Who's building QTS's data center expansion in Fort Worth

Fort Worth issued $404 million in permits in two days for a QTS data center expansion, after the same job was filed at $130 million last year.

By Porter Stanley. Updated .

QTS Data Centers, owned by Blackstone, is expanding the first building of its Fort Worth campus at 14100 Park Vista Blvd. Fort Worth issued two building permits for it in two days: $300 million on Nov. 18, 2026 and $104 million on Nov. 19, $404 million in all, the sum. Adolfson & Peterson is the builder on both. QTS first filed this expansion in 2025 at $130 million, and that permit expired. 10 firms are named on the campus; the list below has all 10.

$404MTwo city building permits, Nov. 18 and 19 (the sum)
$300MCore and shell permit to Adolfson & Peterson
147,946Sq ft in the two-story expansion
10Firms named on the campus

Get all 10 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 10 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 10 firms on the QTS Fort Worth data center?

We list the 10 firms named on QTS's Fort Worth data center campus, one row each, the 2026 expansion first, with what each one does and which permit names it.

1Permit on the recordNov 18, 2026

Adolfson & Peterson Construction (AP Gulf States, Inc.)

General contractor on both new permits: the $300 million core and shell expansion and the $104 million data hall and equipment yard fit-out; also the stormwater operator for the expansion's site work on QTS's FTW1 data center expansion at 14100 Park Vista Blvd, Fort Worth, TX

QTS FTW1 DC1 Expansion, 14100 Park Vista Blvd, Fort Worth (Tarrant County), TX

Building permits, $300,000,000, issued Nov. 18, 2026, and, $104,051,082, issued Nov. 19, 2026

Work: General contractor on both new permits: the $300 million core and shell expansion and the $104 million data hall and equipment yard fit-out; also the stormwater operator for the expansion's site work

Who to call: Adolfson & Peterson Construction (AP Gulf States, Inc.)
Adolfson & Peterson Construction office line
(Dallas, TX)
(972) 387-1700

The opportunity: Fort Worth names Adolfson & Peterson (contractor registration RB026248, Richardson, TX address) on; says it is the fit-out for. AP Gulf States, Inc., with the same registration and address, is the state stormwater operator for 'QTS FTW1 DC1 EXPANSION 18MW' (coverage from July 27, 2026). The same firm is the builder on the campus's second building, DC2: permit ($160,201,754, issued Feb. 11, 2025) and Phase 2 interior permit ($95 million, issued Aug. 31, 2026). It also holds the 2026 dumpster enclosure and security fence permits at the site.

2Latest recordJun 16, 2026

Corgan (Corgan Associates Inc.)

Architect and design firm of record for the $300 million expansion, and the applicant on both November building permits on QTS's FTW1 data center expansion at 14100 Park Vista Blvd, Fort Worth, TX

QTS FTW1 DC1 Expansion, 14100 Park Vista Blvd, Fort Worth (Tarrant County), TX

State building filing, estimated cost $300,000,000, registered June 16, 2026

Work: Architect and design firm of record for the $300 million expansion, and the applicant on both November building permits

Who to call: Corgan (Corgan Associates Inc.)
Corgan office line
(Dallas, TX)
(214) 748-2000

The opportunity: The state filing 'QTS FTW1 DC1 Expansion' names Corgan Associates Inc., 401 N Houston St, Dallas, as design firm. Corgan's Tyler Buser is the applicant on. Corgan is also on the state filings for earlier phases.

3Permit on the recordAug 7, 2026

Kimley-Horn and Associates

Civil engineer: applicant on the expansion's grading permit, building expansion with an electrical yard on QTS's FTW1 data center expansion at 14100 Park Vista Blvd, Fort Worth, TX

QTS FTW1 DC1 Expansion, 14100 Park Vista Blvd, Fort Worth (Tarrant County), TX

Grading permit, issued Aug. 7, 2026; no value stated

Work: Civil engineer: applicant on the expansion's grading permit, building expansion with an electrical yard

Who to call: Kimley-Horn and Associates
Kimley-Horn office line
(Fort Worth, TX)
(817) 335-6511

The opportunity: : 'FTW1 DC1 Expansion Building expansion on Alliance Gateway North site with associated electrical yard,' applicant Eric Jeske, Kimley-Horn & Associates. The applicant works from Kimley-Horn's McKinney office, (469) 301-2580. Kimley-Horn also filed the 2025 grading permit for the earlier version of the expansion and the grading for Oncor's switch station at this address.

