What is Amtrak doing to Philadelphia's 30th Street Station?
Amtrak is restoring and modernizing the William H. Gray III 30th Street Station at 2955 Market Street in Philadelphia. The eight-story station opened in 1933 and is Amtrak's third-busiest: more than 5 million Amtrak passengers got on or off there in fiscal 2025. The job covers nearly 500,000 square feet of renovation.
The work restores the main hall, turns the station's west corridor into a food hall, and makes levels two to five into Amtrak offices. It also upgrades The Porch outside, new elevators and escalators, and the building's systems. Crews have built new electrical substations. The project estimates about 3,000 direct and indirect jobs.
SOM said: "We are preserving its historic character while positioning the station for the next generation of travelers to come."
How much does the 30th Street Station renovation cost?
Amtrak puts the job's estimated capital construction value at $550 million, a figure it gave at the start of construction in January 2024. The Nov. 13, 2026 opening announcement again put the capital investment at about $550 million, with completion by the end of 2028. The cost has grown since the start, and we found no new total.
The $6.5 billion figure often tied to the station is a different scope: the 2016 30th Street Station District Plan, a 35-year plan for about 175 acres next to the station, with about $2 billion of public work and $4.5 billion of private building. This station job is that plan's first phase.
Why did the 30th Street Station South Concourse take so long?
The South Concourse closed for construction on Jan. 1, 2024. Amtrak said then it would reopen in summer 2025. By late January 2024, the whole job's finish had already moved from 2025 to 2027; Amtrak blamed adding its corporate offices and "other market factors."
The South Concourse officially reopened with a ribbon cutting on Nov. 13, 2026, nearly three years after it closed. It has new seating, bathrooms and 15 spaces for shops and food, and Amtrak expects most of them filled by the end of 2027. U.S. Rep. Mary Gay Scanlon called it "a historic transformation of one of our city's most iconic buildings."
The work is not done. The North Concourse closes to the public from November 2026, and construction across the station is now expected to run through 2028.
Who is building 30th Street Station?
Amtrak picked Plenary Infrastructure Philadelphia (PIP) as master developer. Under a 50-year public-private partnership signed in 2021, PIP designs, builds, finances, operates and maintains the station improvements. Plenary Americas, LP is the equity sponsor.
Inside PIP, Gilbane Building Company is the design-build lead and broke ground in 2024, with Skidmore, Owings & Merrill (SOM) as architect and design partner. Johnson Controls runs facility operations and maintenance, and Vantage Group handles the shops and food.
SOM lists 13 more firms among the project's collaborators, from engineers to lighting, signage and historic preservation designers. NELSON Worldwide designed the new retail and restaurants, and Urban Engineers applied for the zoning permit for a freestanding canopy.
Which contractors hold city permits at 30th Street Station?
Philadelphia issued 18 permits at the station's permit address, 1 N 30th St, from April 6 to Nov. 11, 2026, all naming Amtrak as owner. They name 14 firms: 5 building, 5 electrical, 2 mechanical, 2 plumbing, 2 fire sprinkler, 1 site and 1 zoning permit (the count). The city publishes no dollar values on them. Seven more filings were in review, ready to issue or in draft when we read the data.
Most are shop and restaurant fit-outs in the concourses. Gilbane holds the sitework permit and the Dunkin fit-out, with Aerdux, Madden Electric, TKelly and Oliver Sprinkler on its trade permits. Intech Construction built the Starbucks kiosk, with New Light Electric and Keegan & Cunnius. Russ Kelly & Associates holds two shop fit-outs, with Whitemarsh Electrical and H&W Mechanical.
The newest permit, issued Nov. 11, 2026, two days before the ribbon cutting, names Ridge Construction Corp for alterations with partial demolition, new walls, finishes and accessibility work. 30 firms in all are on the list below.
Who built Amtrak's other Northeast rail jobs
SOM, the architect here, also designed New York's Moynihan Train Hall, which Skanska built for Amtrak and Long Island Rail Road riders. Skanska and Traylor Bros. just finished the Portal North Bridge in New Jersey, and Plenary's last big Pennsylvania deal rebuilt 558 bridges.
- Skidmore, Owings & Merrill (SOM): architect on Moynihan Train Hall (client Empire State Development), New York, NY, 2021. Also on this job.
- Skanska: general contractor on the $1.6 billion Moynihan Train Hall, for LIRR and Amtrak passengers, New York, NY, 2021.
- Skanska and Traylor Bros. joint venture: builder on the $1.6 billion Portal North Bridge over the Hackensack River, New Jersey, 2026.
- Plenary Walsh Keystone Partners: development entity, maintaining the bridges until the end of 2042 on PennDOT's Rapid Bridge Replacement, 558 bridges (a P3), Pennsylvania, 2020.
These are earlier or other jobs for the same owner. They are not counted in the 30 firms on this job.
How do the ways into the 30th Street Station job compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on 30th Street Station in Philadelphia | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The shop and food spaces still to open | A place on the fit-out of one of the 15 South Concourse spaces | Fit-out builders, electricians, plumbers and finish suppliers | Work on spaces Amtrak expects mostly filled by the end of 2027 | Each fit-out picks its own builder and trades, space by space |
Who should go after the 30th Street Station job?
| Electrical and low-voltage distributors | Palman, Madden, Whitemarsh and New Light on the station's wiring, cameras, lighting and fire alarm permits, in a job that built new electrical substations. |
|---|
| Plumbing, HVAC and fire sprinkler reps | Aerdux on kitchen hoods and ductwork, H&W Mechanical, TKelly and Keegan & Cunnius on plumbing and gas, and Oliver Sprinkler on the sprinkler work. |
|---|
| Fit-out builders and finish suppliers | Gilbane, Ridge, Intech and Russ Kelly on the concourse fit-outs, with 15 shop and food spaces to fill by the end of 2027. |
|---|
What should you do next on the 30th Street Station job?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Amtrak's 30th Street Station redevelopment in Philadelphia.
