Who's building OpenAI's Stargate in Milam County, Texas

OpenAI's Stargate near Burlington, Texas has a $470 million state filing for its first building alone, and it's a single story covering 548,950 square feet.

By Porter Stanley. Updated .

SB Energy, a SoftBank company, is building a Stargate data center campus for OpenAI on County Road 133 near Burlington, in Milam County, Texas. The first building is filed with the state at $470 million: one single-story, 548,950 sq ft building with four data halls, and the filing names an OpenAI tenant contact. A joint venture of DPR Construction and Sundt holds the state stormwater permit for the building site. Five companies have filed state stormwater permits here since March 2025; the newest, for Building 1, was approved Oct. 2, 2026 and is listed by EPA as effective Nov. 1, 2026. 10 firms are named on the job; the list below has all 10.

$470MFirst building, state filing (TDLR)
548,950Square feet in the first building
4Data halls in the first building
10Firms named on the job

Get all 10 firms and who to call

Each one with what it does on the job and its main office line or website. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 10 firms and who to call

Each one with what it does on the job and its main office line or website. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 10 firms on the Milam County Stargate campus?

We list the 10 firms named on OpenAI's Stargate campus in Milam County, Texas, one row each, grouped by kind of firm, with where each name comes from.

1Named on a state filingJun 23, 2026

Sundt Construction (DPR Sundt Joint Venture 2, LLC)

Builder, in a joint venture with DPR Construction, on the Freebird Data Center; the joint venture holds the state stormwater permit for the site on OpenAI's Stargate campus near Burlington in Milam County, Texas

OpenAI's Stargate campus (SB Energy's Orion campus, Freebird Data Center on state filings), County Road 133 near Burlington, Milam County, TX

TCEQ construction stormwater permit, approved June 23, 2026, at 2700 County Road 133; no dollar value on a stormwater permit

Work: Builder, in a joint venture with DPR Construction, on the Freebird Data Center; the joint venture holds the state stormwater permit for the site

Who to call: Sundt Construction (DPR Sundt Joint Venture 2, LLC)
Sundt Construction office line
(Tempe, AZ)
(480) 293-3000

The opportunity: Operator: Dpr Sundt Joint Venture 2, LLC, site name Freebird Data Center (TCEQ). Baxtel, a data center tracker, also lists DPR Construction and Sundt Construction as a joint venture on Milam County 1.

2Named on a state filingJun 23, 2026

DPR Construction (DPR Sundt Joint Venture 2, LLC)

Builder, in a joint venture with Sundt, on the Freebird Data Center; the joint venture is the operator on the state stormwater permit on OpenAI's Stargate campus near Burlington in Milam County, Texas

OpenAI's Stargate campus (SB Energy's Orion campus, Freebird Data Center on state filings), County Road 133 near Burlington, Milam County, TX

TCEQ construction stormwater permit, approved June 23, 2026; the joint venture's address is in Sacramento, CA

Work: Builder, in a joint venture with Sundt, on the Freebird Data Center; the joint venture is the operator on the state stormwater permit

Who to call: DPR Construction (DPR Sundt Joint Venture 2, LLC)
www.dpr.com (DPR's site lists no office phone; contact form only)

The opportunity: Operator: Dpr Sundt Joint Venture 2, LLC, 1801 J St, Sacramento, CA; site name Freebird Data Center (TCEQ).

3Named on a state filingMar 28, 2025

McCarthy Building Companies

Operator on the first state stormwater permit, for the SB Energy Orion Data Center at 1899 County Road 133, and on two SB Energy road permits; the permits do not state its scope on OpenAI's Stargate campus near Burlington in Milam County, Texas

OpenAI's Stargate campus (SB Energy's Orion campus, Freebird Data Center on state filings), County Road 133 near Burlington, Milam County, TX

TCEQ construction stormwater permits (March 28, 2025), (April 24, 2025) and (May 13, 2025)

Work: Operator on the first state stormwater permit, for the SB Energy Orion Data Center at 1899 County Road 133, and on two SB Energy road permits; the permits do not state its scope

Who to call: McCarthy Building Companies
McCarthy Building Companies office line
(Austin, TX office)
(512) 982-7565

The opportunity: RE Name: SB Energy - Orion Data Center, 1899 County Road 133, Burlington (TCEQ). The road permits cover County Road 134 work and an access road. Not described as the building's general contractor.

What is OpenAI building in Milam County, Texas?

SB Energy, a SoftBank Group company, is building a Stargate data center campus for OpenAI on County Road 133 near Burlington, in Milam County, Texas. SB Energy calls it the Orion campus. State filings call the first building Freebird Data Center Phase 1.

SB Energy's Jan. 12, 2026 post calls it the Stargate data center in Milam County. The state filing for the first building lists an OpenAI tenant contact.

How much is the first Stargate building in Milam County?

The first building is filed with the Texas Department of Licensing and Regulation (TDLR) at $470 million, on a filing registered April 15, 2026. It is one single-story building of 548,950 sq ft, with four data halls, a loading dock and offices.

That figure is for one building, not the whole campus. We found no confirmed dollar figure for the whole campus.

How far along is the Milam County Stargate campus?

The state filing lists a start of Oct. 20, 2025 and a planned finish of Oct. 15, 2026. Baxtel, a data center tracker, said in March 2026 that steel framing and roofing were under way, and it lists the first building going into service in 2027 and a second in 2028.

