What is being built at 1010 Church Street in Nashville?
Giarratana is building Paramount Tower at 1010 Church Street in downtown Nashville. The city's permit describes a 750-foot, 60-story building of about 1 million square feet, with 360 apartments and 140 condos. The plans call for 517 parking spaces.
When it is done, it will be the tallest building in Tennessee. It will rise about 133 feet above the AT&T "Batman" Building, which stands about 617 feet.
How much is Paramount Tower?
Giarratana puts the cost at $460 million. In August 2025 it closed a $340 million construction loan from Benefit Street Partners, which cleared the way for work to start on Sept. 15, 2025.
On Nov. 23, 2026, Tony Giarratana said the job is under budget: "We're over a month ahead of schedule, and we're under budget."
The biggest single permit is the shell electrical permit, held by Bonus Electric, with a stated contract value of $25,932,983. Lee Company's 24 plumbing permits list $11,874,075 in stated values and Heatmasters' 19 mechanical and gas permits list $4,750,000, our sums. Each permit value is what was declared to the city, not the full spend.
How far along is Paramount Tower?
Work started in September 2025. On Nov. 23, 2026, crews were on the 37th of 60 floors. They pour about one new floor a week, with work starting around 1 a.m. on Wednesdays. Giarratana expects crews to reach floor 41 by New Year's Eve.
Inside, the lower floors are filling in. Giarratana said that on the 10th floor you can already open the kitchen and bathroom cabinets. Substantial completion is set for May 2028.
Who is building Paramount Tower?
Brasfield & Gorrie is the general contractor. It holds the tower's building permit and the city's street closure permits for the work, and Giarratana credits it for keeping the job ahead of schedule.
The design team is Goettsch Partners (architect), DeSimone Consulting Engineering (structural engineer) and Bala Consulting Engineers (MEP engineer). GTA did the soil study and now tests the concrete and steel on site.
Which trade firms are on Paramount Tower?
The city's trade permits name three big trade firms. Bonus Electric holds 46 electrical permits, from the shell permit to floor-by-floor permits up to levels 32-40. Lee Company holds 24 plumbing permits, and Heatmasters Mechanical holds 19 mechanical and gas permits.
Perimeter Floors is doing the amenity floors' flooring with Brasfield & Gorrie, and Penetron's waterproofing went into every concrete wall of the underground garage. 10 firms in all are on the list below.
Who Giarratana hired before
Giarratana built its Alcove tower at 900 Church Street with the same builder, architect and engineers it hired for Paramount.
- Brasfield & Gorrie: builder on Alcove, Giarratana's residential tower at 900 Church Street, Nashville, TN, 2024. Also on this job.
- Goettsch Partners: architect on Alcove, 900 Church Street, Nashville, TN, 2024. Also on this job.
- DeSimone Consulting Engineering: structural engineer on Alcove, 900 Church Street (NCSEA structural excellence award), and the Prime tower across the street, Nashville, TN, 2024. Also on this job.
- Bala Consulting Engineers: MEP engineer on Alcove, 900 Church Street, Nashville, TN, 2024. Also on this job.
- AECOM Hunt: builder on Alcove, 900 Church Street, Nashville, TN, 2024.
These are earlier or other jobs for the same owner. They are not counted in the 10 firms on this job.
How do the ways into Paramount Tower compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Paramount Tower at 1010 Church Street | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after Paramount Tower?
| Electrical distributors and gear reps | Bonus Electric, with a $25.9 million electrical permit and 46 electrical permits floor by floor, the newest for levels 32-40. |
|---|
| Plumbing, HVAC and mechanical reps | Lee Company on 24 plumbing permits ($11.9 million stated) and Heatmasters Mechanical on 19 mechanical and gas permits ($4.75 million stated). |
|---|
| Interior, concrete and building product suppliers | Brasfield & Gorrie, the general contractor, with interiors now going in on the lower floors; Perimeter Floors on the amenity floors; Penetron in the garage walls. |
|---|
What should you do next on Paramount Tower?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Paramount Tower at 1010 Church Street in downtown Nashville.
