Who's building Spartanburg County's $5.5 billion in data centers

Spartanburg County, South Carolina just approved deals for $5.5 billion in data centers, and one already has a $771 million building permit.

By Porter Stanley. Updated .

On Nov. 16, 2026, Spartanburg County Council gave final approval to development agreements for three data centers: Valara in the old Kohler plant at 4000 S Pine St (roughly $2.8 billion), AIB Data Centers' CLT1 in Moore (about $1.2 billion) and 300 Jones Road ($1.5 billion), per WYFF. That is about $5.5 billion in planned investment, the sum of the three. Only Valara is being built: Jacobs is the general contractor on its $771.2 million Building 1 permit, issued Sept. 5, 2025, and MMR Constructors holds the $52.9 million Data Hall 1 electrical permit. 19 firms are named on the three jobs; the list below has all 19.

$5.5BPlanned investment in the three agreements (the sum of WYFF's figures)
$771.2MValara Building 1 permit (Jacobs)
457 MWOn-site gas generation in Valara's air permit application
19Firms named on the jobs

Get all 19 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 19 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 19 firms on the Spartanburg County data centers?

We list the 19 firms named on the Spartanburg County data centers, one row each, grouped by site, with where each name comes from.

1Permit on the recordSep 5, 2025

Jacobs (Jacobs Engineering Group Inc., dba Jacobs Project Management Co.)

General contractor on the Building 1 conversion of the old Kohler plant, and EPCM lead for the program on the Valara data center at 4000 S Pine St in Spartanburg County

Valara / NorthMark MOC-1 data center, 4000 S Pine St (former Kohler plant), Spartanburg (Spartanburg County), SC

Building permit COMERCONST-0725-2009, value $771,185,805, issued Sept. 5, 2025

Work: General contractor on the Building 1 conversion of the old Kohler plant, and EPCM lead for the program

Who to call: Jacobs (Jacobs Engineering Group Inc., dba Jacobs Project Management Co.)
Jacobs office line
(Dallas, TX)
(214) 638-0145

The opportunity: Renovation of the existing Kohler building 1 facilities to repurpose them for High Performance Compute Center operations. (Contact type: General Contractor, JACOBS ENGINEERING GROUP INC DBA: JACOBS PROJECT MANAGEMENT CO)

2Permit on the recordJul 27, 2026

MMR Constructors, Inc. (MMR Group)

Electrical contractor for the Building 1 / Data Hall 1 electrical workscope, Phase 1 on the Valara data center at 4000 S Pine St in Spartanburg County

Valara / NorthMark MOC-1 data center, 4000 S Pine St (former Kohler plant), Spartanburg (Spartanburg County), SC

Electrical permit BCELECTRIC-0726-2537, value $52,912,371, issued July 27, 2026

Work: Electrical contractor for the Building 1 / Data Hall 1 electrical workscope, Phase 1

Who to call: MMR Constructors, Inc. (MMR Group)
MMR Constructors, Inc. office line
(Greenville, SC)
(864) 299-8661

The opportunity: Electrical Workscope - for Building 1 or DH1. PHASE 1. Renovation of the existing Kohler Building 1 facilities to repurpose them for High Performance Compute Center Operations. (Electrical Contractor: MMR CONSTRUCTORS INC)

3Permit on the recordNov 24, 2025

Miller Electric Company

Electrical contractor installing 1200A and 3000A busway, with load bank testing and commissioning on the Valara data center at 4000 S Pine St in Spartanburg County

Valara / NorthMark MOC-1 data center, 4000 S Pine St (former Kohler plant), Spartanburg (Spartanburg County), SC

Electrical permit BCELECTRIC-1125-2260, value $9,313,370, issued Nov. 24, 2025

Work: Electrical contractor installing 1200A and 3000A busway, with load bank testing and commissioning

Who to call: Miller Electric Company
Miller Electric Company office line
(Jacksonville, FL)
(904) 388-8000

The opportunity: INSTALLATION OF 1200A & 3000A BUSWAY/BUSDUCT. INCLUDING LOAD BANK TESTING, THERMAL SCAN, CX, COMMISSIONING (Electrical Contractor: MILLER ELECTRIC COMPANY, 6805 Southpoint Pkwy, Jacksonville, FL)

What did Spartanburg County approve for data centers?

