What is Sites Reservoir?
Sites Reservoir is a new off-stream reservoir in the Antelope Valley west of Maxwell, in Colusa County, California. It will hold 1.5 million acre-feet of water, enough for the yearly use of at least 7.5 million people. It is the largest new reservoir in California in more than 50 years.
The Sites Project Authority, a joint powers authority based in Maxwell, owns the job, with the state Department of Water Resources and the Bureau of Reclamation as partners. The reservoir needs two 300-foot earthen dams, the Golden Gate Dam and the Sites Dam, plus 9 smaller dams 20 to 100 feet high, the three-quarter-mile Sites-Lodoga Bridge and an inlet/outlet structure. A separate conveyance package covers pumping and generating plants, large pipelines and tunnels, and a 230 kV substation and lines.
How much will Sites Reservoir cost?
Sites Reservoir is estimated to cost $6.2 billion to $6.8 billion, per news reports in November 2026. It is an estimate, not money spent.
The biggest piece so far is the reservoir and roads package, worth up to $3 billion, which Barnard Construction Company runs as construction manager at risk. The 2027 contract list put to the board on Nov. 20, 2026 sets five-and-a-half-year ceilings, 2022 to June 2027, for its consultants: CH2M Hill Engineers $19,250,829, HDR $18,725,738, ICF $16,252,849, Brown and Caldwell $15,119,976 and AECOM $13,746,854.
What permits has Sites Reservoir won?
On Nov. 4, 2026, the State Water Board voted 5-0 to approve the water right for Sites Reservoir. It allows diversions of up to 986,000 acre-feet a year. Gov. Gavin Newsom said: "California can't afford to keep waiting for the water storage we need."
On Oct. 15, 2026, the Army Corps' Sacramento District issued the Section 404 permit for Work Package 1, SPK-2001-00055. It covers site prep, access roads, borrow areas, the Golden Gate Dam foundation and a tunnel-bored diversion at Stone Corral Creek, on a 1,725.86-acre site. It permanently fills 10.66 acres of wetlands and 14.03 acres of other waters. The Authority's board accepted the permit on Nov. 6, 2026. The state's Section 401 certification came in September 2026.
Who is building Sites Reservoir?
On Jan. 16, 2026, the Sites Project Authority picked Barnard Construction Company, of Bozeman, Montana, as construction manager at risk for the up to $3 billion reservoir and roads package. Dozens of union workers protested the choice at the board meeting in Maxwell, and Gov. Newsom sent a letter the same day raising concerns.
By May 2026 Barnard had signed a project labor agreement with the building trades, whose unions represent about 90% of the craft hours on its contract. Ames Construction, Barnard's key subcontractor, is bound by it, and its work includes most, if not all, of the carpentry on the job.
On Nov. 6, 2026, the board raised Barnard's geotechnical task order by $610,000, to $1.66 million, to drill the Golden Gate Dam's left abutment ridge. The Authority says the work could shorten the dam and save substantial construction cost.
Who is bidding the next Sites Reservoir contracts?
On Oct. 16, 2026, the board shortlisted three teams for the conveyance contract: Barnard-Ames Joint Venture, FlatironDragados Aecon Joint Venture and Kiewit Infrastructure West Company. They are shortlisted to bid, not hired. The request for proposals goes to them in November 2026, proposals are due in February 2027, and the award is planned for April or May 2027.
On June 26, 2026, the board shortlisted two firms for the terrestrial compensatory mitigation contract, the habitat work that makes up for land the reservoir takes: RES and Westervelt Ecological Services. We found no award yet.
Which engineers are on Sites Reservoir?
AECOM handles reservoir engineering, and CH2M Hill Engineers, a Jacobs company, handles conveyance engineering and operations modeling. HDR provides engineering and permitting staff, ICF handles environmental permitting, and Brown and Caldwell handles project controls.
Fugro USA Land billed the Authority for geotechnical engineering in September 2026, and MBK Engineers does water rights and reservoir operations modeling. 13 firms in all are on the list below.
How do the ways into Sites Reservoir compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Sites Reservoir | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The contracts still to be awarded | A place on a team bidding the conveyance package, or with a firm bidding the habitat mitigation contract | Pipe, pump, electrical and tunnel subcontractors | A share of a contract not yet awarded | No award yet; conveyance proposals are due in February 2027 |
Who should go after Sites Reservoir?
| Earthwork, concrete and heavy equipment suppliers | Barnard Construction and Ames Construction on the up to $3 billion reservoir and roads package: two 300-foot earthen dams, 9 smaller dams and the Sites-Lodoga Bridge. |
|---|
| Pipe, pump and electrical suppliers | The conveyance package of pumping and generating plants, pipelines, tunnels and a 230 kV substation. Three teams are shortlisted to bid; proposals are due in February 2027. |
|---|
| Engineering, survey and testing firms | AECOM, CH2M Hill (Jacobs), HDR, ICF, Brown and Caldwell, Fugro and MBK, all already working for the Authority. |
|---|
What should you do next on Sites Reservoir?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Sites Reservoir near Maxwell, California.
- Watch for the conveyance award, planned for April or May 2027, and the start of construction by July 2027.
Questions people ask about Sites Reservoir
How much will Sites Reservoir cost?
It is estimated to cost $6.2 billion to $6.8 billion, per news reports in November 2026. The reservoir and roads package that Barnard Construction manages is worth up to $3 billion. These are estimates, not money spent.
Who is building Sites Reservoir?
