What is QTS building in York County, South Carolina?
QTS Data Centers is building a data center campus off Hands Mill Highway in unincorporated York County, near Clover and south of Lake Wylie. QTS is owned by Blackstone and has more than 90 properties in 15 states, per Commercial Search. County permits call the job Project McFly and the campus CLT1.
QTS plans to invest about $8 billion in nine buildings, built in three phases. QTS says that money is spent over time as the buildings are built and opened, so it is not one contract. The project started at $1 billion in 2023, per the Rock Hill Herald, and in December 2025 QTS paid $26.1 million for more than 400 more acres.
How far along is the QTS York County data center?
The first phase, four buildings on about 109 acres, is under way. Gilbane announced on June 30, 2026 that the steel frame of the first building had topped out; QTS says no building is finished or operating yet. QTS plans to start phase 2 in early 2027 and says the schedule for phases 2 and 3 is still being determined.
York County issued the DC3 permit on May 4, 2026, the DC4 permit on June 9, and permits for the inside build-outs of DC1 and DC2 on Aug. 31. The newest record is a Nov. 12, 2026 permit for power to Evans General Contractors' trailer city, three eight-unit trailers and three double-wides, with Miller Electric as the electrical contractor.
What is being bought on the QTS York County campus?
York County's permits for the four phase-one buildings add up to about $2.28 billion, the sum of six permits: $850 million for DC3, $830 million for DC4, $276.9 million for a DC2 change, $162 million and $157.7 million for the inside build-outs of DC1 and DC2, and $400,000 for the DC1 shell. Each value is for a whole building, not one firm's share.
QTS has a power agreement with York Electric Cooperative for all nine buildings. Overland Contracting built the campus's Palmetto Substation on an $18.9 million permit, which passed its final inspection in October 2026. QTS estimates about 1,000 construction jobs on the campus.
Who is building the QTS York County data center?
Gilbane Building Company is the contractor on DC1 and DC3, and Evans General Contractors on DC4 and the DC2 permit change. Both names are on the campus gate signs. Hourigan Construction holds the permit for the DC2 inside build-out, and Century Contractors is on DC3 and the DC2 build-out.
Brasfield & Gorrie did early site work, including power for construction trailers, and is the contractor on the Phase 2 land disturbance permit, issued Feb. 24, 2026.
Which trade firms are on the QTS York County data center?
York County's building permits name the trade firms on each building. For electrical, they name M.C. Dean, Miller Electric, Adams Electric and Amteck. For pipes, heat and air, they name McKenney's, Shambaugh & Son, SPC Mechanical, Environmental Air Systems, BMWC Constructors and Precision Plumbing, which is on all four buildings. CHA Fire Protection Services and Johnson Controls Fire Protection handle fire protection.
Martin Concrete Construction is on DC4, and Hoopaugh Grading and Draw Enterprises built retaining walls. Black & Veatch, Sheehan Nagle Hartray Architects (now Woolpert) and Highland Associates are the design firms listed on the permits. 25 firms in all are on the list below.
How do the ways into the QTS York County data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the QTS York County data center | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the QTS York County data center?
| Electrical distributors and gear reps | M.C. Dean, Miller Electric, Adams Electric and Amteck, on building permits worth up to $850 million each. |
|---|
| Mechanical, HVAC and plumbing reps | McKenney's, Shambaugh & Son, SPC Mechanical, Environmental Air Systems, BMWC Constructors and Precision Plumbing on the four buildings. |
|---|
| Fire protection, concrete and site suppliers | CHA and Johnson Controls on fire protection; Martin Concrete, Hoopaugh Grading and Draw Enterprises on concrete and walls. |
|---|
What should you do next on the QTS York County data center?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the QTS data center campus off Hands Mill Highway in York County.
Questions people ask about the QTS York County data center
How much is the QTS York County data center?
QTS plans to invest about $8 billion to build its nine-building campus, spent over time as each building is built and opens. It is a planned total, not one contract. York County's building permits for the four phase-one buildings add up to about $2.28 billion, the sum, led by $850 million for DC3 and $830 million for DC4.
Who is building the QTS data center in York County?
Gilbane Building Company is the contractor on DC1 and DC3, and Evans General Contractors on DC4 and the DC2 permit change. Hourigan Construction holds the DC2 inside build-out permit. 25 firms are named on the campus, listed above.
Where is the QTS York County data center?
It is off Hands Mill Highway in unincorporated York County, South Carolina, near Clover and south of Lake Wylie. QTS lists the address as 2286 Guardian Road, with a Rock Hill mailing address. The campus entrance is 2143 Hands Mill Highway.
How many buildings will the QTS York County campus have?
Nine buildings in three phases. The first phase is four buildings, DC1 to DC4, on about 109 acres, per QTS.
When will the QTS York County data center open?
QTS has not given an opening date, and it says no building is finished or operating yet. Gilbane announced on June 30, 2026 that the steel frame of the first building had topped out. QTS plans to start phase 2 in early 2027 and says the schedule for phases 2 and 3 is still being determined.
Who supplies power to the QTS York County data center?
QTS has a power agreement with York Electric Cooperative for all nine buildings. Overland Contracting built the campus's Palmetto Substation on an $18.9 million permit, which passed its final inspection in October 2026.
How many jobs will the QTS York County data center create?
QTS estimates about 1,000 construction jobs and about 100 permanent jobs. QTS's own page and some news reports also give 200 permanent jobs.
Who is the tenant of the QTS York County data center?
QTS has not said. The owner of record on the county's map is QTS York 1 LLC, and QTS is owned by Blackstone.
What is the newest permit on the QTS York County campus?
On Nov. 12, 2026, York County issued a $150,000 permit for power to Evans General Contractors' trailer city, three eight-unit trailers and three double-wides, with Miller Electric as the electrical contractor.
How did the QTS York County project grow to $8 billion?
The project started at $1 billion in 2023, per the Rock Hill Herald. In December 2025 QTS paid $26.1 million for more than 400 more acres, and Commercial Search reported in July 2026 that the total had grown to $8 billion.
What happens next on the QTS York County data center?
Phase 1's four buildings are under construction, with the inside build-outs of DC1 and DC2 permitted in August 2026. QTS plans to start phase 2 in early 2027; the schedule for phases 2 and 3 is still being determined. We'll update this page when a new permit or firm appears.
How we built this list
We read every QTS permit on York County's public Evolve permit portal by number on Nov. 18, 2026, and searched Guardian Rd, Hands Mill Hwy and Campbell Rd for newer ones; none was newer than Nov. 12, 2026. We also read QTS's York County page, Gilbane's June 30, 2026 release, the Post and Courier, Commercial Search and the Rock Hill Herald, and kept each firm a permit or QTS names on this campus. York County's building permits list the firms on each building but not each firm's trade, so trades come from each firm's own description. A permit's value is for the whole building, not one firm's share, and the $2.28 billion is the sum of six permits. Left out: individuals on the permits (South Carolina law), the owner, one firm listed on DC4 with no role stated (MSS Solutions), one firm on the build-out permits with no office line we could find, a substation contractor and a cooperative whose records never name QTS, and the cooperative's wholesale power suppliers. Phones are each firm's own line; M.C. Dean, Johnson Controls, Black & Veatch (also used for Overland Contracting) and Woolpert are national main lines, and Adams Electric's site names no office. First published Nov. 19, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.