Five companies have filed state stormwater permits on the campus since March 2025. The newest, for Milam Data Center Building 1, was approved, with coverage starting, Oct. 2, 2026; EPA's ECHO lists it effective Nov. 1, 2026. Its estimated project end is March 5, 2028.

Who is building the Milam County Stargate campus?

A joint venture of DPR Construction and Sundt holds the state stormwater permit for the Freebird Data Center site, approved June 23, 2026. Baxtel also lists DPR and Sundt as the builders. Corgan Architects of Dallas is the design firm on the state filing.

McCarthy Building Companies held the first stormwater permit, for the SB Energy Orion Data Center, in March 2025, plus two road permits. Mine Service of Rockdale held an earlier permit on the Freebird site. Ebco General Contractor of Cameron is building a 5.7-mile water line to US 77.

Which other firms are named on the Milam County campus?

Baxtel lists M.C. Dean as systems integrator and names Oncor, which provides transmission and distribution in ERCOT. We found no state or county record naming either one, so treat both as reported, not confirmed.

10 firms in all are on the list below, with what each one does and its main office line or website.

How do the ways into the Milam County Stargate campus compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on the Stargate campus in Milam CountyEvery supplier, distributor and sales repA conversation with a firm already working on the jobNo mechanical, plumbing or fire subcontractor is named on a public record yet, so most calls start with the DPR-Sundt joint venture

Who should go after the Milam County Stargate campus?

Electrical distributors and gear repsA four-hall, 548,950 sq ft data center building; ask the DPR-Sundt team and M.C. Dean who buys the electrical work.
Site work, concrete and pipe suppliersMine Service and McCarthy on site and roads, and Ebco on a 5.7-mile water line running into early 2027.
Mechanical, HVAC and plumbing repsNo mechanical or plumbing firm is named on a public record yet, so ask the DPR-Sundt joint venture who has the work.

What should you do next on the Milam County Stargate campus?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on the Stargate data center (Freebird Data Center) on County Road 133 near Burlington, Milam County, Texas.

Questions people ask about the Milam County Stargate campus

How much is the Stargate data center in Milam County?

The first building is filed with Texas at $470 million. That covers one single-story, 548,950 sq ft building with four data halls, not the whole campus. We found no confirmed figure for the whole campus.

Who is building Stargate in Milam County?

SB Energy, a SoftBank company, is the developer. A joint venture of DPR Construction and Sundt holds the state stormwater permit for the Freebird Data Center site. Corgan is the design firm. 10 firms are named on the job, listed above.

Where is the Milam County Stargate site?

On County Road 133 near Burlington, in Milam County, Texas. State stormwater permits list 1899 and 2700 County Road 133.

Is the Milam County campus part of OpenAI's Stargate?

Yes. SB Energy's Jan. 12, 2026 post calls it the Stargate data center in Milam County, Texas, and the state filing for the first building lists an OpenAI tenant contact.

How big is the first building?

One story and 548,950 sq ft, with four data halls, a loading dock and offices, per the state filing. Baxtel, a data center tracker, lists a second building, Milam County 2, set for 2028.

When will the Milam County data center open?

The state filing lists a start of Oct. 20, 2025 and a planned finish of Oct. 15, 2026. Baxtel says the first building goes into service in 2027. We found no source saying it has opened.

What is the newest record on the campus?

A state stormwater permit for Milam Data Center Building 1, held by Mdc Building 1, LLC. Texas approved it, with coverage starting, Oct. 2, 2026; EPA's ECHO lists it effective Nov. 1, 2026; the estimated project end is March 5, 2028.

Is there a county tax deal for the Milam County campus?

Milam County posted a draft tax deal in November 2025 that sets an $18 billion minimum investment for the first phase within five years. It is a draft; we could not confirm the county adopted it, so it is not the project's value.

Who builds the water line for the campus?

Ebco General Contractor, of Cameron, Texas, holds the state stormwater permit for Project Freebird Offsite Water Infrastructure, about 5.7 miles of line from County Road 133 to US 77, set for Aug. 2026 to Feb. 2027.

What happens next on the Milam County Stargate campus?

The Building 1 stormwater permit lists an estimated project end of March 5, 2028, and Baxtel lists a second building for 2028. We'll update this page when a new filing, permit or firm appears.

How we built this list

We read the Texas TDLR filing for the first building, every TCEQ construction stormwater permit we could find for the campus (found through EPA ECHO), SB Energy's Jan. 12, 2026 post, Baxtel's Milam County 1 profile and Milam County's draft Orion 312 agreement, all on Nov. 19, 2026, and kept each firm a record or a named source puts on this campus. The $470 million is TDLR's estimated cost for one building, not the whole campus. The $18 billion in the county's November 2025 draft tax deal is a draft minimum investment; we could not confirm the county adopted it, so we do not use it as the project's value. Sources differ on the campus's power size, so we leave it out. M.C. Dean and Oncor come only from Baxtel; we found no state or county record naming them. Left out: SoftBank (an investor, not on the job), the owner companies on the filings (Milam County Data Center LLC, Milam County DC, LLC and Mdc Building 1, LLC), a gen-tie line contractor tied to SB Energy's solar plants rather than the data center, an accessibility reviewer, firms on other Milam County jobs, and individuals on the filings. Phones are each firm's own office line from its site; DPR, Ebco, SB Energy and OpenAI list no office line we could use, so we give their websites, and M.C. Dean's is its national line. First published Nov. 19, 2026. We'll update this page when a new filing, permit or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 10 firms, free

All 10 firms on the Milam County Stargate campus

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.