When is pricing due on the Samuell High School packages?
Satterfield & Pontikes posted the job, "W.W. Samuell HS Replacement 95% CD", to its public plan room on Nov. 9, 2026, with bids due at 3 PM Central on Dec. 10, 2026. The page reads "Pricing due: December 10, 2026, 3:00 PM CST" and lists 76 packages, from 01A General Requirements to 33A Site Utilities.
It says the construction manager "is seeking budget pricing" for the new school and that "The package covers Divisions 02-33." The documents are the 95% construction drawings and 95% specifications, for CMAR GMP Package 207441-GMP-01A. That pricing feeds the job's guaranteed maximum price, and the page doesn't say how subcontracts are awarded after it.
RFIs are due at 5 PM on Nov. 20, 2026. Every package lists a job walk on Nov. 17 at 2 PM and an expected start of Feb. 9, 2027. The page states no value for any package.
What is the new Samuell High School?
The state accessibility registration, filed Sept. 17, 2026, reads "NEW CONSTRUCTION OF HIGH SCHOOL TO ACCOMODATE 2,000 STUDENTS" with an estimated cost of $168,000,000, an estimated start of Jan. 11, 2027 and an end of Jan. 11, 2029.
The bid page describes a three-level campus of about 311,000 square feet, Type II-B and fully sprinklered, with "brick and stone veneer, long-span canopies with wood-look soffits, and large areas of storefront and curtainwall glazing." Its program runs from a main auditorium of about 888 seats and a second auditorium to competition and P.E. gyms, science labs and a mechanical penthouse with an outdoor chiller yard.
Dallas ISD released the first renderings on Nov. 9, 2026. It wrote that design should be complete by April 2027, that construction is planned from April 2027 through November 2028, and that the campus opens in fall 2030.
What do the city's records show at 8928 Palisade Drive?
ATI holds six City of Dallas records for the site. The commercial demolition permit, applied July 28, 2026 and in its inspection phase, names The Demo Company and removes the existing school, its portables, its foundations and its piers to 10 feet below grade. A tree removal record tied to that permit was marked revisions required.
Two site plan reviews followed, on Oct. 14 and Oct. 27, 2026. The first describes a "New 310,000 gross square foot WW Samuell High School" for 2,000 students, and the second lists an "800 seat auditorium" and a "2000 seat competition gym." A pre-development review from February 2026 and a permit extension from August 2026 complete the six. No building permit for the new school is in the records we hold.
Why are there two dollar figures?
The state registration gives an estimated cost of $168,000,000 for the building. The district's bond page gives a total budget of $200M, and The Dallas Morning News called the project the "$200 million reconstruction of W.W. Samuell High School" in May 2026. A district budget usually carries more than construction, so we use $168 million for the building and name the $200 million as the budget.
Who covered the Samuell rebuild, and who didn't?
The press covered the bond. Voters approved Dallas ISD's $6.2 billion bond in May 2026, and the Morning News named Samuell one of the highest-priority projects. We found no news story naming the construction manager, its 76 packages or the demolition firm, and the district's own project page still lists the contractor as TBD.
How do the ways into the Samuell High School job compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| Price the construction manager | Your budget price on one of the 76 packages, by 3 PM on Dec. 10 | Trade contractors and suppliers | A place in the price the builder takes to the district | It's budget pricing on 95% drawings, and the page doesn't say how subcontracts are awarded later |
| Sell to the demolition firm | Hauling, recycling and equipment for the teardown of the old school | Haulers, recyclers, rental and abatement suppliers | Work on a job that is already permitted | The permit was applied for in July 2026, so part of the work may be done |
| Get specified with the architect | Your product written into Corgan's documents or approved as an equal | Manufacturers and their reps | Your product named across the whole school | The drawings and specifications are at 95% |
| Walk the site on Nov. 17 | The job walk the bid page lists for every package | Estimators pricing any package | A look at the site before you price | It's at 2 PM on Nov. 17, inside this week's window |
| The next campus | Getting known to the district's bond program manager | Firms that want Dallas ISD's later replacement schools | A shot at the bond's other new campuses | It isn't a door into this school's pricing |
Who should go after the Samuell job, and who shouldn't?
| Glazing contractors and glass suppliers | The bid page calls for large areas of storefront and curtain wall on a three-level school, and package 08D is priced by Dec. 10. |
|---|
| MEP, fire protection and low-voltage contractors | HVAC, plumbing, electrical, sprinklers, fire alarm, cabling, access control and cameras are all separate packages under the same date. |
|---|
| Theater, athletic and specialty suppliers | Two auditoriums, a black box theater and a 2,000-seat competition gym bring seating, stage, lighting, bleacher and scoreboard packages. |
|---|
| Firms that only sell after a contract is signed | This isn't the job for you yet: the page asks for budget pricing, and the district hasn't listed a contractor on its project page. |
|---|
What should you do next on the Samuell job?
