What's due Dec. 3 on Renton High School?
Skanska posted its MACC-04 main construction notice on the bid board of Washington's Office of Minority and Women's Business Enterprises on Oct. 15, 2026. Sealed bids go to Renton School District and Skanska U.S.A. Building for subcontracts under Skanska's GC/CM contract.
Bid Group 2 is due no later than 10 a.m. on Dec. 3, 2026, and it holds masonry (04A) and CMU (04B), the concrete block package. Bid Group 1 is due at 10 a.m. the day before. Bids are opened and read aloud after the due time, package by package.
The notice states no estimate for any package. It marks three packages with a star because Skanska intends to bid them itself: structural concrete, interior openings and miscellaneous specialties. Masonry and CMU are not among them.
What are the 19 packages in the MACC-04 round?
The notice's own package names, grouped by due date.
- Dec. 2, 10 a.m.: Final clean, roofing, tile, resilient and carpet, acoustic ceilings and panels, painting and wall coverings, wood athletic flooring, food service equipment, theater and stage equipment.
- Dec. 3, 10 a.m.: Structural concrete (Skanska may bid), masonry, CMU, casework and millwork, precast panel siding, metal panel siding, interior openings (Skanska may bid), aluminum, glass and curtain wall, framing and drywall, miscellaneous specialties (Skanska may bid).
Electrical and mechanical are not in this round: Veca Electric & Tech and Auburn Mechanical are already on the state record, hired by Skanska. Auburn Mechanical takes its own six sub-tier bids until 8 a.m. Nov. 19, 2026.
Why does masonry matter on this school?
At the schematic design approval in January 2025, the Renton Reporter reported that the material palette would try to match the older buildings by using brick and terra cotta on the facades. The 1930s part of the old school stays, alongside the IKEA Performing Arts Center.
The district's April 2026 renderings show brick on the three-story classroom wing, the main entry and the gym. The notice gives no quantity, so read the drawings before you price.
How big is the new Renton High School, and who is on it?
The district says the new school is three stories and 350,000 square feet, with classroom capacity for 1,600 students, on an expanded 33.3-acre site. Work runs in phases while the current school stays open, and it is projected to open in fall 2029.
Skanska puts its contract at $110 million. The Renton Reporter quoted a total project budget of $334,736,000 from the district's August 2025 design presentation, funded by the 2023 bond.
The district's page lists the design team: BRIC Architects, PCS Structural Solutions, AHBL Civil/Landscape, Metrix Engineers (mechanical) and GFT Electrical. It does not name the builder. The state's public works record shows 53 contractors on the project, including Veca Electric & Tech and Auburn Mechanical.
How do the ways into Renton High School compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| A MACC-04 package | A sealed bid on one of 19 packages, masonry and CMU among them | Trade subcontractors | A subcontract under Skanska's GC/CM contract | Bids close 10 a.m. Dec. 2 or Dec. 3, 2026, and no estimate is posted |
| Selling to the masonry bidders | Brick, block, mortar and accessories priced into a mason's bid | Suppliers and manufacturers' reps | Your product in the winning masonry number | No bidder list is public, so you work your own mason customers |
| The mechanical sub-tier | One of Auburn Mechanical's six packages | Controls, insulation, firestop, TAB and water treatment firms | A sub-tier contract under the mechanical contractor | Due 8 a.m. Nov. 19, 2026 |
| The specification | Your product written into the drawings or approved as an equal | Manufacturers and their reps | Your product named across the school | The bid documents are already out, so this is mainly for substitutions and later rounds |
Who should go after Renton High School, and who shouldn't?
| Masonry contractors | Masonry (04A) and CMU (04B) are open packages in Bid Group 2, due 10 a.m. Dec. 3, 2026, and Skanska does not mark either as one it will bid. |
|---|
| Brick, block and masonry supply reps | The design team planned brick and terra cotta to match the older buildings; the masons pricing 04A and 04B are your buyers before Dec. 3. |
|---|
| Envelope and interior subs | Roofing, metal and precast panels, glazing, framing and drywall, ceilings, flooring and paint each have their own package. |
|---|
| HVAC and electrical suppliers | Auburn Mechanical and Veca Electric & Tech are already on the state record, hired by Skanska; sell through them. |
|---|
What should you do next on Renton High School?
