Who's building the Navy's new dry docks in Kittery, Maine

Kittery, Maine's new Navy submarine dry dock was awarded at $1.73 billion, and the Navy now wants $2.46 billion and a May 2029 finish.

By Porter Stanley. Updated .

The U.S. Navy is building two new submarine dry docks at Portsmouth Naval Shipyard in Kittery, Maine, a project called P-381. It awarded the construction contract to 381 Constructors, a joint venture of Cianbro, TIC (a Kiewit company) and Middlesex, at $1.73 billion on Aug. 13, 2021. Federal records now show $1.82 billion obligated. A September 2026 federal audit report says the Navy now asks for $2.46 billion for the project, and expects the work to finish in May 2029; the 2021 award set June 2028. 18 firms are named on the job; the list below has all 18.

$1.82BObligated on the Navy contract (July 2026)
$2.46BWhat the Navy now asks for
27Concrete blocks, about 4,000 tons each
18Firms named on the job

Get all 18 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 18 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 18 firms on the Portsmouth dry dock?

We list the 18 firms named on the Navy's P-381 dry dock at Portsmouth Naval Shipyard, one row each, strongest tie first, with what each one does on the job and where its name comes from.

1Latest recordMay 17, 2024

Cianbro Corporation

Partner in 381 Constructors, the prime contractor; casts the 27 precast dry dock blocks at its Brewer, Maine yard and barges them to the shipyard on the Navy's P-381 dry dock at Portsmouth Naval Shipyard in Kittery, Maine

P-381 Multi-Mission Dry Dock #1, Portsmouth Naval Shipyard, Kittery (York County), ME

Prime contract N40085-21-C-0077 to 381 Constructors, $1,731,477,644 at award (Aug. 13, 2021), $1.82 billion obligated through July 2026; for the whole joint venture, not one firm's share

Work: Partner in 381 Constructors, the prime contractor; casts the 27 precast dry dock blocks at its Brewer, Maine yard and barges them to the shipyard

Who to call: Cianbro Corporation
Cianbro Corporation office line
(Pittsfield, ME)
(207) 487-3311

The opportunity: The project site says: '381 Constructors, a joint venture between Cianbro, TIC and Middlesex Corporation.' A Navy release of May 17, 2024 says the first of 27 concrete monoliths arrived on May 16 on a specialty barge from Cianbro Corporation's Modular Manufacturing Facility in Brewer, Maine. Cianbro also holds its own subawards on the job (temporary casing bracing, berthing), and its affiliate Cianbro Fabrication and Coating supplied bearing plates and crane mats. The phone is the Pittsfield headquarters.

2Latest recordAug 13, 2021

TIC - The Industrial Company (Kiewit)

Partner in 381 Constructors, the prime contractor; TIC is a Kiewit company, and the prime's federal record lists Kiewit's Omaha headquarters as its address on the Navy's P-381 dry dock at Portsmouth Naval Shipyard in Kittery, Maine

P-381 Multi-Mission Dry Dock #1, Portsmouth Naval Shipyard, Kittery (York County), ME

Prime contract N40085-21-C-0077 to 381 Constructors, $1,731,477,644 at award (Aug. 13, 2021), $1.82 billion obligated through July 2026; for the whole joint venture, not one firm's share

Work: Partner in 381 Constructors, the prime contractor; TIC is a Kiewit company, and the prime's federal record lists Kiewit's Omaha headquarters as its address

Who to call: TIC - The Industrial Company (Kiewit)
TIC Denver office line
(Lone Tree, CO)
(720) 920-4200

The opportunity: ENR, August 2021: 381 Constructors is a joint venture of The Industrial Company (TIC), a Kiewit Corp. subsidiary, with Maine-based Cianbro Corp. and The Middlesex Corp. The prime award's recipient address is 3555 Farnam St, Omaha, Kiewit's headquarters. The phone is TIC's Denver office, from the locations page on TIC's own site; which TIC office runs the job is not stated.