What is QTS building in Fort Worth?

QTS Data Centers is adding on to DC1, the first building of its Fort Worth 1 campus at 14100 Park Vista Blvd, near AllianceTexas in Tarrant County. Blackstone owns QTS; it bought the company for about $10 billion in 2021.

The state filing calls the job a two-story, 147,946 sq ft expansion of the data center with an equipment yard. The city's shell permit lists 215,770 sq ft. The state's stormwater notice names the site "QTS FTW1 DC1 EXPANSION 18MW".

QTS bought the original 8 megawatt building here in 2017 for about $50 million. It says the 52-acre campus has room for 200 megawatts. A second building, DC2, stands next door. The state lists its accessibility inspection as complete, and its $95 million interior build-out permit was issued Aug. 31, 2026.

How much is the QTS Fort Worth data center expansion?

QTS has given no cost. Fort Worth issued a $300,000,000 permit for the core and shell on Nov. 18, 2026, and a $104,051,082 permit for the data hall and equipment yard fit-out on Nov. 19. Together that is $404 million, the sum.

The state filing, from June 16, 2026, estimates $300 million for the expansion. Each permit value is what was declared to the city for that work, not QTS's total spend.

Why was the QTS Fort Worth expansion filed twice?

QTS first filed this expansion in April 2025 at $130 million. That permit expired in June 2026 with no builder named; its contractor line reads "out to bid". A $42 million data hall permit filed in July 2025 expired too.

QTS filed again on June 18, 2026, now at $300 million for the shell and $104 million for the fit-out. Both permits were issued five months later, a day apart.

How far along is the QTS Fort Worth expansion?

Site work has started. The grading permit was issued Aug. 7, 2026, and state stormwater coverage for the site began July 27. A plumbing permit was issued at the address on Oct. 27.

The building permits came on Nov. 18 and 19, 2026. The state filing plans the work from July 1, 2026 to Oct. 1, 2027. No electrical or mechanical permit for the new work has been filed yet.

Who is building the QTS Fort Worth data center expansion?

Adolfson & Peterson Construction is the general contractor on both new building permits. Its Gulf States arm is also the operator on the state stormwater notice for the expansion.

Adolfson & Peterson is the builder on DC2 next door too, on a $160.2 million city permit issued Feb. 11, 2025 and a $95 million interior permit issued Aug. 31, 2026. The state filing for DC2 describes a 42 megawatt building at $220 million, and the state lists its accessibility inspection as complete.

Corgan of Dallas is the design firm and applied for both new permits. Kimley-Horn filed the grading permit for the expansion.

Which trade firms have worked on the QTS Fort Worth campus?

Maverick Utility Construction is the plumber on a site utility permit for the expansion, issued Oct. 27, 2026 and tied to its grading permit. Oncor is building an electric switch station at the campus address, on a grading permit from May 2025.

Earlier phases name more firms. Rogers-O'Brien Construction built data hall fit-outs in DC1, including a $16.3 million job finished in 2025. Walker Engineering did electrical work and TDIndustries did mechanical and plumbing work. Overland Contracting built QTS's on-site substation, including a $5 million equipment enclosure and transformer pad, with Black & Veatch as the engineer. All 10 firms are on the list below.

What other data centers did Fort Worth permit this month?

Fort Worth issued about $679 million of data center building permits from Nov. 16 to Nov. 19, 2026, the sum. Besides QTS's two, a $275,000,000 permit for a new data center shell at 9501 Asphalt Dr, CyrusOne's DFW8 Building 2, was issued Nov. 16. No other data center building permit was issued in the city those four days.

A $327,000,000 permit for a new two-story data center at 10200 Hicks Field Rd, called DFW14 for ACS Digital, was filed Nov. 12 and is still in plan review. Counting it, data center permits filed and issued in Fort Worth over two weeks pass $1 billion.