- Open Satterfield & Pontikes' public plan room, find "W.W. Samuell HS Replacement 95% CD" and join the package you sell.
- Send your questions before the RFI deadline of 5 PM on Nov. 20, 2026, and walk the site on Nov. 17 at 2 PM if you can.
- Get your budget price to the construction manager by 3 PM Central on Dec. 10, 2026.
- Open the full list for the demolition firm, the architect, the program manager and every package.
Questions people ask about the new W.W. Samuell High School
Who is building the new W.W. Samuell High School?
Satterfield & Pontikes Construction is the construction manager at risk on its own public bid page, which reads "Construction Manager: SFP2 Construction (CMAR)" and sits in Satterfield & Pontikes' plan room. The district's bond page still lists the contractor as TBD.
When is pricing due on the Samuell High School packages?
The bid page says "Pricing due: December 10, 2026, 3:00 PM CST" for all 76 packages. RFIs are due at 5 PM on Nov. 20, 2026, and every package lists a job walk on Nov. 17 at 2 PM.
Is this a bid for award?
The page says the construction manager "is seeking budget pricing" on the 95% construction drawings and specifications, for CMAR GMP Package 207441-GMP-01A. That pricing feeds the job's guaranteed maximum price. The page doesn't say how subcontracts will be awarded after that.
How much will the new Samuell High School cost?
The state accessibility registration gives an estimated cost of $168,000,000. The district's bond page gives a total budget of $200M, and The Dallas Morning News reported a $200 million reconstruction. The budget is the district's whole project figure, and the registration is a construction estimate.
Where is the new Samuell High School being built?
At 8928 Palisade Drive, Dallas, Texas 75217, in Pleasant Grove, on the site of the existing school. The bid page says the existing site athletics remain, except the tennis courts.
How big is the new Samuell High School?
The bid page says "Approximately 311,000 SF, three levels", and the city's site plan reviews describe a 310,000-gross-square-foot school for 2,000 students in grades 9 through 12.
What is in the building?
The bid page lists a main auditorium of about 888 seats, a second auditorium, a black box theater, competition and P.E. gyms, science and career labs, a food service kitchen and a mechanical penthouse with an outdoor chiller yard. The city's site plan review lists an 800-seat auditorium and a 2,000-seat competition gym, so confirm counts in the drawings.
Who designed the new Samuell High School?
Corgan. The bid page reads "Architect: Corgan" and the bond page "Architect: Corgan Associates Inc." The district released the first renderings of the new campus on Nov. 9, 2026.
Who is demolishing the old Samuell building?
The city's commercial demolition permit, applied for on July 28, 2026, names The Demo Company. Its scope removes the one- and two-story school building, the portables, the foundations and the piers to 10 feet below grade.
How can a subcontractor or supplier get on this job?
Join the package you sell in Satterfield & Pontikes' public plan room and send your budget price by 3 PM Central on Dec. 10, 2026. A manufacturer whose product isn't specified needs Corgan's approval as an equal.
When does construction start and when does the school open?
The bid page lists an expected start of Feb. 9, 2027 and the state registration Jan. 11, 2027. The district wrote on Nov. 9, 2026 that construction is planned from April 2027 through November 2028, with the campus opening in fall 2030.
What are the risks of chasing this job?
It's budget pricing, not an award, and the start dates on the bid page, the state registration and the district's post don't agree. Check the plan room for addenda before you price.
How we built this list
We read Satterfield & Pontikes' public plan room on BuildingConnected (the opportunity list and the school's project page, with all 76 packages), the state accessibility registration for the school, Dallas ISD's bond page, the district's Nov. 9, 2026 and Aug. 4, 2026 news posts and its May 19, 2026 community presentation, and the City of Dallas records ATI holds for 8928 Palisade Drive, and we searched the press. A row is a pricing row only where the construction manager's page gives the date. No package value is published, so no row carries a dollar figure for its package. First published Nov. 10, 2026. We'll update this page when the construction manager posts an addendum or a new date, or the city issues a building permit for the school.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 10, 2026- Satterfield & Pontikes public plan room, bid opportunities
- Satterfield & Pontikes plan room, W.W. Samuell HS Replacement 95% CD
- TDLR, Dallas ISD - W.W. Samuell High School registration TABS2027001370
- Dallas ISD bond program, W.W. Samuell High School
- Dallas ISD Hub, A new chapter for W.W. Samuell High School, Nov. 9, 2026
- Dallas ISD Hub, Building momentum for new school year, Aug. 4, 2026
- Dallas ISD, W.W. Samuell HS community visioning session, May 19, 2026
- City of Dallas, Accela permit portal
- The Dallas Morning News, Dallas ISD voters approved historic $6.2 billion bond issue, May 3, 2026
- NBC DFW, Dallas ISD plans 26 new schools after voters approve historic bond, May 4, 2026
- Corgan, office locations
- TEXO, The Demo Company listing