Who's building QTS's $10 billion data center campus in Cedar Rapids

Cedar Rapids issued a $168 million electrical permit last week on QTS's $10 billion data center, the biggest project in the city's history.

By Porter Stanley. Updated .

QTS, owned by Blackstone, is building seven data center buildings on 612 acres in Cedar Rapids' Big Cedar Industrial Center, a project QTS has said will reach $10 billion over its development, among the largest in Iowa history and the largest in Cedar Rapids history. Weitz and Layton build the campus in a joint venture, and the city is now issuing the data-hall fit-out permits: $756 million stated on 23 permits since July 2026, the biggest a $168 million electrical permit to MMR issued Nov. 13, 2026. 19 firms are named on the job; the list below has all 19.

$10BQTS investment over the project (QTS)
$168MMMR electrical permit, Nov. 13, 2026
7Data center buildings on 612 acres
19Firms named on the job

Get all 19 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 19 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 19 firms on QTS's Cedar Rapids campus?

We list the 19 firms named on QTS's Cedar Rapids campus, one row each, with where each name comes from.

1Permit on the recordNov 6, 2026

HITT Contracting Inc.

Tenant fit-out general contractor (data halls in DC1, DC2, DC5 on QTS's Cedar Rapids campus

QTS Data Centers' Cedar Rapids campus, Big Cedar Industrial Center, 4300 and 6200 76th Ave SW, Cedar Rapids (Linn County)

7 Cedar Rapids permits, 2026-09-24 to 2026-11-06; the biggest states $52 million

Work: Tenant fit-out general contractor (data halls in DC1, DC2, DC5

Who to call: HITT Contracting Inc.
HITT Contracting Inc. office line
(Falls Church, VA)
(703) 846-9000

The opportunity: Permit: Fit out data halls 1250, 1450, & 1650. Fit out includes installation of feeder & power branch cables, light fixtures & associated cabling, manual transfer switches & rack busway w/associated feeder cables. DC-6 Interior CONSTRUCTION OF A ~844,850 SF TENANT UPFIT WITHIN A SINGLE-STORY DATA CENTER. UP

2Permit on the recordAug 19, 2026

Suffolk Construction Company, Inc.

Contractor for the east-campus guard house (300 SF) on QTS's Cedar Rapids campus

QTS Data Centers' Cedar Rapids campus, Big Cedar Industrial Center, 4300 and 6200 76th Ave SW, Cedar Rapids (Linn County)

1 Cedar Rapids permit, issued 2026-08-19; the biggest states $83,000

Work: Contractor for the east-campus guard house (300 SF)

Who to call: Suffolk Construction Company, Inc.
(Boston, MA)

The opportunity: Permit: INSTALLATION OF A 300 S.F. COMMERCIAL BUILDING "QTS" GUARD HOUSE TO INCLUDE GUARD BOOTH AREA-1 BATHROOM (EAST CAMPUS) PLEASE CALL 319-286-5831 FOR FOOTING-FRAMING-FINAL INSPECTIONS

3Named in the newsNov 2, 2026

Layton Construction

General contractor, joint venture with Weitz on QTS's Cedar Rapids campus

QTS Data Centers' Cedar Rapids campus, Big Cedar Industrial Center, 4300 and 6200 76th Ave SW, Cedar Rapids (Linn County)

Work: General contractor, joint venture with Weitz

Who to call: Layton Construction
Layton Construction office line
(Sandy, UT)
(801) 568-9090

The opportunity: The joint venture of Des Moines-based Weitz Company and Sandy, Utah-based Layton construction is building the project.

What is QTS building in Cedar Rapids?

QTS Data Centers, owned by Blackstone, is building seven data center buildings on 612 acres in the Big Cedar Industrial Center on Cedar Rapids' southwest side. QTS has said the campus will be a $10 billion investment over its development, among the largest economic development projects in Iowa history and the largest in Cedar Rapids history; its city development agreement anticipates $1.75 billion.

Phase one wraps up in late 2026 and phase two follows in 2027. The city is now issuing the data-hall fit-out permits: 23 since July 2026 state $756 million, including MMR's $168 million electrical permit for DC6's data halls, issued Nov. 13, 2026.

Who gets what?

No one has published the campus's trade split. By the math on Turner & Townsend's data center cost index, about $840 million of the $1.75 billion QTS anticipates in its city agreement is electrical work and about $578 million is pipes, heat and air. The fit-out permits alone state $756 million.

Which firms are on the job?

The Weitz Company and Layton Construction build the campus in a joint venture, HITT Contracting holds the data-hall fit-out permits, and Suffolk built the east-campus guard house. Helix Electric is the primary electrical contractor; MMR, Bemrich, Price Industrial and Enterprise Electrical hold electrical permits. The cooling pipe work runs through TP Mechanical, Performance Contractors, Loenbro and BMWC, with Modern Piping, API HVAC, Temp-Con and Bowker Pinnacle on HVAC and plumbing. Alliant Energy is the utility and 3E supplies electrical gear. 19 firms in all are on the list below.

How do the ways into QTS's Cedar Rapids campus compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on QTS's Cedar Rapids campusEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell

Who should go after QTS's Cedar Rapids campus?

Electrical distributors and gear repsMMR's $168 million DC6 data halls, Helix Electric and HITT's fit-outs.
Mechanical, chiller and pipe repsTP Mechanical, Performance Contractors and Loenbro on stainless technical cooling water piping.
HVAC and plumbing suppliersModern Piping, API HVAC, Temp-Con and Bowker Pinnacle on the support spaces.

What should you do next on QTS's Cedar Rapids campus?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on QTS's Cedar Rapids campus.

Questions people ask about QTS's Cedar Rapids campus

How much is the QTS Cedar Rapids data center?

QTS has said $10 billion over the project's development; its city development agreement anticipates $1.75 billion.

Who is building the QTS Cedar Rapids data center?

The Weitz Company and Layton Construction in a joint venture, with HITT on the fit-outs. 19 firms are named in all, listed above.

What is the biggest permit on the QTS campus?

MMR Constructors' $168 million electrical permit for DC6's data halls, issued Nov. 13, 2026.

How we built this list

We read all 23 City of Cedar Rapids permits for the QTS campus since July 2026 (each record lists every contractor on it), CNR Magazine and the Corridor Business Journal, and kept each firm a permit or page names on this campus (read Nov. 17, 2026). Some permits are filed and not yet issued, marked as such. The trade split is the math on Turner & Townsend's published data center shares. Phones are each firm's own office line. First published Nov. 17, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 19 firms, free

All 19 firms on QTS's Cedar Rapids campus

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.