- Read Skanska's MACC-04 notice on Washington's OMWBE bid board and pick your package.
- Pull the drawings from BuildingConnected or the Builders Exchange of Washington, under Skanska's projects bidding.
- Deliver a sealed bid to Renton School District and Skanska by 10 a.m. Dec. 3, 2026 for masonry or CMU (Dec. 2 for Group 1 packages).
- If you supply brick or block, call the masonry subs you sell to before they price it.
- Open the full list of 39 for the firms already on the state record.
Questions people ask about the new Renton High School
Who is building the new Renton High School?
Skanska USA Building, as general contractor/construction manager (GC/CM) for the Renton School District. Skanska announced the contract on Oct. 5, 2026 at USD 110 million and says work has begun.
When are masonry bids due on Renton High School?
Skanska's MACC-04 notice puts masonry (package 04A) and CMU (package 04B) in Bid Group 2, due no later than 10:00 a.m. on Dec. 3, 2026. Bids are sealed and are opened and read aloud after the due time.
What other packages are in the MACC-04 round?
19 in all. Group 1, due 10:00 a.m. Dec. 2, 2026: final clean, roofing, tile, resilient and carpet, acoustic ceilings and panels, painting and wall coverings, wood athletic flooring, food service equipment, and theater and stage equipment. Group 2, due 10:00 a.m. Dec. 3: structural concrete, masonry, CMU, casework and millwork, precast and metal panel siding, interior openings, aluminum, glass and curtain wall, framing and drywall, and miscellaneous specialties.
Does Skanska bid any packages itself?
The notice marks three packages with a star, meaning Skanska intends to submit a bid on them: structural concrete (03A), interior openings (08A) and miscellaneous specialties (10Z). Masonry and CMU carry no star.
Where do I get the drawings?
The notice says the contract documents are on BuildingConnected and the Builders Exchange of Washington (bxwa.com), under Posted Projects, General Contractor Project areas, Washington, Skanska, Projects Bidding.
How much does the new Renton High School cost?
Skanska's contract is USD 110 million, per its Oct. 5, 2026 release. In August 2025 the Renton Reporter quoted the district's design presentation as giving a total project budget of $334,736,000, funded by the 2023 bond.
How big is the new Renton High School, and when does it open?
Three stories and 350,000 square feet, with classroom capacity for 1,600 students, on an expanded 33.3-acre site, per the district. It is projected to open in fall 2029, and the current school stays open during construction.
What about HVAC and plumbing work?
Auburn Mechanical is the mechanical contractor (MC/CM). Its own notice asks for sub-tier bids on six packages, from building controls to testing, adjusting and balancing, due 8:00 a.m. Nov. 19, 2026.
How we built this list
We read Skanska's MACC-04 notice and Auburn Mechanical's sub-tier notice on the bid board of Washington's Office of Minority and Women's Business Enterprises, Skanska's Oct. 5, 2026 release, the Renton School District's project page and renderings, two Renton Reporter articles on the design and budget, and Construction Dive's coverage. The firms already on the job come from the Washington State Department of Labor & Industries public works intents for project 1191969, held in American Trades Index. A row is on the list only if a record ties it to the new Renton High School. We left every person's name, phone and email off the list. The intents state no trade, so we name a trade only where the firm's name or its own notice says it. First published Nov. 2026. We'll update this page when Skanska posts the next round or the state record shows who won masonry.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 10, 2026- Skanska, Renton High School Replacement Project MACC-04 bid notice (OMWBE bid board), Oct. 15, 2026
- Auburn Mechanical, Renton High School Replacement mechanical sub-tier notice (OMWBE bid board), Oct. 26, 2026
- Skanska, "Skanska to construct new high school in Renton, Washington, USA for USD 110M", Oct. 5, 2026 (via Inderes)
- Renton School District, Rebuilding Renton High School
- Renton Reporter, schematic design of the new Renton High School, Jan. 31, 2025
- Renton Reporter, "District approves design development of Renton HS expansion", Aug. 7, 2025
- Construction Dive, "Skanska goes back to school with $418M in education builds", Oct. 7, 2026
- Washington State Department of Labor & Industries, public works intents, project 1191969 (data.wa.gov)