- Move soon: the frame rises about one floor a week, and interiors are going in floor by floor behind it.
Questions people ask about Paramount Tower
How much does Paramount Tower in Nashville cost?
Giarratana puts it at $460 million. A $340 million construction loan from Benefit Street Partners cleared the way to start construction in September 2025. The developer said on Nov. 23, 2026 that the job is under budget.
How tall is Paramount Tower?
750 feet and 60 stories. It will be the tallest building in Tennessee, about 133 feet taller than the AT&T "Batman" Building, which stands about 617 feet.
Who is building Paramount Tower in Nashville?
Brasfield & Gorrie is the general contractor. Goettsch Partners is the architect, DeSimone the structural engineer and Bala the MEP engineer. 10 firms are named on the job, listed above.
Who is the electrician on Paramount Tower?
Bonus Electric holds the tower's shell electrical permit, with a stated contract value of $25,932,983, plus 45 more electrical permits floor by floor.
Where is Paramount Tower?
At 1010 Church Street in downtown Nashville, Tennessee, at Church Street, YMCA Way and 10th Avenue North.
How far along is Paramount Tower?
On Nov. 23, 2026, crews were on the 37th of 60 floors. They pour about one floor a week, starting around 1 a.m. on Wednesdays. Giarratana expects floor 41 by New Year's Eve and says the job is over a month ahead of schedule.
When will Paramount Tower be finished?
Substantial completion is set for May 2028.
How many homes are in Paramount Tower?
500: 360 rental apartments and 140 condos, with 517 parking spaces.
Who developed Paramount Tower?
Giarratana, the Nashville developer led by Tony Giarratana. It used the same builder, architect and engineers on its Alcove tower on Church Street.
What happens next on Paramount Tower?
Floors keep rising about one a week, and interiors keep going in on the lower floors. We'll update this page when a new permit or firm appears.
How we built this list
We read Metro Nashville's open building, trade and street permit records for 1010 Church Street, about 91 permits from September 2025 to Oct. 14, 2026, plus FOX 17, The Real Deal and BD+C, and the project pages of GTA, Perimeter Floors and Penetron, all on Nov. 25, 2026. We kept each firm a public record names on this tower. The city's trade permits name a contact on each permit, not a role: the general contractor is Brasfield & Gorrie, per the building team in the trade press and its own building permit, and Bonus Electric is the electrical contractor. The $11.9 million and $4.75 million are our sums of the stated permit values; the $25.9 million electrical figure is repeated on four Bonus permits, so we count it once. The original 2025 building permit is not in the city's open data, and fire sprinkler and alarm permits are not published there. Left out: the developer, the YMCA, the lenders, a crane company seen only in a photo, a utility contractor whose street permits do not name the building, an engineer whose page shows an earlier Paramount design on a different site, and individuals. Phones are each firm's own line from its own site; Bonus Electric and Heatmasters are out-of-state offices, and Goettsch Partners, DeSimone and Bala show no main line we could verify, so we give their websites only. First published Nov. 25, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 25, 2026- FOX 17: Paramount Tower construction ahead of schedule, set to become Tennessee's tallest building (Nov. 23, 2026)
- The Real Deal: Giarratana lands financing for Nashville's tallest tower (Aug. 21, 2025)
- BD+C: At 60 stories, the Paramount multifamily development will stand as Nashville's tallest high rise
- Metro Nashville Codes, Trade Permits (electrical permit 2025084696), read Nov. 25, 2026
- Metro Nashville Codes, Trade Permits (plumbing permit 2025081820), read Nov. 25, 2026
- Metro Nashville Codes, Trade Permits (mechanical permit 2026075391), read Nov. 25, 2026
- Metro Nashville Codes, Building Permits Issued (permit 2026061089), read Nov. 25, 2026
- GTA project page: Paramount Tower/1010 Church
- Perimeter Floors project page: 1010 Church Street Tower
- Penetron project page: 1010 Church Street Tower
- e-architect: Alcove Nashville Residential Tower (2024-11-23)