What is being built on the Second Avenue Subway Phase 2?
Phase 2 extends the Q line north from 96th St to 125th St into East Harlem and Harlem. It adds three new stations, at 106th St, 116th St and 125th St, and every one will be accessible. The 125th St station links to the 4, 5 and 6 trains, Metro-North and the M60 bus.
The MTA says East Harlem has been a subway desert since the Second Avenue El stopped running above 57th St in 1940. Phase 1, from 63rd St to 96th St, opened on Jan. 1, 2017. The state says Phases 1 and 2 together will serve 300,000 riders a day.
The new line reuses tunnel built in the 1970s, including the stretch from 110th to 120th St. A new tunnel will run from 120th St to 125th St and Lenox Ave.
How much does the Second Avenue Subway Phase 2 cost?
The state says the whole project is budgeted at $6.968 billion. The federal grant agreement puts the total cost at $7,699.03 million, or about $7.7 billion.
The federal government signed a $3.4 billion grant in November 2023. The three contracts awarded so far add up to about $3.1 billion to $3.2 billion, the sum: $1.972 billion for the tunnel, $1.02 billion for the 106th St station and $116.8 million to $182 million for the utility work (the award record shows $116.8 million; the state announced $182 million).
Who is digging the Second Avenue Subway tunnels?
In August 2025 the state announced the $1.972 billion tunneling contract, C-26202, for Connect Plus Partners, a joint venture of Halmar International and FCC Construction. It covers the new tunnel from 120th St to 125th St and Lenox Ave, work for the future 116th St station in the 1970s tunnel and the space for the 125th St station. COWI is its lead designer, and Geocomp watches the ground and nearby buildings.
The state's 2025 release describes 750-ton machines with 22-foot cutting heads, digging 35 to 120 feet below Second Avenue. Ground was broken at the 120th St launch site on June 8, 2026, and jet grouting there, to clear obstructions from the machine's path, started Nov. 14, 2026. The machine goes in the ground in early 2027.
Who is building the 106th St station?
In June 2026 the MTA awarded Contract 3, a $1.02 billion design-build contract, to a joint venture of Skanska, Traylor Bros. and Walsh Construction. The job is the station's structural shell between 105th and 110th St, its entrances and tie-ins, with substantial completion by August 2030 on a 50-month term. Mott MacDonald leads its design.
Before the station can go in, C.A.C. Industries is moving the pipes, wires and vaults under Second Avenue on Contract 1, C-26201, with Tectonic Engineering as construction manager. In its September 2026 update on that contract, the state said Contract 1 was about 60 percent complete and expected to be finished by summer 2027. On Nov. 23, 2026, crews shifted traffic to start trunk main utility work between 104th and 105th St.
What permits are on the Second Avenue Subway Phase 2?
New York City's building records show the program's filings on 37 Second Avenue buildings since Sept. 19, 2023. They cover underpinning, cellar doors, vaults and building protection next to the work, and C.A.C. Industries is the applicant on every issued permit.
The biggest stated cost is $1,847,880 to underpin 2100 Second Avenue (M01120847-I1), filed Oct. 29, 2024. The newest issued permit, M01245490-I1, is for cellar door and vault work at 2128 Second Avenue, issued Oct. 19, 2026.
Did the federal government stop the Second Avenue Subway?
News reports say the Trump administration held back federal money for the Hudson Tunnel and the Second Avenue Subway, $18 billion for the two together. The MTA sued, the money was restored in April 2026, and the state broke ground on the major construction stage on June 8, 2026. The state says trains are on track to run in 2032.
Which engineering firms are on the Second Avenue Subway Phase 2?
STV and WSP, as the Phase 2 Partnership joint venture, are the MTA's design consultant, on a contract now worth about $255.5 million. AECOM and HNTB, as a joint venture, are the program management consultant over three of the four construction contracts, on a $186.6 million contract awarded in April 2025. AKRF is the environmental consultant.
The last big contract, Contract 4, covers the systems and station fit-out, including 22 elevators and 20 escalators. The MTA asked for qualifications in September 2026 and plans to pick a builder in mid-2027. 16 firms in all are on the list below.
Who the MTA hired before
On Phase 1 of the same line (63rd to 96th St, opened 2017), the MTA used several of the same engineering firms now on Phase 2.