On Nov. 16, 2026, Spartanburg County Council gave final approval to development agreements for three data centers (WYFF). Valara, NorthMark Strategies' project in the old Kohler plant at 4000 S Pine St, lists roughly $2.8 billion. AIB Data Centers' CLT1 in Moore lists about $1.2 billion, and 300 Jones Road Associates lists $1.5 billion on the former R.R. Donnelley plant.

That is about $5.5 billion in planned investment, the sum of the three. Each figure is the company's anticipated investment over years, including power and equipment, not a construction contract. The council approved Valara 3-2 and the other two unanimously, and advanced three more AIB agreements on first reading the same night.

What is being built at the Valara data center in Spartanburg?

Valara is the only one of the three under construction. Jacobs is the general contractor on the county's $771,185,805 permit to turn Kohler Building 1 into a high performance compute center, issued Sept. 5, 2025, and Jacobs says it is the EPCM lead for the program. NorthMark said in May 2026 that about 1,445 workers were on site daily.

WYFF calls Valara a 457 megawatt data center, but 457 MW is the gas generation in its state air permit application: 24 Cummins generators already permitted, plus five 17 MW Baker Hughes turbines and six 54 MW GE turbines. Phase II, four new buildings of about 494,000 sq ft and the turbine plant, is in county review.

What are AIB's CLT1 and the 300 Jones Road data centers?

CLT1 is a former bitcoin mine of about 16 acres at 389 Tyger River Industrial Dr in Moore. AIB Data Centers' 10-Q says it will provide 50 MW of IT capacity in two 25 MW data halls to a customer guaranteed by Nebius Group, with target dates in the fourth quarter of 2027 and the first quarter of 2028. Integrated Design Solutions filed a $300 million building permit application for it on Oct. 9, 2026.

The county denied the 300 Jones Road site plan the developer filed in April 2026 (county records). The developer appealed in July and refiled on Oct. 30, 2026 for a 60 MW data center of about 200,000 sq ft, now in review. We found no general contractor on the record for CLT1 or Jones Road.

Who gets what on the Valara data center?

NorthMark has not published a trade split. By the math on Turner & Townsend's data center cost index, about $370 million of Valara's $771.2 million Building 1 permit is electrical work, about $254 million is pipes, heat and air, and about $69 million is the building shell. The county's own trade permits put MMR's Data Hall 1 electrical at $52.9 million and Performance Contractors' Phase 2 mechanical application at $30 million.

Which firms are on the Spartanburg County data centers?

On Valara, the county's permits name Jacobs as general contractor; MMR Constructors, Miller Electric and Gross Electric for electrical; Performance Contractors and Environmental Air Systems for mechanical; KSBG Plumbing for underground plumbing; Shambaugh & Son for sprinklers; and Communication Technology Services for emergency radio. MMR's $74.5 million Data Hall 2 permit shows Void, so we list MMR on Data Hall 1.

NorthMark names LEL Critical, which integrates some of the power systems, and Asheville Hwy Rental as local partners. The air permit application names Cummins, Baker Hughes and GE as the generator and turbine makers, and a Transco metering station, Williams' pipeline, is on Jacobs' access road permit.

On CLT1, Integrated Design Solutions is the architect, Thomas & Hutton the civil engineer and Universal Civil Construction the listed contact on the zoning permit. Thomas & Hutton is also the engineer on Jones Road, where Duke Energy supplies the power. 19 firms in all are on the list below.

How do the ways into the Spartanburg County data centers compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on the Spartanburg data centerEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell

Who should go after the Spartanburg County data centers?

