What did Spartanburg County approve for data centers?
On Nov. 16, 2026, Spartanburg County Council gave final approval to development agreements for three data centers (WYFF). Valara, NorthMark Strategies' project in the old Kohler plant at 4000 S Pine St, lists roughly $2.8 billion. AIB Data Centers' CLT1 in Moore lists about $1.2 billion, and 300 Jones Road Associates lists $1.5 billion on the former R.R. Donnelley plant.
That is about $5.5 billion in planned investment, the sum of the three. Each figure is the company's anticipated investment over years, including power and equipment, not a construction contract. The council approved Valara 3-2 and the other two unanimously, and advanced three more AIB agreements on first reading the same night.
What is being built at the Valara data center in Spartanburg?
Valara is the only one of the three under construction. Jacobs is the general contractor on the county's $771,185,805 permit to turn Kohler Building 1 into a high performance compute center, issued Sept. 5, 2025, and Jacobs says it is the EPCM lead for the program. NorthMark said in May 2026 that about 1,445 workers were on site daily.
WYFF calls Valara a 457 megawatt data center, but 457 MW is the gas generation in its state air permit application: 24 Cummins generators already permitted, plus five 17 MW Baker Hughes turbines and six 54 MW GE turbines. Phase II, four new buildings of about 494,000 sq ft and the turbine plant, is in county review.
What are AIB's CLT1 and the 300 Jones Road data centers?
CLT1 is a former bitcoin mine of about 16 acres at 389 Tyger River Industrial Dr in Moore. AIB Data Centers' 10-Q says it will provide 50 MW of IT capacity in two 25 MW data halls to a customer guaranteed by Nebius Group, with target dates in the fourth quarter of 2027 and the first quarter of 2028. Integrated Design Solutions filed a $300 million building permit application for it on Oct. 9, 2026.
The county denied the 300 Jones Road site plan the developer filed in April 2026 (county records). The developer appealed in July and refiled on Oct. 30, 2026 for a 60 MW data center of about 200,000 sq ft, now in review. We found no general contractor on the record for CLT1 or Jones Road.
Who gets what on the Valara data center?
NorthMark has not published a trade split. By the math on Turner & Townsend's data center cost index, about $370 million of Valara's $771.2 million Building 1 permit is electrical work, about $254 million is pipes, heat and air, and about $69 million is the building shell. The county's own trade permits put MMR's Data Hall 1 electrical at $52.9 million and Performance Contractors' Phase 2 mechanical application at $30 million.
Which firms are on the Spartanburg County data centers?
On Valara, the county's permits name Jacobs as general contractor; MMR Constructors, Miller Electric and Gross Electric for electrical; Performance Contractors and Environmental Air Systems for mechanical; KSBG Plumbing for underground plumbing; Shambaugh & Son for sprinklers; and Communication Technology Services for emergency radio. MMR's $74.5 million Data Hall 2 permit shows Void, so we list MMR on Data Hall 1.
NorthMark names LEL Critical, which integrates some of the power systems, and Asheville Hwy Rental as local partners. The air permit application names Cummins, Baker Hughes and GE as the generator and turbine makers, and a Transco metering station, Williams' pipeline, is on Jacobs' access road permit.
On CLT1, Integrated Design Solutions is the architect, Thomas & Hutton the civil engineer and Universal Civil Construction the listed contact on the zoning permit. Thomas & Hutton is also the engineer on Jones Road, where Duke Energy supplies the power. 19 firms in all are on the list below.
How do the ways into the Spartanburg County data centers compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Spartanburg data center | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Spartanburg County data centers?
| Electrical distributors and gear reps | MMR's $52.9 million Data Hall 1 electrical, Miller Electric's busway and Gross Electric on Valara. |
|---|
| Mechanical, HVAC and plumbing reps | Performance Contractors' $30 million Phase 2 mechanical application, Environmental Air Systems' HVAC and KSBG's plumbing. |
|---|
| Fire protection and power suppliers | Shambaugh & Son's sprinkler permits, and LEL Critical on the on-site power systems. |
|---|
What should you do next on the Spartanburg County data centers?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the Valara, CLT1 or Jones Road data center in Spartanburg County.
