What is Crusoe building in Abilene?
Crusoe is building the first Stargate campus on the Lancium Clean Campus north of Abilene: eight single-story data center buildings of about 480,000 square feet each, 1.2 gigawatts in all, run by Oracle for OpenAI. A $15 billion joint venture of Crusoe, Blue Owl Capital and Primary Digital Infrastructure funds it. Texas filings put a single building's shell at $292 million and one building's data hall fit-out at $384 million.
More than 7,000 construction workers were on site each day in December 2025. On Sept. 10, 2026, Oracle said 6 of the 8 buildings, 618 megawatts, had been delivered to the customer.
Who gets what?
No one has published the campus's trade split. By the math on Turner & Townsend's data center cost index, about $7.2 billion of the $15 billion is electrical work and about $5 billion is pipes, heat and air.
Which firms are on the job?
DPR Construction leads the build and manages about 60 subcontractors, with Rosendin and Southland Industries as design-build electrical and mechanical primes; Rosendin's Modular Power Solutions built about 60% of the electrical gear in its shops. HKS is the design firm on the Texas filings, AlfaTech engineered the campus, GPLA did structural engineering and Digital Building Components installed the wall panels. Crusoe's own partner list adds Cupertino Electric, W&W|AFCO Steel, E2 Optics, Goins Crane, Cherry Coatings and BW Design Group. Mortenson builds the campus substations for Lancium, and federal safety records name Abilene Glass & Mirror and Ruiz-Boyter as subcontractors. 17 firms in all are on the list below.
How do the ways into the Abilene Stargate campus compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Abilene Stargate campus | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Abilene Stargate campus?
| Electrical distributors and gear reps | Rosendin, Modular Power Solutions and Cupertino Electric on 1.2 gigawatts of buildings. |
|---|
| Mechanical, chiller and pipe reps | Southland Industries' chilled water and plumbing, and Ruiz-Boyter's pipe insulation. |
|---|
| Steel, panel and glass suppliers | W&W|AFCO Steel, Digital Building Components and Abilene Glass & Mirror. |
|---|
What should you do next on the Abilene Stargate campus?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the Abilene Stargate campus.
Questions people ask about the Abilene Stargate campus
How much is the Abilene Stargate data center?
Crusoe, Blue Owl and Primary Digital Infrastructure formed a $15 billion joint venture to fund it.
Who is building the Abilene Stargate data center?
DPR Construction leads, with Rosendin and Southland Industries as primes. 17 firms are named in all, listed above.
Is the Abilene Stargate finished?
Not yet. Oracle said in September 2026 that 6 of the 8 buildings had been delivered.
How we built this list
We read Crusoe's releases, ENR, Texas Contractor, Texas Standard, TIME, Oracle's earnings call, Mortenson's project page and three Texas TDLR filings, and kept each firm a page names on this campus (read Nov. 17, 2026). Six firms come only from the partner list in Crusoe's award release, which gives no scope. The trade split is the math on Turner & Townsend's published data center shares. Phones are each firm's own office line. First published Nov. 17, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.