Electrical distributors and gear repsMMR's $52.9 million Data Hall 1 electrical, Miller Electric's busway and Gross Electric on Valara.
Mechanical, HVAC and plumbing repsPerformance Contractors' $30 million Phase 2 mechanical application, Environmental Air Systems' HVAC and KSBG's plumbing.
Fire protection and power suppliersShambaugh & Son's sprinkler permits, and LEL Critical on the on-site power systems.

What should you do next on the Spartanburg County data centers?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on the Valara, CLT1 or Jones Road data center in Spartanburg County.

Questions people ask about the Spartanburg County data centers

How much are the Spartanburg County data centers?

The three development agreements list roughly $2.8 billion for Valara, about $1.2 billion for AIB's CLT1 and $1.5 billion for 300 Jones Road (WYFF). That is about $5.5 billion in planned investment, the sum. The biggest permit on the record is Valara's Building 1 permit, $771,185,805.

Who is building the Valara data center in Spartanburg?

Jacobs is the general contractor on the Building 1 permit and the EPCM lead for the program. 19 firms are named across the three data centers, listed above.

Where are the three Spartanburg County data centers?

Valara is at 4000 S Pine St in Spartanburg, in the old Kohler plant. AIB's CLT1 is at 389 Tyger River Industrial Dr in Moore. The third is at 300 Jones Rd in Spartanburg, the former R.R. Donnelley plant; county records file it under 430 Jones Rd.

Is Valara a 457 megawatt data center?

No. 457 MW is the on-site natural gas generation in Valara's state air permit application: 24 Cummins generators of 2,000 kW, five 17 MW Baker Hughes turbines and six 54 MW GE turbines. It is power the site makes, not computing load.

How did Spartanburg County Council vote on the data centers?

On Nov. 16, 2026 the council approved Valara's agreement 3-2 and the CLT1 and 300 Jones Road agreements unanimously (WYFF; Spartanburg Herald-Journal).

Who is the tenant of AIB's CLT1 data center?

AIB Data Centers' 10-Q says CLT1 will provide 50 MW of critical IT capacity in two 25 MW data halls to a customer whose obligations are guaranteed by its parent, Nebius Group N.V. The target dates for the halls are the fourth quarter of 2027 and the first quarter of 2028.

Who is building CLT1 and the 300 Jones Road data center?

We found no general contractor on the record for either yet. Integrated Design Solutions is the architect on CLT1's $300 million permit application, and Thomas & Hutton is the civil engineer on both sites.

How many people work on the Valara data center?

NorthMark said in May 2026 that about 1,445 workers were on site daily, roughly one in three from Spartanburg County.

What happened to the 300 Jones Road data center plan?

The county denied the site plan filed in April 2026 (county records). The developer appealed in July and refiled on Oct. 30, 2026 for a 60 MW, approximately 200,000 sq ft data center, which is in review. Its developer says Duke Energy allocated power from its Peach Valley Switching Station.

What happens next on the Spartanburg data centers?

Valara's construction runs through 2028, with a Phase II of four new buildings and the turbine plant in county review. CLT1's permits were filed in October 2026, and the Jones Road site plan is in review.

How we built this list

We read Spartanburg County's public permit records for the three sites (contacts from the portal's public record, read Nov. 18, 2026), Valara's state air permit application, AIB Data Centers' 10-Q, NorthMark's May 2026 community update, the Jones Road developer's site, Jacobs' project page and WYFF, and kept each firm a record or the company names on these jobs. Jones Road's permits are filed under 430 Jones Rd. Left out: two law firms, the CLT1 landowner, contractors on the earlier bitcoin mining work, a plumbing firm on Valara's $2.15 million plumbing permit known only by an email address, and individuals on the permits. Two Phase 1 mechanical permits carry a value we read as a data entry error, so we quote none for them. The trade split is the math on Turner & Townsend's published data center shares, applied to Valara's Building 1 permit. Phones are each firm's own office line; KSBG Plumbing, GE Vernova, Cummins and Duke Energy have no verified main line, and Williams' is its general inquiries line. First published Nov. 19, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 19 firms, free

All 19 firms on the Spartanburg County data centers

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.