett, a joint venture of Clark Construction Group and Charlotte-based D.A. Everett Construction Group, is the construction manager at risk. The builder's pre-bid slides list Tepper Sports & Entertainment as owner and CAA ICON as program manager.
Who owns Bank of America Stadium?
Tepper Sports & Entertainment, which also owns the Carolina Panthers and Charlotte FC. The City of Charlotte is paying $650 million toward the renovation, approved by the City Council in June 2024.
How much does the Bank of America Stadium renovation cost?
The project grew to $1.3 billion in July 2026, when Tepper Sports & Entertainment raised its share to $650 million from an original $150 million pledge. The City of Charlotte's share is fixed at $650 million. Clark's news page announced it in November 2025 as an $800 million renovation.
When are the next bids due on the Panthers' stadium renovation?
The builder's bid portal says all trade packages for its fifth bid round, RP5, are issued, and all bids are due no later than Nov. 20, 2026. Its pre-bid slides say by 2 pm, and give LED videoboards an earlier date, Nov. 13.
What's in the RP5 bid round?
The RP5 online pre-bid meetings were split into structural and finishes on Oct. 19, 2026, and skin and MEPF, tech and kitchen equipment on Oct. 22. The slides show the trade lines only as pictures, so ask the builder for the exact list. The slides set MEPF bids due Oct. 23, LED videoboards Nov. 13 and all other bids Nov. 20.
How do subcontractors get on the Bank of America Stadium renovation?
All prime subcontractors must be prequalified. The builder's steps are a prequalification initiation form, an up-to-date BuildingConnected and TradeTapp account, then the project team's review. Bids go in through BuildingConnected.
Can a firm that isn't on the prime bidder list still bid?
The builder's pre-bid slide on its bidder list says the list is continuously updated, and that a company not on it should not worry and should still bid. The portal still requires prequalification.
Who is on the builder's prime bidder list?
The public list has 50 trade headings and 377 firm entries, which come to about 238 different firms once spelling variants are merged. Among them, 36 firms sit under drywall and carpentry, ceilings, tile, flooring and painting.
Does the city require local or diverse-owned firms?
WSOC reported that the City Council approved its $650 million with a requirement that 27% of the taxpayer money, $179 million, go to diverse-owned firms. The builder's resources page points firms to the City of Charlotte's Charlotte Business INClusion certification.
When will the renovation be finished?
Work runs in phases between NFL and Major League Soccer seasons through 2030. The builder says interior work is taking place in 2026, with fan-facing elements set to begin in 2027.
What does ATI hold on the stadium?
Mecklenburg County permit COM-GBLD-26-001116, issued Oct. 29, 2026 to Clark Construction Group, LLC for a retaining wall, concrete finishing and pile installation, with a $250,000 cost of construction, plus the county's other permits at 800 S Mint St.
How we built this list
We read the builder's bid portal, its public prime bidder list (firm names only, all 50 headings), its RP5 pre-bid slides, its prequalification form and news posts, Mecklenburg County's permit records for 800 S Mint St, and WSOC and Clark's coverage. A row is on the list only if a record ties it to the stadium. The bidder list has no date, so its rows carry none. We merged spelling variants to count firms, and left off every person's name and email. First published Nov. 8, 2026. We'll update this page when the builder posts RP5 results, a new bid round or a new permit.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 8, 2026- Clark/D.A. Everett, bid portal
- Clark/D.A. Everett, prime bidder list
- Clark/D.A. Everett, RP5 pre-bid meeting slides
- Clark/D.A. Everett, prequalification initiation form
- Clark/D.A. Everett, new renderings post, Aug. 3, 2026
- Clark/D.A. Everett, kickoff recap, Jan. 28, 2026
- Clark/D.A. Everett, small and local business resources
- Clark Construction, Nov. 3, 2025
- WSOC, Jan. 8, 2026
- WSOC, Jan. 28, 2026
- WSOC, July 23, 2026
- Mecklenburg County permit COM-GBLD-26-001116