What is Serverfarm building in Clarksville, Arkansas?
Serverfarm is building a data center campus near Johnson Regional Medical Center in Clarksville. The plan is four two-story buildings, ARK1 to ARK4. Each is 300,000 sq ft and needs about 108 MW, for 1.2 million sq ft and 432 MW in all, on a 135-acre site.
The company says the buildings use a closed-loop cooling system that recirculates water instead of using it up. Project leaders will not name the tenant, but in July 2026 they called it a "Fortune 10" tech company with a household name.
How much is the Serverfarm Clarksville data center?
Serverfarm says it is investing $6.6 billion to build the campus. On Nov. 18, 2026, its chief people officer put the cost at 5 to 6 billion dollars, fully paid by Serverfarm.
The $55 billion figure is not the cost. In July 2026 the city council approved up to $50 billion in industrial bonds to Hatchbo LLC and up to $5 billion to SF ARK1 LLC, which is Serverfarm. That is a ceiling on the bonds the city may issue. Serverfarm also plans $548 million in payments in lieu of taxes through 2060, and it has already paid $2.1 million in city construction permit fees.
Why are Clarksville voters deciding on the data center bonds?
Residents filed petitions against the two bond ordinances the council passed in July. The petitions needed 291 signatures and had about 350 valid ones. On Sept. 28, 2026, the council set a special election for Tuesday, Dec. 1, 2026.
On Oct. 8, 2026, the Johnson County Quorum Court heard a request for a pause on future data centers in the county. That request covers future projects, not this one.
Where will the Clarksville data center get its power?
The four buildings need about 432 MW. The mayor says the whole city uses 40 MW on its busiest day. So at first most of the power will come from a gas plant Solaris Energy Infrastructure is building and will run next to the campus, with 40 gas turbines.
The city utility, Clarksville Connected Utilities, approved an energy service agreement for the first 318 MW of phase one, plus water and sewer. Three new 161 kV lines are being built for the campus, and the utility holds an 18 MW block of capacity for the project's first stage. Throughline is buying the easements for about 4 miles of new line, paid by Serverfarm.
How far along is the Clarksville data center?
By July 20, 2026, all four building pads were ready, the second building's foundations were done and drilling had started for the third. On Oct. 7, 2026, crews set the last steel beam on ARK1, and the CEO pledged $150,000 to Clarksville schools.
Serverfarm expects the first building done by May 2027, if the Solaris plant is finished by then,. It held a job fair on Nov. 17, 2026 and opened a downtown office at 116 South Fulton Street on Nov. 18. Building will take more than 2,000 workers at its peak.
Which firms are building the Clarksville data center?
Serverfarm is working with three builders: Nabholz Construction of Conway, Arkansas, and Yates Construction and Eutaw Construction Company, both from Mississippi. A subcontractor's case study lists Yates, Nabholz and NABCO Mechanical & Electrical as the lead team, and Sitewide Project Solutions handles electrical execution, safety and completions management.
Kimley-Horn drew up the site's stormwater plan. The city utility's engineers on the job are Olsson for water and Fisher Arnold for drawings and construction review. 12 firms in all are on the list below.
Who Serverfarm hired before
Serverfarm's Houston campus went to a national data center builder and a Dallas design firm; neither is named in Clarksville, where it hired Southern builders.
- Clune Construction: builder on CTX1, retrofit of a nearly 500,000 sq ft data center, Houston, TX, 2026.
- HKS Inc.: design firm on serverfarm - HTX2, $137 million, 565,000 sq ft ground-up data center, Hockley, TX, 2025.
These are earlier or other jobs for the same owner. They are not counted in the 12 firms on this job.
How do the ways into the Serverfarm Clarksville data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Serverfarm's Clarksville data center | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Serverfarm Clarksville data center?
| Electrical and mechanical distributors and reps | NABCO Mechanical & Electrical on the lead team and Sitewide on electrical and completions work, on four buildings of 108 MW each. |
|---|
| Steel, concrete and building suppliers | Nabholz Construction, Yates Construction and Eutaw Construction Company, with buildings 2 and 3 under way after ARK1 topped out. |
|---|
| Power, gas and line suppliers | Solaris's 40-turbine gas plant next door, and Clarksville Connected Utilities' new 161 kV lines, with Fisher Arnold reviewing the drawings. |
|---|
What should you do next on the Serverfarm Clarksville data center?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Serverfarm's ARK data center campus in Clarksville, Arkansas.
- Watch the Dec. 1, 2026 bond vote and the work on buildings 2 to 4.
Questions people ask about the Serverfarm Clarksville data center
How much does the Serverfarm Clarksville data center cost?