Questions people ask about the Spartanburg County data centers
How much are the Spartanburg County data centers?
The three development agreements list roughly $2.8 billion for Valara, about $1.2 billion for AIB's CLT1 and $1.5 billion for 300 Jones Road (WYFF). That is about $5.5 billion in planned investment, the sum. The biggest permit on the record is Valara's Building 1 permit, $771,185,805.
Who is building the Valara data center in Spartanburg?
Jacobs is the general contractor on the Building 1 permit and the EPCM lead for the program. 19 firms are named across the three data centers, listed above.
Where are the three Spartanburg County data centers?
Valara is at 4000 S Pine St in Spartanburg, in the old Kohler plant. AIB's CLT1 is at 389 Tyger River Industrial Dr in Moore. The third is at 300 Jones Rd in Spartanburg, the former R.R. Donnelley plant; county records file it under 430 Jones Rd.
Is Valara a 457 megawatt data center?
No. 457 MW is the on-site natural gas generation in Valara's state air permit application: 24 Cummins generators of 2,000 kW, five 17 MW Baker Hughes turbines and six 54 MW GE turbines. It is power the site makes, not computing load.
How did Spartanburg County Council vote on the data centers?
On Nov. 16, 2026 the council approved Valara's agreement 3-2 and the CLT1 and 300 Jones Road agreements unanimously (WYFF; Spartanburg Herald-Journal).
Who is the tenant of AIB's CLT1 data center?
AIB Data Centers' 10-Q says CLT1 will provide 50 MW of critical IT capacity in two 25 MW data halls to a customer whose obligations are guaranteed by its parent, Nebius Group N.V. The target dates for the halls are the fourth quarter of 2027 and the first quarter of 2028.
Who is building CLT1 and the 300 Jones Road data center?
We found no general contractor on the record for either yet. Integrated Design Solutions is the architect on CLT1's $300 million permit application, and Thomas & Hutton is the civil engineer on both sites.
How many people work on the Valara data center?
NorthMark said in May 2026 that about 1,445 workers were on site daily, roughly one in three from Spartanburg County.
What happened to the 300 Jones Road data center plan?
The county denied the site plan filed in April 2026 (county records). The developer appealed in July and refiled on Oct. 30, 2026 for a 60 MW, approximately 200,000 sq ft data center, which is in review. Its developer says Duke Energy allocated power from its Peach Valley Switching Station.
What happens next on the Spartanburg data centers?
Valara's construction runs through 2028, with a Phase II of four new buildings and the turbine plant in county review. CLT1's permits were filed in October 2026, and the Jones Road site plan is in review.
How we built this list
We read Spartanburg County's public permit records for the three sites (contacts from the portal's public record, read Nov. 18, 2026), Valara's state air permit application, AIB Data Centers' 10-Q, NorthMark's May 2026 community update, the Jones Road developer's site, Jacobs' project page and WYFF, and kept each firm a record or the company names on these jobs. Jones Road's permits are filed under 430 Jones Rd. Left out: two law firms, the CLT1 landowner, contractors on the earlier bitcoin mining work, a plumbing firm on Valara's $2.15 million plumbing permit known only by an email address, and individuals on the permits. Two Phase 1 mechanical permits carry a value we read as a data entry error, so we quote none for them. The trade split is the math on Turner & Townsend's published data center shares, applied to Valara's Building 1 permit. Phones are each firm's own office line; KSBG Plumbing, GE Vernova, Cummins and Duke Energy have no verified main line, and Williams' is its general inquiries line. First published Nov. 19, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 19, 2026- WYFF4: Spartanburg County Council approves three data center agreements, advances three more (Nov. 16, 2026)
- Spartanburg County Citizen Self Service permit records (EnerGov), read Nov. 18, 2026
- SCDES air construction permit application, Valara Holdings (April 23, 2026)
- NorthMark Strategies: MoC1 community update (May 5, 2026, hosted by WSPA)
- AIB Data Centers Inc. Form 10-Q, quarter ended Sept. 30, 2026 (Nov. 13, 2026)
- Jacobs project page (read Nov. 18, 2026)
- Project Jones Road Spartanburg, the developer's site (read Nov. 18, 2026)