3Latest recordAug 13, 2021

The Middlesex Corporation

Partner in 381 Constructors, the prime contractor; lists the two new dry docks on its own project page on the Navy's P-381 dry dock at Portsmouth Naval Shipyard in Kittery, Maine

P-381 Multi-Mission Dry Dock #1, Portsmouth Naval Shipyard, Kittery (York County), ME

Prime contract N40085-21-C-0077 to 381 Constructors, $1,731,477,644 at award (Aug. 13, 2021), $1.82 billion obligated through July 2026; for the whole joint venture, not one firm's share

Work: Partner in 381 Constructors, the prime contractor; lists the two new dry docks on its own project page

Who to call: The Middlesex Corporation
Middlesex Corporation office line
(Littleton, MA)
(978) 742-4400

The opportunity: Middlesex's project page: 'The Middlesex Corporation, as part of a joint venture with The Industrial Company and Cianbro Corporation, is constructing two new drydocks at the historic Portsmouth Naval Shipyard.' ENR named it in the venture at the August 2021 award. The phone is the Littleton headquarters.

What is the Navy building at Portsmouth Naval Shipyard in Kittery?

The U.S. Navy is building two new dry docks at Portsmouth Naval Shipyard, on Seavey Island in Kittery, Maine. The project is called P-381 Multi-Mission Dry Dock #1. The new docks, #1 North and #1 West, sit beside the old Dry Dock #1 and will hold Virginia-class nuclear attack submarines.

The job also builds a pump station, a utility building and electrical facilities. It is part of the Navy's Shipyard Infrastructure Optimization Program.

How much does the Portsmouth Naval Shipyard dry dock cost?

The Navy awarded the construction contract at $1,731,477,644 on Aug. 13, 2021. Federal records show $1,822,402,355 obligated through a change dated July 10, 2026. That includes a $44.6 million funding action on Feb. 27, 2026.

A September 2026 federal audit report says the Navy now asks for $2.46 billion for the project. That figure covers the whole project, not only the construction contract. The same report puts the finish at May 2029, almost a year after the June 2028 date set in 2021.

Who is building the Portsmouth Naval Shipyard dry dock?

381 Constructors holds the prime contract, N40085-21-C-0077. It is a joint venture of three builders: Cianbro Corporation of Pittsfield, Maine, The Industrial Company (TIC), a Kiewit company based in Omaha, and The Middlesex Corporation of Littleton, Massachusetts.

Cianbro casts the dock's concrete blocks at its Modular Manufacturing Facility in Brewer, Maine. The contract value is for the whole joint venture, not one firm's share.

How are the dry dock's concrete blocks built and moved?

The docks are built from 27 precast concrete blocks, called monoliths, of about 4,000 tons each. They are cast in Brewer and floated to Kittery by barge. The first one arrived on May 16, 2024.

The biggest subcontract on the job is rebar: $80,550,334 to Dimension Fabricators of Glenville, New York, reported March 7, 2022. Conrad Shipyard built the deck barges for $13.8 million. Mammoet holds a $28 million heavy lift subcontract, and PERI supplies wall formwork.

Which trades work on the dry dock's pump station and utility building?

The Jamar Company holds an $8.8 million subcontract for plumbing and HVAC in the utility building. Cascade Pump Company holds $6 million for three dewatering pumps and motors. ibcontrols, a Maine firm, holds about $5.2 million for HVAC controls, with its newest report on April 28, 2026.

Consolidated Electrical Distributors supplies switchgear, transformers, load centers and light fixtures, about $11.1 million across 11 reports. Milton CAT supplied generators and load centers. In all, 867 subcontract reports worth about $457 million are on file.

What is the newest work on the Portsmouth Naval Shipyard dry dock?

The Navy's newest contract changes, in June and July 2026, cover conduit for the dewatering pumps and pumpwell doors. The newest, dated July 10, 2026, reroutes the dewatering pump conduit.

On Nov. 12, 2026, the National Commission on the Future of the Navy toured the dry dock site. Navy leaders also visited on Jan. 29 and July 24, 2026. Photos from the November tour show the dock under construction.

How do the ways into the Portsmouth dry dock compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on the P-381 dry dock at Portsmouth Naval ShipyardEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell
381 Constructors' subcontractsA subcontract or purchase order from the prime contractor's venture partnersTrades and suppliers with Navy or marine workA share of a job with $457 million in subcontracts reported so farWork on a Navy shipyard has its own access and security rules

Who should go after the Portsmouth dry dock?

