What is being built at Six Fisher Island?
The Residences at Six Fisher Island is a 50-home condo at 6 Fisher Island Dr, on the last buildable lot of Fisher Island in Miami-Dade County. The island sits in ZIP code 33109, which a 2018 analysis of IRS income data ranked as the richest ZIP code in America, with an average income of $2.5 million in 2015. Related Group is the developer, with BH Group, Teddy Sagi and Wanxiang America. The owner on the county permits for the project is PRH Parcel 7 Owner LLC.
The county's master permit lists one residential building of 584,671 sq ft, with 50 units and 12 floors. The developers call it a 10-story building. Homes run from 3,800 to 16,000 sq ft, with 3 to 8 bedrooms, and the plans include north and south podiums and villa homes. A separate county permit covers a new bulkhead, dredging and moorings on the waterfront.
How much is Six Fisher Island worth?
Miami-Dade County values the construction at $154.3 million on master permit 2024067740, issued Aug. 19, 2024. The same value is copied onto the trade permits, so it is one job, not a sum.
The homes cost far more to buy. Two penthouses sold for a combined $150 million, and homes start at $15 million. Those are sale prices, not what the building costs to build.
Who is building Six Fisher Island?
Coastal Construction is the general contractor. The master permit names Coastal Condominiums of Miami LLC, at Coastal's own headquarters address and phone, and Coastal's own project page says it is building the job. Coastal also holds the $3.9 million marina permit for the bulkhead, dredging and moorings, with Moffatt & Nichol as the marine engineer.
Kobi Karp designed the building, and CFE Architects is the architect of record. Tara Bernerd & Partners did the interiors, and Enea Garden Design is the landscape architect.
Which trades are on the Six Fisher Island permits?
The county's trade permits name OC Electrical for the building's power, Hart Mechanical for heating and air, TASCO Plumbing for plumbing and gas, and Polaris Fire Protection for the sprinklers. HEDsouth holds the low-voltage permit.
On the outside, the permits name Ocean Doors and Windows and GM&P Glazing, plus two roofers, Isaacs Roofing and Crown Roofing. Dillon Pools holds the pool and spa permits, Arazoza Brothers holds a plumbing permit, and LTG Carlson Fence put up the job-site fence.
How far along is Six Fisher Island?
Work began in September 2024. By August 2026 the tower cranes were taken down, and glass railings, podiums, pools and amenity decks were under way. Completion is expected in late 2026 or 2027.
The county issued a generator test permit on Aug. 17, 2026 and a temporary elevator test permit on Aug. 27. On Nov. 13 it issued Dillon Pools a $207,000 cabana pool permit, and on Nov. 18 it approved an inspection on the master building permit. No certificate of occupancy is on the record yet.
How do the ways into Six Fisher Island compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on The Residences at Six Fisher Island | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after Six Fisher Island?
| Pool, deck and landscape suppliers | Dillon Pools on the cabana pool ($207,000), spas and cold plunge; Arazoza Brothers and Enea Garden Design on the grounds. |
|---|
| Electrical, HVAC and plumbing reps | OC Electrical, Hart Mechanical, TASCO Plumbing, Polaris Fire Protection and HEDsouth, on a building the county values at $154.3 million. |
|---|
| Glass, roofing and finish suppliers | Ocean Doors and Windows, GM&P Glazing, Isaacs Roofing and Crown Roofing, with Tara Bernerd & Partners on the interiors. |
|---|
What should you do next on Six Fisher Island?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on The Residences at Six Fisher Island, 6 Fisher Island Dr.
Questions people ask about Six Fisher Island
How much is Six Fisher Island worth?
Miami-Dade County values the construction at $154.3 million on master permit 2024067740. The same value repeats on the trade permits, so it is one job, not a sum. Two penthouses sold for $150 million combined, and homes start at $15 million.
Who is building Six Fisher Island?
