Who's building Nashville's Paramount Tower

Nashville's $460 million Paramount Tower, set to be Tennessee's tallest building, is at floor 37 of 60 and over a month ahead of schedule.

By Porter Stanley. Updated .

Giarratana is building Paramount Tower, a 750-foot, 60-story condo and apartment tower at 1010 Church Street in downtown Nashville. It will be the tallest building in Tennessee. Giarratana puts the cost at $460 million. On Nov. 23, 2026, crews were on floor 37 of 60, rising about one floor a week and over a month ahead of schedule. Brasfield & Gorrie is the general contractor, and Bonus Electric holds a $25.9 million electrical permit. 10 firms are named on the job; the list below has all 10.

$460MGiarratana's cost for the tower
$25.9MBonus Electric's electrical permit
37 of 60Floor crews reached by Nov. 23, 2026
10Firms named on the job

Get all 10 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 10 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 10 firms on Paramount Tower?

We list the 10 firms named on Nashville's Paramount Tower, one row each, strongest tie first, with what each one does on the job and where its name comes from.

1Permit on the recordJul 23, 2026

Brasfield & Gorrie, LLC

General contractor on the 60-story tower; holds the city building permit on the job and the city's lane and sidewalk closures on Church St and 10th Ave N for the work on Paramount Tower at 1010 Church Street in downtown Nashville, TN

Paramount Tower (1010 Church), 1010 Church St, downtown Nashville (Davidson County), TN

Building permit amendment 2026061089, $500,000, issued July 23, 2026; street closure permits filed Sept. 23, 2026, for closures from October 2026; Giarratana puts the whole project at $460 million

Work: General contractor on the 60-story tower; holds the city building permit on the job and the city's lane and sidewalk closures on Church St and 10th Ave N for the work

Who to call: Brasfield & Gorrie, LLC
Brasfield & Gorrie office line
(Nashville, TN)
(615) 313-2900

The opportunity: Metro Nashville building permit 2026061089 at 1010 Church St lists 'Contact: BRASFIELD & GORRIE LLC'. City street permits name it for 'Construction of 60 story apartment building'. The building team in the trade press reads 'General contractor: Brasfield & Gorrie', and the developer credited Brasfield & Gorrie for keeping work ahead of schedule (Nov. 23, 2026). The original 2025 building permit is not in the city's open data. Brasfield & Gorrie also built Giarratana's Alcove tower.

2Permit on the recordOct 7, 2025

Bonus Electric Construction Company LLC

Electrical contractor: the shell electrical permit for the whole tower, plus 45 more electrical permits for the garage, lobby, amenity floors and apartment levels on Paramount Tower at 1010 Church Street in downtown Nashville, TN

Paramount Tower (1010 Church), 1010 Church St, downtown Nashville (Davidson County), TN

Electrical permit 2025084696, issued Oct. 7, 2025, stated contract value $25,932,983; 46 electrical permits in all, the newest on Oct. 14, 2026 for levels 32-40

Work: Electrical contractor: the shell electrical permit for the whole tower, plus 45 more electrical permits for the garage, lobby, amenity floors and apartment levels

Who to call: Bonus Electric Construction Company LLC
Bonus Electric office line
(Romeoville, IL)
(630) 257-3336

The opportunity: Metro Nashville trade permit 2025084696: 'Contact: BONUS ELECTRIC CONSTRUCTION COMPANY LLC ... Purpose: Shell Permit Only ... Construction of a 750' tall, 60-story building.' The same $25,932,983 is repeated on three other Bonus permits, so we do not add them up. Apartment-floor permits run $200,000 to $250,000 each. Bonus is the electrical contractor, not the general contractor.