The Sites Project Authority owns the job. Barnard Construction Company is the construction manager at risk on the up to $3 billion reservoir and roads package, and Ames Construction is its key subcontractor. 13 firms are named on the job, listed above.
Where is Sites Reservoir?
In the Antelope Valley west of Maxwell, in Colusa County, California, with part in Glenn County. The Golden Gate Dam sits on Funks Creek in Colusa County.
How big is Sites Reservoir?
It will hold 1.5 million acre-feet of water, enough for the yearly use of at least 7.5 million people. It needs two 300-foot earthen dams and 9 smaller dams 20 to 100 feet high. It is the largest new reservoir in California in more than 50 years.
When will Sites Reservoir be built?
Construction is set to begin by July 2027 and finish in 2034. Barnard is already drilling the Golden Gate Dam ridge under a $1.66 million task order.
Did Sites Reservoir get its water right?
Yes. On Nov. 4, 2026, the State Water Board voted 5-0 to approve the water right, allowing diversions of up to 986,000 acre-feet a year.
What is the Army Corps permit for Sites Reservoir?
The Army Corps' Sacramento District issued the Section 404 permit for Work Package 1 (SPK-2001-00055) on Oct. 15, 2026. It covers site prep, access roads, borrow areas, the Golden Gate Dam foundation and a diversion tunnel at Stone Corral Creek. The Authority's board accepted it on Nov. 6, 2026.
Why did unions protest Sites Reservoir?
Dozens of union workers protested the choice of Barnard Construction, a Montana firm, for the reservoir contract in January 2026. Gov. Gavin Newsom sent a letter of concern on Jan. 16, 2026. Barnard has since signed a project labor agreement with the building trades, whose unions represent about 90% of the craft hours on its contract.
Which Sites Reservoir contracts are still to be awarded?
The conveyance package: pumping and generating plants, large pipelines, tunnels and a 230 kV substation and lines. Three teams are shortlisted to bid: Barnard-Ames Joint Venture, FlatironDragados Aecon Joint Venture and Kiewit Infrastructure West Company. Proposals are due in February 2027. Two firms are also shortlisted for the habitat mitigation contract.
How can subcontractors get on Sites Reservoir?
Call the firms already on the job, starting with Barnard Construction and Ames Construction on the reservoir package. For the conveyance package, the way in is one of the three shortlisted teams before proposals are due in February 2027.
What are the risks on Sites Reservoir?
The cost is an estimate, the conveyance contract is not yet awarded, and labor issues drew a protest and a letter from the governor in January 2026. Construction has not started; it is set to begin by July 2027.
How we built this list
We read the Sites Project Authority's board items from January to November 2026 (the Barnard selection, the project labor agreement update, the Army Corps permit, the Barnard task order, the conveyance and mitigation shortlists, the 2027 consultant contract list and the Nov. 20 payment list), the State Water Board and governor's releases, and news reports, all on Nov. 24, 2026. We kept each firm a public record names on this project. Nine are under contract; four (Kiewit, FlatironDragados Aecon Joint Venture, Westervelt and RES) are shortlisted to bid and not hired. Barnard-Ames Joint Venture, also shortlisted for the conveyance package, is the same two firms as rows 1 and 2, so it is not counted twice. Contract ceilings are the most each consultant may be paid from 2022 to June 2027, not money spent. Left out: the owner and partner agencies, lawyers, financial advisors, lobbying and communications firms, land agents, the Authority's own contract staff, labor unions, a firm seen only on a sign-in sheet, and a permitting firm with no website we could find. The firm drilling the Golden Gate Dam under Barnard is not named in the records we read. Phones are each firm's own line from its own site; Barnard, HDR and Brown and Caldwell are headquarters or general lines, Flatiron's is its Atlanta office, and the other firms show no main line we could verify, so we give their websites. First published Nov. 24, 2026. We'll update this page when a new contract, permit or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 24, 2026- Press Democrat: Newsom administration approves largest new reservoir in California in 50 years (Nov. 5, 2026)
- Office of the Governor: largest new reservoir in more than 50 years clears final permit (Nov. 5, 2026)
- State Water Board: water right approved for Sites Reservoir (Nov. 4, 2026)
- Sites Project Authority: Barnard Construction selected for the reservoir contract (Jan. 16, 2026)
- Sites Project Authority board item 3.1: status update on the reservoir CMAR project labor agreement (Feb. 20, 2026)
- Sites Project Authority board item 1.4: construction workforce policy and the executed reservoir project labor agreement (June 26, 2026)
- Agri-Pulse: Sites backers pick controversial construction firm despite labor protests (Jan. 21, 2026)
- Sites Project Authority board item 1.1: Army Corps Section 404 permit for Work Package 1 (Nov. 6, 2026)
- Sites Project Authority board item 1.2: task order amendment for Barnard Construction (Nov. 6, 2026)
- Sites Project Authority board item 2.3: conveyance CMAR shortlist (Oct. 16, 2026)
- Sites Project Authority board item 2.4: terrestrial compensatory mitigation shortlist (June 26, 2026)
- Sites Project Authority board item 2.2: 2027 consultant contract authority (Nov. 20, 2026)
- Sites Project Authority board item 1.4: payment of claims (Nov. 20, 2026)
- Sites Project Authority: CH2M Hill task order amendment (Oct. 16, 2026)
- Sites Project Authority: HDR task order amendment (Oct. 16, 2026)
- Sites Project Authority: monthly status report (Nov. 20, 2026)
- Sites Project Authority: draft minutes of the Nov. 6, 2026 special board meeting
- Sites Project Authority: conveyance package CMAR request for qualifications (May 2026)