What is Samsung building in Taylor, Texas?
Samsung is building a chip fab campus at 1530 FM 973 in Taylor, in Williamson County, northeast of Austin. The owner is Samsung Austin Semiconductor, part of Samsung Electronics.
The first plant, Fab 1, has a three-story fab building of 1,202,040 sq ft, a 442,935 sq ft gas and chemical supply building, a central utility building, an office, a garage and warehouses. A 138-kV substation powers the site. A second fab is planned next door.
How much is the Samsung Taylor fab?
Samsung says it expects to invest more than $37 billion in the region. Samsung's plans include two Taylor fabs, research and an Austin expansion. Of the fab's first $17 billion, Samsung says $6 billion is buildings and $11 billion is equipment.
The construction part is easier to see in Samsung's own numbers: it says it spent $1.72 billion on construction at Taylor in 2025 alone, with 6,674 construction workers on site and $627.7 million in construction pay.
Six state filings from Nov. 5, 2022 put $2.07 billion on the first buildings, the sum: $950 million for the manufacturing building, $350 million for the gas and chemical building, $300 million for the fab, $300 million for the central utility building, $150 million for the office and $15 million for the garage. A filing's cost is what was declared for that work, not Samsung's total spend.
How far along is the Samsung Taylor fab?
News reports on Nov. 8, 2026 said its trial runs could begin around mid-to-late December, and that construction of the second Taylor fab is expected to start this month. Samsung has not confirmed a date, and we found no state filing for Fab 2 yet.
Taylor's mayor said in August 2026 that much of the groundwork for Fab 2 was already done while Fab 1 was built. The newest state filing on the site is a $6.5 million fab cleanroom observation deck, registered March 31, 2026.
Who is building the Samsung Taylor fab?
Samsung C&T, Samsung's own construction arm, holds the state's construction stormwater coverage for the site named TAYLOR FAB1 through its US company, Samsung E&C America, active since September 2022. Yates Construction was named general contractor for the first plant in 2023.
Samsung E&A America and Clayco hold their own active coverages on the site, and Clayco also built the warehouses. Jordan Foster Construction has been the site work operator since April 2022.
Which trade and design firms are on the Samsung Taylor fab?
Primoris led construction of the 138-kV substation, with DIS-TRAN Steel listed as structural engineer and Samoo listed as general contractor. Garney holds a coverage tied to the end of the raw water line, Nomura Micro Science, an ultrapure water firm, holds one on the fab, and IE2 Construction holds one on a yard at the site.
Jacobs, Page, CDM Smith, Gensler, Stantec and Abel Design Group are the design firms on the state filings for the buildings. 18 firms in all are on the list below.
How do the ways into the Samsung Taylor fab compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Samsung's Taylor fab | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Samsung Taylor fab?
| Electrical distributors and gear reps | Primoris on the 138-kV substation that powers the fab, with DIS-TRAN Steel as its structural engineer, on a site where Samsung spent $1.72 billion on construction in 2025. |
|---|
| Pipe, water and mechanical reps | Garney on the raw water line's end point and Nomura Micro Science, an ultrapure water firm, on the fab. |
|---|
| Concrete, site and building suppliers | Samsung C&T, Yates, Clayco, Samsung E&A and Jordan Foster, the builders and site firms, as Fab 2 is reported to start. |
|---|
What should you do next on the Samsung Taylor fab?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Samsung's Taylor fab at 1530 FM 973, and ask about Fab 2.
Questions people ask about the Samsung Taylor fab
How much is the Samsung Taylor fab?
Samsung says it expects to invest more than $37 billion in the region; its plans include two Taylor fabs, research and an Austin expansion. Samsung says it spent $1.72 billion on construction at Taylor in 2025.
Who is building the Samsung Taylor fab?
Samsung C&T, Samsung's construction arm, holds the fab's state stormwater coverage, and Yates Construction was named general contractor on the first plant. 18 firms are named on the job, listed above.
Where is the Samsung Taylor fab?
It is at 1530 FM 973 in Taylor, Williamson County, Texas, northeast of Austin.
How big is the Samsung Taylor fab?
The fab building alone is 1,202,040 sq ft, and the gas and chemical supply building is 442,935 sq ft, per state filings.
How many people work on the Samsung Taylor fab?
Samsung says there were 6,674 construction workers on site in 2025.
When will the Samsung Taylor fab open?
News reports on Nov. 8, 2026 said trial runs at the first fab could begin around mid-to-late December. Samsung has not confirmed a date.
Is Samsung building a second fab in Taylor?
News reports on Nov. 8, 2026 said construction of a second Taylor fab is expected to start this month. We found no state filing for it yet.
What is the newest filing on the Samsung Taylor fab?
A $6.5 million state filing for a fab cleanroom observation deck, registered March 31, 2026.
What happens next on the Samsung Taylor fab?
Fab 1 trial runs and the start of Fab 2. We'll update this page when a new filing or firm appears.
How we built this list
We read Samsung's Taylor page and its 2025 economic impact report, the state's architectural barrier filings (TDLR TABS) for Samsung in Taylor, the state's construction stormwater records (TCEQ) and EPA ECHO for the site, and the news, on Nov. 20, 2026. TABS lists design firms, not builders, so the builders come from the stormwater records and the news. The $2.07 billion is the sum of six TABS filings, not Samsung's spend. A stormwater record names a firm as an operator on the site, not its scope; where we give a trade it comes from the firm's line of work. Left out: the owner (Samsung Austin Semiconductor and SEA Construction), the water partner that finances and owns the water plants (EPCOR), the power utility (named only in the news), a drilled shaft firm with no website or phone we could verify (Texas Shafts), firms named only in payment-dispute listings, suppliers building their own plants nearby, chip customers, tool vendors and individuals. Phones are each firm's own main or office line from its own site, except Page's and CDM Smith's, which come from the state filings; Jacobs' and Stantec's Austin lines on the filings are noted too. Samsung C&T, Jordan Foster, Nomura Micro Science and Samoo list no US main line on their own sites, so we give their websites only. Yates, Samsung E&A, Clayco, Primoris, Garney, DIS-TRAN and Austin Bridge & Road are head or regional offices, not Taylor. First published Nov. 20, 2026. We'll update this page when a new filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 20, 2026- Samsung Semiconductor: Taylor page (read Nov. 20, 2026)
- Samsung Austin Semiconductor 2025 Economic Impact Report
- TDLR TABS2023004768, Semiconductor FAB (registered Nov. 5, 2022)
- TDLR TABS2023004769, Manufacturing Facility (registered Nov. 5, 2022)
- TDLR TABS2023004770, GCS Building (registered Nov. 5, 2022)
- TDLR TABS2026016417, FAB Cleanroom Observation Deck (registered Mar. 31, 2026)
- TDLR TABS2023022470, Office 1 TI Workplace
- TDLR TABS2024002520, TI Showroom
- TCEQ construction stormwater general permit search, Williamson County (read Nov. 20, 2026)
- Construction Dive: Samsung picks Yates Construction for $17B chip plant (Mar. 20, 2023)
- ENR Texas & Southeast Best Projects 2025: Samsung T-Project (Oct. 13, 2025)
- Samsung C&T newsroom: Making the fabs that make semiconductors (Dec. 9, 2022)
- The Korea Herald (Nov. 8, 2026)
- Korea JoongAng Daily: groundwork for Samsung's second Taylor fab (Aug. 18, 2026)