3Permit on the recordSep 25, 2025

Lee Company

Plumbing contractor: 24 plumbing permits across the garage, ramp and tower floors, September 2025 to June 2026 on Paramount Tower at 1010 Church Street in downtown Nashville, TN

Paramount Tower (1010 Church), 1010 Church St, downtown Nashville (Davidson County), TN

24 plumbing permits, $11,874,075 in stated values (the sum); the biggest is permit 2025081820, $1,469,000, for the above-grade garage, ramp and levels 2-8M, issued Sept. 25, 2025

Work: Plumbing contractor: 24 plumbing permits across the garage, ramp and tower floors, September 2025 to June 2026

Who to call: Lee Company
Lee Company main line
(615) 567-1000

The opportunity: Metro Nashville trade permit 2025081820: 'Address: 1010 CHURCH ST ... Subdivision_Lot: LOT 2 DOWNTOWN YMCA Contact: LEE COMPANY.'

What is being built at 1010 Church Street in Nashville?

Giarratana is building Paramount Tower at 1010 Church Street in downtown Nashville. The city's permit describes a 750-foot, 60-story building of about 1 million square feet, with 360 apartments and 140 condos. The plans call for 517 parking spaces.

When it is done, it will be the tallest building in Tennessee. It will rise about 133 feet above the AT&T "Batman" Building, which stands about 617 feet.

How much is Paramount Tower?

Giarratana puts the cost at $460 million. In August 2025 it closed a $340 million construction loan from Benefit Street Partners, which cleared the way for work to start on Sept. 15, 2025.

On Nov. 23, 2026, Tony Giarratana said the job is under budget: "We're over a month ahead of schedule, and we're under budget."

The biggest single permit is the shell electrical permit, held by Bonus Electric, with a stated contract value of $25,932,983. Lee Company's 24 plumbing permits list $11,874,075 in stated values and Heatmasters' 19 mechanical and gas permits list $4,750,000, our sums. Each permit value is what was declared to the city, not the full spend.

How far along is Paramount Tower?

Work started in September 2025. On Nov. 23, 2026, crews were on the 37th of 60 floors. They pour about one new floor a week, with work starting around 1 a.m. on Wednesdays. Giarratana expects crews to reach floor 41 by New Year's Eve.

Inside, the lower floors are filling in. Giarratana said that on the 10th floor you can already open the kitchen and bathroom cabinets. Substantial completion is set for May 2028.

Who is building Paramount Tower?

Brasfield & Gorrie is the general contractor. It holds the tower's building permit and the city's street closure permits for the work, and Giarratana credits it for keeping the job ahead of schedule.

The design team is Goettsch Partners (architect), DeSimone Consulting Engineering (structural engineer) and Bala Consulting Engineers (MEP engineer). GTA did the soil study and now tests the concrete and steel on site.

Which trade firms are on Paramount Tower?

The city's trade permits name three big trade firms. Bonus Electric holds 46 electrical permits, from the shell permit to floor-by-floor permits up to levels 32-40. Lee Company holds 24 plumbing permits, and Heatmasters Mechanical holds 19 mechanical and gas permits.

Perimeter Floors is doing the amenity floors' flooring with Brasfield & Gorrie, and Penetron's waterproofing went into every concrete wall of the underground garage. 10 firms in all are on the list below.

Who Giarratana hired before

Giarratana built its Alcove tower at 900 Church Street with the same builder, architect and engineers it hired for Paramount.

  • Brasfield & Gorrie: builder on Alcove, Giarratana's residential tower at 900 Church Street, Nashville, TN, 2024. Also on this job.
  • Goettsch Partners: architect on Alcove, 900 Church Street, Nashville, TN, 2024. Also on this job.
  • DeSimone Consulting Engineering: structural engineer on Alcove, 900 Church Street (NCSEA structural excellence award), and the Prime tower across the street, Nashville, TN, 2024. Also on this job.
  • Bala Consulting Engineers: MEP engineer on Alcove, 900 Church Street, Nashville, TN, 2024. Also on this job.
  • AECOM Hunt: builder on Alcove, 900 Church Street, Nashville, TN, 2024.