- Watch for new city permits at 1 N 30th St as the shop and food spaces are fitted out and the North Concourse work starts.
Questions people ask about the 30th Street Station renovation
How much does the 30th Street Station renovation cost?
Amtrak puts the job's estimated capital construction value at $550 million, and the Nov. 13, 2026 opening announcement again put it at about $550 million. The cost has grown since the start, and we found no new total.
Is 30th Street Station a $6.5 billion project?
No. The $6.5 billion is the 2016 30th Street Station District Plan, a 35-year plan for about 175 acres next to the station, with about $2 billion of public work and $4.5 billion of private building. The station job is its first phase, at $550 million.
When did the 30th Street Station South Concourse reopen?
It officially reopened with a ribbon cutting on Nov. 13, 2026. It closed on Jan. 1, 2024, and Amtrak had said it would reopen in summer 2025.
Who is building the 30th Street Station renovation?
Gilbane Building Company is the design-build lead, with Skidmore, Owings & Merrill (SOM) as architect and design partner. They work within Plenary Infrastructure Philadelphia, Amtrak's master developer. 30 firms are named on the job, listed above.
What is Plenary's role at 30th Street Station?
Plenary Infrastructure Philadelphia is the master developer. Under a 50-year public-private partnership with Amtrak, it designs, builds, finances, operates and maintains the station improvements. Johnson Controls runs facility operations and maintenance and Vantage Group runs the shops and food.
When will the 30th Street Station work be finished?
Construction is now expected to run through 2028. In 2024 Amtrak said 2027, and the first plan said 2025. The North Concourse closes to the public from November 2026.
What is in the new South Concourse?
New seating, bathrooms and 15 spaces for shops and food. Amtrak expects most of the 15 spaces to be filled by the end of 2027. Crews also put in new elevators and escalators and built new electrical substations.
Which contractors hold permits at 30th Street Station?
Philadelphia issued 18 permits at the station from April 6 to Nov. 11, 2026, naming 14 firms. The newest, on Nov. 11, names Ridge Construction Corp. Most are shop and restaurant fit-outs, like Dunkin and Starbucks, and the city publishes no dollar values.
How big is the 30th Street Station renovation?
Nearly 500,000 square feet of renovation in the eight-story station, which opened in 1933. It is Amtrak's third-busiest station: more than 5 million Amtrak passengers got on or off there in fiscal 2025.
How can subcontractors get work at 30th Street Station?
Call the firms already on the job, starting with Gilbane for the main work. Each shop and food space gets its own fit-out with its own builder and trade permits, so the fit-out builders, electricians and plumbers on the list are a way in too.
What happens next at 30th Street Station?
The North Concourse closes from November 2026, more shop and food openings are planned for 2027, and the work runs through 2028. We'll update this page when a new permit or firm appears.
How we built this list
We read Amtrak's 2024 release, the project site, SOM's project page, the 2026 news on the South Concourse opening and the 2024 schedule change, and Philadelphia's open permit data for 1 N 30th St (owner Amtrak), all on Nov. 24, 2026. We kept each firm a public record names on this job. Five come from Amtrak and the news, 14 from the city's 2026 permits (Gilbane is also among the five, and Urban Engineers is also on SOM's list), and 12 only from SOM's list of project collaborators, which names firms but not their roles, so each of those rows gives the firm's line of work. The permit counts are ours. The city's permits carry no dollar values, so we give no permit sum. Left out: Amtrak (the owner), Plenary Americas as a second row (counted once with PIP), the shop and restaurant tenants, the 2016 district plan's partners, the original 1930s architect, one SOM collaborator we could not identify, and the firms on 2017 to 2019 permits before this program. Phones are each firm's own line from its own site; AECOM's is its Dallas headquarters, Plenary's is its Denver office and Jensen Hughes's is its Baltimore office. Gilbane's site lists no phone for its Philadelphia office, so its line is from Gilbane's own 2021 Philadelphia report. SOM and Johnson Controls show no main line on their sites, Vantage lists no US main line, TKelly's and Michael Blades's sites show no phone, and we found no website of their own for Aerdux, Russ Kelly, Madden, Whitemarsh, New Light, H&W and Keegan & Cunnius, so we give no phone for those. First published Nov. 24, 2026. We'll update this page when a new permit, contract or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 24, 2026- Construction Dive: Amtrak, Gilbane open Philadelphia concourse as part of $550M update (Nov. 20, 2026)
- Philadelphia Inquirer: 30th Street Station south concourse is open (Nov. 16, 2026)
- Dezeen: SOM's 30th Street Station South Concourse (Nov. 17, 2026)
- Amtrak: construction kicks off at William H. Gray III 30th Street Station (Jan. 19, 2024)
- ENR: $550M Philadelphia Amtrak station upgrade has new timeline (Jan. 29, 2024)
- Amtrak: Pennsylvania state fact sheet, fiscal year 2025
- Vantage Group: Amtrak celebrates major milestones at Gray 30th Street Station (Nov. 13, 2026)
- William H. Gray III 30th Street Station project site (read Nov. 24, 2026)
- SOM: William H. Gray III 30th Street Station Redevelopment project page (read Nov. 24, 2026)
- City of Philadelphia L&I permits at 1 N 30th St, open data (read Nov. 24, 2026)
- Planetizen: plans released for $6.5 billion development in Philadelphia (2016)
- Philadelphia Inquirer: $6.5B price tag for 35-year University City overhaul (June 16, 2016)
- SOM: Moynihan Train Hall project page
- Skanska release, 2021
- PennDOT: Rapid Bridge Replacement Project