- AECOM (DMJM+Harris/Arup JV): engineer on Engineering services for the Second Avenue line (Phase 1), Manhattan, NY, 2001. Also on this job.
- WSP USA (Parsons Brinckerhoff): construction manager on Construction management for the Second Avenue Subway (Phase 1), Manhattan, NY, 2007. Also on this job.
- Skanska (with J.F. Shea and Schiavone): builder on Second Avenue Subway Phase 1, Manhattan, NY, 2017. Also on this job.
- 86th Street Constructors JV: builder on 86th Street Station finishes (C-26012, $253.7M), Manhattan, NY, 2013.
- Judlau Contracting: builder on 63rd St Station reconstruction for the Second Avenue Subway (C26006, $229.5M), Manhattan, NY, 2011.
These are earlier or other jobs for the same owner. They are not counted in the 16 firms on this job.
How do the ways into the Second Avenue Subway Phase 2 compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Second Avenue Subway Phase 2 | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The contract still to be awarded | A place on a team bidding Contract 4, the systems and station fit-out | Electrical, elevator, systems and finish subcontractors | A share of the last big contract, with 22 elevators and 20 escalators | No award yet; the MTA plans to pick a builder in mid-2027 |
Who should go after the Second Avenue Subway Phase 2?
| Tunneling, concrete and steel suppliers | Connect Plus Partners (Halmar and FCC) on the $1.972 billion tunnel contract, and the Skanska-Traylor-Walsh team on the $1.02 billion 106th St station shell. |
|---|
| Utility, pipe and underground suppliers | C.A.C. Industries, moving the pipes, wires and vaults under Second Avenue, with trunk main work started Nov. 23, 2026. |
|---|
| Engineering, survey and monitoring firms | COWI, Mott MacDonald, Geocomp and Tectonic on the contracts, and the design and program teams (STV and WSP, AECOM and HNTB). |
|---|
What should you do next on the Second Avenue Subway Phase 2?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the Second Avenue Subway Phase 2 in East Harlem.
- Watch for the Contract 4 award, planned for mid-2027.
Questions people ask about the Second Avenue Subway Phase 2
How much does the Second Avenue Subway Phase 2 cost?
The state budgets it at $6.968 billion. The federal grant agreement puts the total cost at about $7.7 billion. The federal government signed a $3.4 billion grant for it in November 2023.
Who is building the Second Avenue Subway Phase 2?
The MTA owns the job. C.A.C. Industries is moving the utilities (Contract 1), Connect Plus Partners, a Halmar International and FCC Construction joint venture, is digging the tunnel ($1.972 billion, Contract 2), and Skanska, Traylor Bros. and Walsh are building the 106th St station ($1.02 billion, Contract 3). 16 firms are named on the job, listed above.
Who won the Second Avenue Subway tunnel contract?
Connect Plus Partners, a joint venture of Halmar International and FCC Construction, won the $1.972 billion tunneling contract in August 2025. COWI is its lead designer.
Who is building the 106th St station on the Second Avenue Subway?
A joint venture of Skanska, Traylor Bros. and Walsh Construction, on a $1.02 billion design-build contract awarded in June 2026, with substantial completion by August 2030. Mott MacDonald leads the design.
When will the Second Avenue Subway Phase 2 open?
The state says the project is on track for trains in 2032.
Where are the new Second Avenue Subway stations?
At 106th St, 116th St and 125th St in East Harlem, Manhattan. The 125th St station, near Lexington Ave, links to the 4, 5 and 6 trains, Metro-North and the M60 bus.
What is happening on Second Avenue now?
On Nov. 23, 2026, crews started trunk main utility work on Second Avenue between 104th and 105th St. Jet grouting at the 120th St tunnel launch site started Nov. 14, 2026.
When does the Second Avenue Subway tunnel boring machine start?
The machine goes in the ground at 120th St and Second Ave in early 2027 and digs to 125th St and Lenox Ave. The state's 2025 release describes 750-ton machines with 22-foot cutting heads.
Did the Trump administration stop the Second Avenue Subway?
News reports say the administration held back federal money for the Second Avenue Subway and the Hudson Tunnel. The MTA sued, the money was restored in April 2026, and the state broke ground on the major construction stage on June 8, 2026.