These are earlier or other jobs for the same owner. They are not counted in the 10 firms on this job.

How do the ways into Paramount Tower compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on Paramount Tower at 1010 Church StreetEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell

Who should go after Paramount Tower?

Electrical distributors and gear repsBonus Electric, with a $25.9 million electrical permit and 46 electrical permits floor by floor, the newest for levels 32-40.
Plumbing, HVAC and mechanical repsLee Company on 24 plumbing permits ($11.9 million stated) and Heatmasters Mechanical on 19 mechanical and gas permits ($4.75 million stated).
Interior, concrete and building product suppliersBrasfield & Gorrie, the general contractor, with interiors now going in on the lower floors; Perimeter Floors on the amenity floors; Penetron in the garage walls.

What should you do next on Paramount Tower?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on Paramount Tower at 1010 Church Street in downtown Nashville.
  3. Move soon: the frame rises about one floor a week, and interiors are going in floor by floor behind it.

Questions people ask about Paramount Tower

How much does Paramount Tower in Nashville cost?

Giarratana puts it at $460 million. A $340 million construction loan from Benefit Street Partners cleared the way to start construction in September 2025. The developer said on Nov. 23, 2026 that the job is under budget.

How tall is Paramount Tower?

750 feet and 60 stories. It will be the tallest building in Tennessee, about 133 feet taller than the AT&T "Batman" Building, which stands about 617 feet.

Who is building Paramount Tower in Nashville?

Brasfield & Gorrie is the general contractor. Goettsch Partners is the architect, DeSimone the structural engineer and Bala the MEP engineer. 10 firms are named on the job, listed above.

Who is the electrician on Paramount Tower?

Bonus Electric holds the tower's shell electrical permit, with a stated contract value of $25,932,983, plus 45 more electrical permits floor by floor.

Where is Paramount Tower?

At 1010 Church Street in downtown Nashville, Tennessee, at Church Street, YMCA Way and 10th Avenue North.

How far along is Paramount Tower?

On Nov. 23, 2026, crews were on the 37th of 60 floors. They pour about one floor a week, starting around 1 a.m. on Wednesdays. Giarratana expects floor 41 by New Year's Eve and says the job is over a month ahead of schedule.

When will Paramount Tower be finished?

Substantial completion is set for May 2028.

How many homes are in Paramount Tower?

500: 360 rental apartments and 140 condos, with 517 parking spaces.

Who developed Paramount Tower?

Giarratana, the Nashville developer led by Tony Giarratana. It used the same builder, architect and engineers on its Alcove tower on Church Street.

What happens next on Paramount Tower?

Floors keep rising about one a week, and interiors keep going in on the lower floors. We'll update this page when a new permit or firm appears.

How we built this list

We read Metro Nashville's open building, trade and street permit records for 1010 Church Street, about 91 permits from September 2025 to Oct. 14, 2026, plus FOX 17, The Real Deal and BD+C, and the project pages of GTA, Perimeter Floors and Penetron, all on Nov. 25, 2026. We kept each firm a public record names on this tower. The city's trade permits name a contact on each permit, not a role: the general contractor is Brasfield & Gorrie, per the building team in the trade press and its own building permit, and Bonus Electric is the electrical contractor. The $11.9 million and $4.75 million are our sums of the stated permit values; the $25.9 million electrical figure is repeated on four Bonus permits, so we count it once. The original 2025 building permit is not in the city's open data, and fire sprinkler and alarm permits are not published there. Left out: the developer, the YMCA, the lenders, a crane company seen only in a photo, a utility contractor whose street permits do not name the building, an engineer whose page shows an earlier Paramount design on a different site, and individuals. Phones are each firm's own line from its own site; Bonus Electric and Heatmasters are out-of-state offices, and Goettsch Partners, DeSimone and Bala show no main line we could verify, so we give their websites only. First published Nov. 25, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 10 firms, free

All 10 firms on Paramount Tower

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.