What did NJ TRANSIT and Amtrak build over the Hackensack?
The Portal North Bridge carries Amtrak and NJ TRANSIT trains over the Hackensack River between Kearny and Secaucus, on the line into New York's Penn Station. It replaces the Portal Bridge, a swing bridge in service since 1910. That bridge turns open to let boats pass and then has to close again for trains. Amtrak said it had trouble closing it 15% of the time in 2017, and when it got stuck in October 2018, trains ran up to 90 minutes late in the evening rush (ABC7).
The new bridge sits 50 feet over the river, so boats pass without stopping the trains (Amtrak). Its three 400-foot steel arches, about 2,900 tons each, were put together 150 miles away at the Port of Coeymans near Albany and floated down the Hudson, the first in November 2024 and the last in February 2025 (Genesis Structures). Amtrak and NJ TRANSIT say the job took about 23,000 tons of steel and 219,000 cubic yards of concrete.
The first track opened March 13, 2026. After a five-week switch-over, both tracks went into full service on Nov. 16, 2026. "The cutover is complete, and Portal North Bridge is ready to deliver," Amtrak's interim president said. The old swing bridge is retired and is set to come down in 2027.
Where does the $1.8 billion go?
ENR puts the total project at $1.8 billion. The biggest piece is the building contract: $1,559,993,000 to the Skanska and Traylor Bros. joint venture, the largest single construction award in NJ TRANSIT's history (Amtrak; NJ TRANSIT). Skanska says its share is $1.09 billion. The rest pays for design, construction management and the early work.
The money came from several places. The Federal Transit Administration signed a $766.5 million grant in January 2021 (Construction Equipment Guide), and New Jersey and Amtrak paid much of the rest. No one has published a split of the money by trade, so we do not estimate one here.
Which firms are on the job?
Skanska and Traylor Bros. hold the building contract: the walls, the deep foundations, the piers, the three steel arches, the track and signal systems, and taking down the old bridge (Skanska). HNTB, Jacobs and Gannett Fleming designed it as Portal Partners, with PACO Group helping them. AECOM and STV manage and inspect the building for NJ TRANSIT.
Under the builders, Malcolm Drilling put in the deep drilled shafts, Genesis Structures planned how to lift the arches, Mammoet jacked them into place, and Carver Marine's barges and tugs carried them down the Hudson. Skanska worked with VSL on the arches' cable ends, and PKF-Mark III did an early $14.5 million contract from 2017 to 2019.
Daidone Electric holds the electrical work, with Martin Electric running conduit for the overhead power, fiber and arch lighting. AEIS, JPCL Engineering and Muñoz Engineering handle inspection, quality control and survey for the builders, Geoquest designed the T-Wall retaining walls, and McDonough Marine's barges also carried the arches. Hill International and Gall Zeidler support Amtrak, and Jois Construction Management works on project controls for NJ TRANSIT. 28 firms in all are on the list below.
How do the ways into the Portal North Bridge compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Portal North Bridge | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Portal North Bridge?
| Steel, concrete and foundation suppliers | Skanska, Traylor Bros. and Malcolm Drilling, on a job that used about 23,000 tons of steel and 219,000 cubic yards of concrete. |
|---|
| Rail, signal and power reps | The Skanska/Traylor joint venture, whose contract covers the track, overhead power and signal systems, and Daidone Electric, its electrical contractor. |
|---|
| Heavy lift, marine and demolition firms | Mammoet, Carver Marine and the crews taking down the old swing bridge in 2027. |
|---|
What should you do next on the Portal North Bridge?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the Portal North Bridge.
Questions people ask about the Portal North Bridge
How much did the Portal North Bridge cost?
ENR puts the total project at $1.8 billion. The building contract alone is $1,559,993,000, awarded to a Skanska and Traylor Bros. joint venture in October 2021.
Who built the Portal North Bridge?
The Skanska/Traylor Bros PNB Joint Venture built it for NJ TRANSIT and Amtrak. HNTB, Jacobs and Gannett Fleming designed it, and AECOM and STV manage the building. 28 firms are named in all, listed above.
When did the new Portal Bridge open?
The first track opened March 13, 2026, and both tracks went into full service on Nov. 16, 2026 (Amtrak; NJ TRANSIT).
What happens to the old Portal Bridge?
The 116-year-old swing bridge is retired and is set to come down in 2027. Skanska's contract covers taking it down, and STV manages that work.
Why was the old Portal Bridge a problem?
It swings open for boats and has to close again for trains. Amtrak said it had trouble closing it 15% of the time in 2017, and a stuck bridge in October 2018 left trains up to 90 minutes late (ABC7).
How we built this list
This is a state and federal rail job, so no city permits name its firms. We read NJ TRANSIT's and Amtrak's releases, ENR, Railway Technology, Construction Equipment Guide, Breakbulk News and each firm's own project page, and kept every firm an opened source ties to this bridge (read Nov. 17, 2026). PKF-Mark III's early contract ended in 2019. Daidone Electric and Martin Electric are the only electrical firms a source names; no signal or traction power installer or arch steel maker is named. Skanska names only "VSL"; we list it under Structural Technologies, which runs VSL in the US. The cost is ENR's total-project figure; no one has published a split by trade, so we do not estimate one. Phones are each firm's own office line; we found none for Gannett Fleming, Mammoet or Aerix Industries. First published Nov. 18, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 18, 2026- ENR: invitations to bid go out for $1.8 billion NJ Portal Bridge replacement (Jan. 15, 2021)
- ENR: Skanska/Traylor JV tapped for $1.6B NJ bridge replacement (Oct. 13, 2021)
- Amtrak and NJ TRANSIT: Portal North Bridge enters full service (Nov. 16, 2026)
- NJ TRANSIT: Portal North Bridge enters full service (Nov. 16, 2026)
- Skanska: Skanska builds the Portal North Bridge replacement for USD 1.09B (Jan. 10, 2022)
- Construction Equipment Guide: Portal North Bridge nears completion (April 30, 2026)
- ABC7: stuck Portal Bridge causes big NJ Transit mess (Oct. 31, 2018)
- Genesis Structures: Portal North Bridge erection (2025)
- Skanska: behind the delivery of three bridge arches down the Hudson River
- Railway Technology: Portal North Bridge replacement (Oct. 27, 2017)