Who's building OpenAI and Oracle's $15 billion Stargate in Abilene

By Porter Stanley. Updated .

Crusoe is building the first Stargate campus for OpenAI and Oracle on the Lancium Clean Campus in Abilene, Texas: eight data center buildings of about 480,000 square feet each, 1.2 gigawatts in all, funded by a $15 billion joint venture with Blue Owl and Primary Digital Infrastructure. DPR Construction leads the build with prime contractors Rosendin (electrical) and Southland (mechanical), and in September 2026 Oracle said 6 of the 8 buildings had been delivered. 17 firms are named on the campus; the list below has all 17.

$15BJoint venture funding the campus (Crusoe)
1.2 GWEight buildings
7,000+Workers on site a day (Dec. 2025)
17Firms named on the job

Get all 17 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 17 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 17 firms on the Abilene Stargate campus?

We list the 17 firms named on the Abilene Stargate campus, one row each, with where each name comes from.

1Named in the newsAug 4, 2025

DPR Construction

Lead construction partner on the Abilene Stargate campus

Crusoe's Stargate campus for OpenAI and Oracle, Lancium Clean Campus, 615 FM 2404, Abilene (Taylor County)

Work: Lead construction partner

Who to call: DPR Construction
DPR Construction office line
(Redwood City, CA)
(214) 979-9900

The opportunity: So far, the team, led by DPR Construction and prime contractors Rosendin Electric and Southland Brandt, has proven it can deliver each 474,000-sq-ft single-story building in under a year.

2Named by the companyDec 22, 2025

Cupertino Electric, Inc.

Named in the design team (electrical design on the Abilene Stargate campus

Crusoe's Stargate campus for OpenAI and Oracle, Lancium Clean Campus, 615 FM 2404, Abilene (Taylor County)

Work: Named in the design team (electrical design

Who to call: Cupertino Electric, Inc.
Cupertino Electric, Inc. office line
(San Jose, CA)
(877) 747-4234

The opportunity: Design Team: KH, HKS, GPLA, BW Design Group, MPS, Cupertino Electric, Maverick, Sabre

3Named in the newsSep 10, 2026

Modular Power Solutions

Rosendin subsidiary that built about 60% of the electrical infrastructure as prefabricated modules on the Abilene Stargate campus

Crusoe's Stargate campus for OpenAI and Oracle, Lancium Clean Campus, 615 FM 2404, Abilene (Taylor County)

Work: Rosendin subsidiary that built about 60% of the electrical infrastructure as prefabricated modules

Who to call: Modular Power Solutions
Modular Power Solutions office line
(McKinney, TX)
(469) 907-8870

The opportunity: Rosendin developed 60 percent of the necessary electrical infrastructure through Modular Power Solutions, a wholly owned subsidiary of Rosendin, headquartered in McKinney, Texas.

What is Crusoe building in Abilene?

Crusoe is building the first Stargate campus on the Lancium Clean Campus north of Abilene: eight single-story data center buildings of about 480,000 square feet each, 1.2 gigawatts in all, run by Oracle for OpenAI. A $15 billion joint venture of Crusoe, Blue Owl Capital and Primary Digital Infrastructure funds it. Texas filings put a single building's shell at $292 million and one building's data hall fit-out at $384 million.

More than 7,000 construction workers were on site each day in December 2025. On Sept. 10, 2026, Oracle said 6 of the 8 buildings, 618 megawatts, had been delivered to the customer.

Who gets what?

No one has published the campus's trade split. By the math on Turner & Townsend's data center cost index, about $7.2 billion of the $15 billion is electrical work and about $5 billion is pipes, heat and air.

Which firms are on the job?

DPR Construction leads the build and manages about 60 subcontractors, with Rosendin and Southland Industries as design-build electrical and mechanical primes; Rosendin's Modular Power Solutions built about 60% of the electrical gear in its shops. HKS is the design firm on the Texas filings, AlfaTech engineered the campus, GPLA did structural engineering and Digital Building Components installed the wall panels. Crusoe's own partner list adds Cupertino Electric, W&W|AFCO Steel, E2 Optics, Goins Crane, Cherry Coatings and BW Design Group. Mortenson builds the campus substations for Lancium, and federal safety records name Abilene Glass & Mirror and Ruiz-Boyter as subcontractors. 17 firms in all are on the list below.

How do the ways into the Abilene Stargate campus compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on the Abilene Stargate campusEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell

Who should go after the Abilene Stargate campus?

Electrical distributors and gear repsRosendin, Modular Power Solutions and Cupertino Electric on 1.2 gigawatts of buildings.
Mechanical, chiller and pipe repsSouthland Industries' chilled water and plumbing, and Ruiz-Boyter's pipe insulation.
Steel, panel and glass suppliersW&W|AFCO Steel, Digital Building Components and Abilene Glass & Mirror.

What should you do next on the Abilene Stargate campus?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on the Abilene Stargate campus.

Questions people ask about the Abilene Stargate campus

How much is the Abilene Stargate data center?

Crusoe, Blue Owl and Primary Digital Infrastructure formed a $15 billion joint venture to fund it.

Who is building the Abilene Stargate data center?

DPR Construction leads, with Rosendin and Southland Industries as primes. 17 firms are named in all, listed above.

Is the Abilene Stargate finished?

Not yet. Oracle said in September 2026 that 6 of the 8 buildings had been delivered.

How we built this list

We read Crusoe's releases, ENR, Texas Contractor, Texas Standard, TIME, Oracle's earnings call, Mortenson's project page and three Texas TDLR filings, and kept each firm a page names on this campus (read Nov. 17, 2026). Six firms come only from the partner list in Crusoe's award release, which gives no scope. The trade split is the math on Turner & Townsend's published data center shares. Phones are each firm's own office line. First published Nov. 17, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 17 firms, free

All 17 firms on the Abilene Stargate campus

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.