Serverfarm says it is investing $6.6 billion. A company officer put it at 5 to 6 billion dollars on Nov. 18, 2026. The $55 billion on the ballot is a ceiling on bonds, not the cost.
What is the $55 billion Clarksville bond vote?
In July 2026 the council approved up to $50 billion in industrial bonds to Hatchbo LLC and up to $5 billion to SF ARK1 LLC (Serverfarm). Residents forced a public vote with petitions, and the election is Dec. 1, 2026. The amount is the most the city may issue, not what the campus costs.
Who is building the Clarksville data center?
Serverfarm says it is working with Nabholz Construction, Yates Construction and Eutaw Construction Company. NABCO Mechanical & Electrical is listed with Yates and Nabholz on the lead team, and Sitewide handles electrical execution, safety and completions management.
Who is the tenant of the Clarksville data center?
Serverfarm has not named it. Project leaders called it a "Fortune 10" tech company with a household name.
How much power will the Clarksville data center use?
About 432 MW for four buildings of 108 MW each. The mayor says the whole city uses 40 MW on its busiest day.
Where will the power come from?
At first, mostly from a natural gas plant Solaris Energy Infrastructure is building and will run next to the campus, with 40 gas turbines. Clarksville Connected Utilities is adding new 161 kV lines.
When will the first building open?
Serverfarm expects the first building done by May 2027, if the Solaris plant is finished by then. ARK1's steel topped out on Oct. 7, 2026.
How many jobs will the Clarksville data center create?
More than 2,000 construction jobs at the peak and more than 200 permanent jobs, Serverfarm says. It held a job fair on Nov. 17, 2026.
How big is the Clarksville data center?
Four two-story buildings of 300,000 sq ft each, 1.2 million sq ft in all, on a 135-acre site.
How can subcontractors and suppliers get on the Clarksville data center?
Call the firms already on the job, starting with Nabholz Construction, Yates Construction and Eutaw Construction Company for the buildings, NABCO and Sitewide for mechanical and electrical work, and Solaris for the power plant.
What happens next on the Clarksville data center?
The bond vote is Dec. 1, 2026. Crews are working on buildings 2 and 3, and the first building is due by May 2027. We'll update this page when a new contract, filing or firm appears.
How we built this list
We read Serverfarm's fact sheet and Arkansas page, the city utility's commission agendas and minutes from June to November 2026, the state air permit list, local and trade news on the bond vote, the power plant and the topping-out, and a subcontractor's own case study, all on Nov. 25, 2026. We kept each firm a public record names on this campus; all 12 were checked word for word against their source. Left out: the owner and its bond affiliate, the land agent, the bond lawyers and the utility's lawyer, a financial adviser not yet hired, the regional grid operator, a training college, and firms named only in one newsletter's bid list (the architect and engineers) or in an older fuel cell plan that has since given way to the gas plant. The city's permit site blocks scripts, so we did not read its permits. The $6.6 billion is Serverfarm's own figure; the $55 billion is a bond ceiling, not a cost. Phones are each firm's own line from its own site; Nabholz, Yates, Eutaw, NABCO and Solaris are head offices, Olsson and Fisher Arnold are Arkansas offices, and we found no line for Kimley-Horn, Throughline or SymbioPower. First published Nov. 25, 2026. We'll update this page when a new contract, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 25, 2026- Serverfarm: Clarksville data center campus fact sheet (Oct. 2026)
- Serverfarm: Arkansas campus page (read Nov. 25, 2026)
- KATV: multi-billion-dollar data center under construction in Clarksville (Nov. 18, 2026)
- Johnson County Graphic: Serverfarm opens downtown office (Nov. 24, 2026)
- Johnson County Graphic: Serverfarm topping-out and school donation (Oct. 13, 2026)
- Johnson County Graphic: quorum court hears data center moratorium request (Oct. 13, 2026)
- Johnson County Graphic: Clarksville sets December referendum on revenue bonds (Sept. 29, 2026)
- Johnson County Graphic: council work session on the data center (July 21, 2026)
- Johnson County Graphic: air permit and site clearing records (March 3, 2026)
- KNWA: Clarksville residents to vote on $55B in bond ordinances (Sept. 29, 2026)
- MLQ: Serverfarm tops out 108MW first building (Oct. 19, 2026)
- Sitewide: Serverfarm Clarksville case study (read Nov. 25, 2026)
- Clarksville Connected Utilities: commission agenda and minutes (July 27, 2026)
- Clarksville Connected Utilities: commission agenda (Aug. 24, 2026)
- Clarksville Connected Utilities: commission agenda (Nov. 16, 2026)
- Arkansas DEQ: permit database export (read Nov. 25, 2026)
- Clune Construction, 2026-05-12
- TDLR