How do the ways into the QTS Fort Worth data center compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on QTS's FTW1 expansion on Park Vista BlvdEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell
The trade work still to be filedThe electrical, mechanical and plumbing work inside the $104 million fit-outElectrical, mechanical and plumbing contractors and their suppliersA part of the fit-out workNo subcontractor is on the record yet, so the builder is the way in

Who should go after the QTS Fort Worth data center?

Electrical distributors and gear repsA $104 million data hall and equipment yard fit-out with no electrical subcontractor on the record yet; Walker Engineering did the campus's earlier electrical work, and Oncor and Overland Contracting are on its power.
Mechanical, HVAC and plumbing repsTDIndustries on earlier mechanical and plumbing work, and Maverick Utility Construction on the expansion's site utility permit.
Concrete, steel and site suppliersAdolfson & Peterson holds the $300 million core and shell permit, with Kimley-Horn as civil engineer on the grading.

What should you do next on the QTS Fort Worth data center?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask Adolfson & Peterson's Dallas office for the team on QTS's FTW1 DC1 expansion at 14100 Park Vista Blvd.
  3. Watch for the electrical and mechanical permits on the new work.

Questions people ask about the QTS Fort Worth data center

How much is the QTS Fort Worth data center expansion?

QTS has given no cost. Fort Worth's two building permits add up to $404 million, the sum: $300 million for the core and shell and $104 million for the data hall fit-out. The state filing estimates $300 million.

Who is building the QTS data center in Fort Worth?

Adolfson & Peterson Construction is the general contractor on both building permits issued Nov. 18 and 19, 2026. Corgan is the design firm and Kimley-Horn filed the grading permit.

Where is the QTS Fort Worth data center?

It is at 14100 Park Vista Blvd, Fort Worth, TX 76177, in Tarrant County near AllianceTexas.

Who owns QTS?

Blackstone. It bought QTS for about $10 billion in 2021. The permit owner is a QTS Fort Worth property company.

How big is the QTS Fort Worth expansion?

The state filing calls it a two-story, 147,946 sq ft expansion with an equipment yard. The city's shell permit lists 215,770 sq ft. The state stormwater notice names it an 18 MW expansion.

When will the QTS Fort Worth expansion be done?

The state filing plans the work from July 1, 2026 to Oct. 1, 2027.

Why did the first QTS Fort Worth expansion permit expire?

QTS filed the expansion at $130 million in April 2025. The permit expired in June 2026 with no builder named; its contractor line reads "out to bid". QTS filed again in June 2026 at $300 million.

Has QTS hired electrical and mechanical subcontractors for the expansion?

None is on the record yet. No electrical or mechanical permit for the new work had been filed as of Nov. 20, 2026. Walker Engineering and TDIndustries did that work on earlier phases.

What other data centers is Fort Worth permitting?

Fort Worth issued a $275 million data center shell permit at 9501 Asphalt Dr on Nov. 16, 2026. A $327 million data center called DFW14 at 10200 Hicks Field Rd was filed Nov. 12 and is in plan review.

What happens next on the QTS Fort Worth data center?

Expect electrical, mechanical and plumbing permits for the new work. We'll update this page when a new permit or firm appears.

How we built this list

We read Fort Worth's public Accela permit records for 14100 Park Vista Blvd on Nov. 20, 2026, opening each key permit by number, plus the city's permit map back to 2016. We also read the state's building filings for the expansion and for DC2, the state's stormwater notice, QTS's Fort Worth page and QTS's 2017 news release. We kept each firm a city or state record names at this address. Five are on the 2026 expansion or the site's power; five are on earlier phases, and each row says which permit and date. Record dates are the issue date, or the filing date where no issue date is published. The $404 million and $679 million figures are our sums of city permit values, not QTS's spend. Left out: the owner, a city plan review firm, accessibility inspectors, a plumber at the DC2 address, and two small service jobs (a 2023 electrical job and a 2025 backflow test). Phones are each firm's own main or office line from its own site, except Maverick Utility Construction and Overland Contracting, whose numbers come from the permits. First published Nov. 20, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 10 firms, free

All 10 firms on the QTS Fort Worth data center

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.