Concrete, rebar and steel suppliersDimension Fabricators on the $80.6 million rebar subcontract, Owen J. Folsom and Redimix on concrete, Skyline Steel on shaft casing and PERI on formwork, with Cianbro casting the blocks.
Electrical, pump and HVAC repsConsolidated Electrical Distributors on switchgear and transformers, Milton CAT on generators, Cascade Pump on the dewatering pumps, and Jamar and ibcontrols in the pump station and utility building.
Marine and heavy lift firmsUnderwater Construction Corporation on diving, Mammoet on heavy lift and Conrad Shipyard on the deck barges.

What should you do next on the Portsmouth dry dock?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on the P-381 Multi-Mission Dry Dock at Portsmouth Naval Shipyard in Kittery, Maine.
  3. Watch for new subcontract reports on the Navy contract; the newest were filed in June 2026.

Questions people ask about the Portsmouth dry dock

How much does the Portsmouth Naval Shipyard dry dock cost?

The Navy awarded the construction contract at $1,731,477,644 in August 2021. Federal records show $1.82 billion obligated through July 2026. A September 2026 federal audit report says the Navy now asks for $2.46 billion for the whole project.

Who is building the Portsmouth Naval Shipyard dry dock?

381 Constructors, a joint venture of Cianbro Corporation, The Industrial Company (TIC, a Kiewit company) and The Middlesex Corporation, holds the prime contract. 18 firms are named on the job, listed above.

When will the Portsmouth dry dock be finished?

A September 2026 federal audit report puts the finish at May 2029. When the contract was awarded in 2021, the work was due in June 2028.

Who is the general contractor on the P-381 dry dock?

381 Constructors is the prime contractor, under Navy contract N40085-21-C-0077. Its federal record lists Kiewit's Omaha headquarters as its address.

How can subcontractors get on the Portsmouth dry dock?

Call the firms already on the job, starting with the three venture partners: Cianbro, TIC and Middlesex. The prime contractor has filed 867 subcontract reports so far, and new ones were still reported in 2026.

What is being bought for the Portsmouth dry dock?

Rebar ($80.6 million to Dimension Fabricators), heavy lift ($28 million to Mammoet), deck barges ($13.8 million to Conrad Shipyard), concrete, electrical gear, steel casing, dewatering pumps, formwork and HVAC work.

How big is the Portsmouth dry dock project?

It builds two new dry docks for Virginia-class submarines from 27 concrete blocks of about 4,000 tons each, plus a pump station and a utility building.

Where are the dry dock's concrete blocks made?

Cianbro casts them at its Modular Manufacturing Facility in Brewer, Maine. Each block is barged to the shipyard in Kittery. The first arrived on May 16, 2024.

Why did the Portsmouth dry dock cost go up?

The Navy's request rose to $2.46 billion, per a September 2026 federal audit report, and the expected finish is now May 2029. We found no single stated reason for the increase in what we read.

Who owns the Portsmouth dry dock project?

The U.S. Navy, through Naval Facilities Engineering Systems Command (NAVFAC). It is part of the Navy's Shipyard Infrastructure Optimization Program.

What happens next on the Portsmouth dry dock?

Work runs toward a May 2029 finish. The newest contract changes, in mid-2026, cover the dewatering pump conduit and pumpwell doors. We'll update this page when a new contract or firm appears.

How we built this list

We read the Navy prime contract N40085-21-C-0077 and its 867 subaward reports on USAspending, the 2021 contract announcement, NAVFAC and Portsmouth Naval Shipyard releases and photos, ENR's August 2021 and September 2026 reports, and the venture's and Middlesex's own pages, all on Nov. 20, 2026. We kept the three venture partners and 15 subcontractors whose subaward line states their work on this job, biggest tie first. Subaward amounts are what the prime contractor reported, and some firms filed several reports. Contract values for the joint venture are for the whole team, not one firm's share. Left out: the Navy as owner, a rebar installer we could not reach by phone or website, a jet grouting firm we could not pin to one company, a Kiewit foundations affiliate (to avoid counting Kiewit twice), material, fuel and rental suppliers, temporary staffing firms, testing and consulting firms, waste haulers, and equipment and tooling suppliers. Phones are each firm's own line from its own site where it shows one. The lines for Mammoet and Jamar come from outside listings because their own sites show none or refused our read, and that CED's Maine branch, CED Yankee, serves the job is the reading. First published Nov. 20, 2026. We'll update this page when a new contract, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports