What is QTS building in Fort Worth?
QTS Data Centers is adding on to DC1, the first building of its Fort Worth 1 campus at 14100 Park Vista Blvd, near AllianceTexas in Tarrant County. Blackstone owns QTS; it bought the company for about $10 billion in 2021.
The state filing calls the job a two-story, 147,946 sq ft expansion of the data center with an equipment yard. The city's shell permit lists 215,770 sq ft. The state's stormwater notice names the site "QTS FTW1 DC1 EXPANSION 18MW".
QTS bought the original 8 megawatt building here in 2017 for about $50 million. It says the 52-acre campus has room for 200 megawatts. A second building, DC2, stands next door. The state lists its accessibility inspection as complete, and its $95 million interior build-out permit was issued Aug. 31, 2026.
How much is the QTS Fort Worth data center expansion?
QTS has given no cost. Fort Worth issued a $300,000,000 permit for the core and shell on Nov. 18, 2026, and a $104,051,082 permit for the data hall and equipment yard fit-out on Nov. 19. Together that is $404 million, the sum.
The state filing, from June 16, 2026, estimates $300 million for the expansion. Each permit value is what was declared to the city for that work, not QTS's total spend.
Why was the QTS Fort Worth expansion filed twice?
QTS first filed this expansion in April 2025 at $130 million. That permit expired in June 2026 with no builder named; its contractor line reads "out to bid". A $42 million data hall permit filed in July 2025 expired too.
QTS filed again on June 18, 2026, now at $300 million for the shell and $104 million for the fit-out. Both permits were issued five months later, a day apart.
How far along is the QTS Fort Worth expansion?
Site work has started. The grading permit was issued Aug. 7, 2026, and state stormwater coverage for the site began July 27. A plumbing permit was issued at the address on Oct. 27.
The building permits came on Nov. 18 and 19, 2026. The state filing plans the work from July 1, 2026 to Oct. 1, 2027. No electrical or mechanical permit for the new work has been filed yet.
Who is building the QTS Fort Worth data center expansion?
Adolfson & Peterson Construction is the general contractor on both new building permits. Its Gulf States arm is also the operator on the state stormwater notice for the expansion.
Adolfson & Peterson is the builder on DC2 next door too, on a $160.2 million city permit issued Feb. 11, 2025 and a $95 million interior permit issued Aug. 31, 2026. The state filing for DC2 describes a 42 megawatt building at $220 million, and the state lists its accessibility inspection as complete.
Corgan of Dallas is the design firm and applied for both new permits. Kimley-Horn filed the grading permit for the expansion.
Which trade firms have worked on the QTS Fort Worth campus?
Maverick Utility Construction is the plumber on a site utility permit for the expansion, issued Oct. 27, 2026 and tied to its grading permit. Oncor is building an electric switch station at the campus address, on a grading permit from May 2025.
Earlier phases name more firms. Rogers-O'Brien Construction built data hall fit-outs in DC1, including a $16.3 million job finished in 2025. Walker Engineering did electrical work and TDIndustries did mechanical and plumbing work. Overland Contracting built QTS's on-site substation, including a $5 million equipment enclosure and transformer pad, with Black & Veatch as the engineer. All 10 firms are on the list below.
What other data centers did Fort Worth permit this month?
Fort Worth issued about $679 million of data center building permits from Nov. 16 to Nov. 19, 2026, the sum. Besides QTS's two, a $275,000,000 permit for a new data center shell at 9501 Asphalt Dr, CyrusOne's DFW8 Building 2, was issued Nov. 16. No other data center building permit was issued in the city those four days.
A $327,000,000 permit for a new two-story data center at 10200 Hicks Field Rd, called DFW14 for ACS Digital, was filed Nov. 12 and is still in plan review. Counting it, data center permits filed and issued in Fort Worth over two weeks pass $1 billion.
How do the ways into the QTS Fort Worth data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on QTS's FTW1 expansion on Park Vista Blvd | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The trade work still to be filed | The electrical, mechanical and plumbing work inside the $104 million fit-out | Electrical, mechanical and plumbing contractors and their suppliers | A part of the fit-out work | No subcontractor is on the record yet, so the builder is the way in |
Who should go after the QTS Fort Worth data center?
| Electrical distributors and gear reps | A $104 million data hall and equipment yard fit-out with no electrical subcontractor on the record yet; Walker Engineering did the campus's earlier electrical work, and Oncor and Overland Contracting are on its power. |
|---|
| Mechanical, HVAC and plumbing reps | TDIndustries on earlier mechanical and plumbing work, and Maverick Utility Construction on the expansion's site utility permit. |
|---|
| Concrete, steel and site suppliers | Adolfson & Peterson holds the $300 million core and shell permit, with Kimley-Horn as civil engineer on the grading. |
|---|
What should you do next on the QTS Fort Worth data center?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask Adolfson & Peterson's Dallas office for the team on QTS's FTW1 DC1 expansion at 14100 Park Vista Blvd.
- Watch for the electrical and mechanical permits on the new work.
Questions people ask about the QTS Fort Worth data center
How much is the QTS Fort Worth data center expansion?
QTS has given no cost. Fort Worth's two building permits add up to $404 million, the sum: $300 million for the core and shell and $104 million for the data hall fit-out. The state filing estimates $300 million.
Who is building the QTS data center in Fort Worth?
Adolfson & Peterson Construction is the general contractor on both building permits issued Nov. 18 and 19, 2026. Corgan is the design firm and Kimley-Horn filed the grading permit.
Where is the QTS Fort Worth data center?
It is at 14100 Park Vista Blvd, Fort Worth, TX 76177, in Tarrant County near AllianceTexas.
Who owns QTS?
Blackstone. It bought QTS for about $10 billion in 2021. The permit owner is a QTS Fort Worth property company.
How big is the QTS Fort Worth expansion?
The state filing calls it a two-story, 147,946 sq ft expansion with an equipment yard. The city's shell permit lists 215,770 sq ft. The state stormwater notice names it an 18 MW expansion.
When will the QTS Fort Worth expansion be done?
The state filing plans the work from July 1, 2026 to Oct. 1, 2027.
Why did the first QTS Fort Worth expansion permit expire?
QTS filed the expansion at $130 million in April 2025. The permit expired in June 2026 with no builder named; its contractor line reads "out to bid". QTS filed again in June 2026 at $300 million.
Has QTS hired electrical and mechanical subcontractors for the expansion?
None is on the record yet. No electrical or mechanical permit for the new work had been filed as of Nov. 20, 2026. Walker Engineering and TDIndustries did that work on earlier phases.
What other data centers is Fort Worth permitting?
Fort Worth issued a $275 million data center shell permit at 9501 Asphalt Dr on Nov. 16, 2026. A $327 million data center called DFW14 at 10200 Hicks Field Rd was filed Nov. 12 and is in plan review.
What happens next on the QTS Fort Worth data center?
Expect electrical, mechanical and plumbing permits for the new work. We'll update this page when a new permit or firm appears.
How we built this list
We read Fort Worth's public Accela permit records for 14100 Park Vista Blvd on Nov. 20, 2026, opening each key permit by number, plus the city's permit map back to 2016. We also read the state's building filings for the expansion and for DC2, the state's stormwater notice, QTS's Fort Worth page and QTS's 2017 news release. We kept each firm a city or state record names at this address. Five are on the 2026 expansion or the site's power; five are on earlier phases, and each row says which permit and date. Record dates are the issue date, or the filing date where no issue date is published. The $404 million and $679 million figures are our sums of city permit values, not QTS's spend. Left out: the owner, a city plan review firm, accessibility inspectors, a plumber at the DC2 address, and two small service jobs (a 2023 electrical job and a 2025 backflow test). Phones are each firm's own main or office line from its own site, except Maverick Utility Construction and Overland Contracting, whose numbers come from the permits. First published Nov. 20, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 20, 2026- Fort Worth Accela permit PB26-08758, read Nov. 20, 2026
- Fort Worth Accela permit PB26-08779, read Nov. 20, 2026
- Fort Worth Accela permit PB25-04588 (expired), read Nov. 20, 2026
- Fort Worth Accela grading permit CG26-00111
- Texas Department of Licensing and Regulation, TABS2026022992
- Texas Department of Licensing and Regulation, TABS2024010121 (DC2)
- EPA ECHO, stormwater permit TXR1571YY
- QTS Fort Worth campus page (read Nov. 20, 2026)
- QTS news release, Jan. 30, 2017
- Wikipedia: Quality Technology Services