Which Second Avenue Subway contract is still to be awarded?
Contract 4: the systems and station fit-out, with 22 elevators and 20 escalators. The MTA plans to pick a builder in mid-2027.
How can subcontractors get on the Second Avenue Subway Phase 2?
Call the firms already on the job, starting with Connect Plus Partners for the tunnel, the Skanska-Traylor-Walsh team for the 106th St station and C.A.C. Industries for the utility work. For Contract 4, the way in is a team that bids it.
What happens next on the Second Avenue Subway Phase 2?
The utility work is due in summer 2027, the tunnel machine launches in early 2027 and a Contract 4 builder is picked in mid-2027. We'll update this page when a new contract or firm appears.
How we built this list
We read the governor's releases of Jan. 22, 2024, Aug. 18, 2025, June 8, 2026 and Sept. 14, 2026, the MTA's construction notices, the MTA's award records in New York's public authority procurement data, New York City building filings and permits, the firms' own releases and trade news, all on Nov. 24, 2026. We kept each firm a public record names on Phase 2. Connect Plus Partners, the joint venture that holds the tunnel contract, is listed as well as its two members, Halmar and FCC, each as a partner, because the MTA's award record names the joint venture itself; the design joint ventures are listed only through their members. Contract values for joint ventures are for the whole team, not one firm's share. The award record shows $116.8 million for Contract 1; the state announced $182 million. Left out: the MTA (the owner), lawyers, appraisers, landlords, building owners on the city filings, people named on the filings, losing bidders, a relocation consultant whose MTA record does not name Phase 2, a community outreach venture with no named members, a staffing vendor, a concrete supplier seen only in a photo, the tunnel machine's maker (not confirmed) and Phase 1 firms. Phones are each firm's own line from its own site; Halmar's line stands for Connect Plus Partners; Traylor, Walsh and Geocomp are head office lines; and C.A.C. Industries, FCC, COWI, AECOM and WSP have no line we could verify on their own sites. First published Nov. 24, 2026. We'll update this page when a new contract, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 24, 2026- MTA: Second Avenue Subway Phase 2 project page (updated Nov. 23, 2026)
- MTA construction notice: trunk main work on 2 Av, 104-105 St (Nov. 23, 2026)
- MTA construction notice: jet grouting at 120 St and 2 Av (Nov. 14, 2026)
- NY Governor: MTA advances final construction contract (Sept. 14, 2026)
- NY Governor: groundbreaking on the major construction stage (June 8, 2026)
- NY Governor: tunneling contract award (Aug. 18, 2025)
- NY Governor: $182 million utility relocation contract (Jan. 22, 2024)
- ENR: MTA awards $1B contract for Second Ave Subway Phase II station package (June 1, 2026)
- Construction Dive: Skanska, Walsh, Traylor on the NYC subway extension (June 2, 2026)
- Walsh Group: Skanska-Traylor-Walsh JV awarded $1.02B contract (June 2026)
- ENR: AECOM-HNTB team wins $186M contract to manage the extension (March 26, 2025)
- COWI: lead design for New York's 2nd Avenue Subway expansion (Sept. 26, 2025)
- Geocomp: selected for key phase of Second Avenue Subway expansion (2026)
- Mass Transit: MTA selects Tectonic Engineering for construction management (Dec. 2024)
- Tectonic Engineering: Second Avenue Subway project page
- STV: construction milestone on Second Avenue Subway Phase 2 (June 10, 2026)
- Smart Cities Dive: MTA Second Avenue Subway in East Harlem (June 9, 2026)
- FTA: FY26 Annual Report on Funding Recommendations (Nov. 2025)
- NY public authority procurement data: MTA contract C-26202
- NY public authority procurement data: MTA contract C-26201
- NY public authority procurement data: MTA contract D81483
- NY public authority procurement data: MTA contract C81190
- NY public authority procurement data: MTA contract C81191
- NYC Department of Buildings permits issued (read Nov. 24, 2026)
- NYC Department of Buildings job filings (read Nov. 24, 2026)
- NY procurement data, MTA contract C81188
- NY procurement data, MTA contracts C81338/C81338A
- NY procurement data, MTA contract C26012
- NY procurement data, MTA contract C26006