Coastal Construction is the general contractor and holds the master building permit. Related Group is the developer with BH Group, Teddy Sagi and Wanxiang America. 19 firms are named on the job, listed above.
How much do homes at Six Fisher Island cost?
Homes start at $15 million, and two penthouses sold for a combined $150 million. Those are sale prices, not the cost to build.
Who designed Six Fisher Island?
Kobi Karp is the design architect and CFE Architects is the architect of record. Tara Bernerd & Partners did the interiors and Enea Garden Design is the landscape architect.
How big is Six Fisher Island?
The county permit lists 50 units, 12 floors and 584,671 sq ft. The developers call it a 10-story building, with homes of 3,800 to 16,000 sq ft and 3 to 8 bedrooms.
When will Six Fisher Island be finished?
Completion is expected in late 2026 or 2027. The tower cranes came down by August 2026, and no certificate of occupancy is on the record yet.
What is the newest permit on Six Fisher Island?
On Nov. 13, 2026, Miami-Dade issued Dillon Pools a $207,000 permit for the cabana pool. On Nov. 18, the county approved an inspection on the master building permit.
Which trade contractors work on Six Fisher Island?
The county permits name OC Electrical (electrical), Hart Mechanical (heating and air), TASCO Plumbing (plumbing and gas), Polaris Fire Protection (sprinklers), HEDsouth (low voltage), Dillon Pools (pools and spas), two roofers, two window and glass firms and a fence firm.
How can suppliers get on Six Fisher Island?
Call the firms already on the job, starting with the ones whose trade matches what you sell. With the cranes down and the pools under way, the work left is mostly finishes, pools, decks and the marina.
What happens next on Six Fisher Island?
Pool, spa and finish work runs on toward delivery in late 2026 or 2027. We'll update this page when a new permit or firm appears.
How we built this list
We read Miami-Dade County's permit records for 6 Fisher Island Dr on Nov. 20, 2026, about 52 records, along with the property appraiser's parcel record, local real estate news, national business news on the penthouse sale and the ZIP code ranking, the sales agent's building page, and the project pages of Coastal Construction and Fisher Marantz Stone. We kept each firm a county permit or a public page names on this building. Each permit's trade comes from its permit type; for Ocean Doors and Windows and Arazoza Brothers, the line of work comes from the firm, not the permit. Record dates are each permit's issue date or the date of the page. The $154.3 million is the county's construction value on the master permit, repeated on the trade permits, so we never add them up. Left out: the owner and developers, the lender, the loan broker and the sales agent, the firms on the old 2023 demolition and 2020 seawall work, a restaurant operator, and a site work firm on the 2023 fill permit for which we found no phone or website. Phones are each firm's own line from its own site, except OC Electrical, Hart Mechanical, Ocean Doors and Windows and GM&P Glazing, whose phones are the ones shown on the county permit. Tara Bernerd & Partners lists only its London office line on its site. First published Nov. 20, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 20, 2026- Miami-Dade County building permit 2024067740, master permit (read Nov. 20, 2026)
- Miami-Dade County building permit 2027009292, cabana pool (read Nov. 20, 2026)
- Miami-Dade County building permit 2026043658, bulkhead, dredge and mooring (read Nov. 20, 2026)
- Miami-Dade County building permit 2026067967, temporary elevator test (read Nov. 20, 2026)
- PROFILEmiami: Related Group and BH Group nearing completion on The Residences at Six Fisher Island (Aug. 10, 2026)
- Douglas Elliman: The Residences at Six Fisher Island (read Nov. 20, 2026)
- Coastal Construction: The Residences at Six Fisher Island (read Nov. 20, 2026)
- Fisher Marantz Stone: 6 Fisher Island project page (read Nov. 20, 2026)
- Bloomberg: Miami condo king scores $150 million for two island penthouses (April 4, 2024)
- Bloomberg via Fortune: America's richest ZIP code is Fisher Island, from 2015 IRS data (April 12, 2018)