What is being built in Santa Teresa?
Project Jupiter is an AI data center campus on about 1,400 acres along the Pete V. Domenici Highway, next to the Santa Teresa border crossing (Construction Review Online). The Albuquerque Journal calls it the size of a small town, with four large buildings that will house servers for Oracle and OpenAI. STACK Infrastructure and BorderPlex Digital Assets are the developers.
Clayco and Kiewit New Mexico Co. build it together. They topped out the first 855,000 square foot building in October 2026, and Clayco says the job is more than 25% complete (Construction Review Online). STACK says more than 5,000 workers are on site, 1,652 of them New Mexicans (KVIA).
The power is not there yet. The campus is to run on up to 2.45 gigawatts of Bloom Energy fuel cells (Oracle), but in October that ground was still flat (Albuquerque Journal). The air permit hearing set for Dec. 7 was called off with no new date, and the Nov. 23 deadline for a decision was waived (Albuquerque Journal, Nov. 6).
Is it really a $165 billion project?
No. Doña Ana County approved up to $165 billion in industrial revenue bonds in September 2025, on a 4-1 vote (Construction Review Online). That is a 30-year ceiling on investment, not the construction bill. A separate $18 billion loan package is paying for the build (Construction Review Online).
The best count of money spent so far is the developers' own. Their annual report to the county lists about $4.7 billion of estimated total investment through June 30, 2026, across four data center buildings and the power plant site. Oracle says more than $994 million in contracts had gone to 30 New Mexico firms by Sept. 30, 2026, in HVAC, insulation, plumbing, electrical, sanitation and equipment rental.
The developers have not published a trade split. By the math on Turner & Townsend's data center cost index, about $2.3 billion of the $4.7 billion invested through June 30, 2026 is electrical work and about $1.6 billion is pipes, heat and air.
Why is the county fighting the developers?
On Nov. 10, 2026 Doña Ana County commissioners voted 4-0 to send the developers a second breach notice in a month, because a jobs report due Oct. 31 did not arrive (Albuquerque Journal). The first notice came in late October over Oracle's plan for El Paso Electric backup power, which Oracle later walked back.
STACK says the job is already beating its hiring promises (KVIA). Work on site has not stopped: the steel is up on the first building, and contractors keep filing new permits with the EPA for work around the site.
Which firms are on the job?
Clayco and Kiewit New Mexico Co. are the builders (Clayco founder Bob Clark, Albuquerque Journal). Kiewit is also the stormwater operator for the two power plant sites (EPA stormwater records). Concrete Strategies, a Clayco company, has had crews on site since January 2026 (Searchlight New Mexico), and Albuquerque's JB Henderson Construction is one of the New Mexico firms working on it (Oracle).
EPA stormwater filings name Sundt Construction on the off-site utility work for STACK, and Smith & Aguirre Construction and RT Electric, both of Las Cruces, on the highway intersection work at NM-136 and NM-9. Bloom Energy supplies the fuel cells, Energy Transfer's Transwestern unit is behind the 17-mile gas line to feed them, Trinity Consultants prepared the air permit, and aci environmental consulting did the site study for BorderPlex. Quanta Infrastructure Solutions Group drew the stormwater plans for the second power plant site (EPA filing), Apache AllForm supplied forming for the equipment foundations (its own project list), and Santa Teresa Capital's replacement well supplies the construction water (Albuquerque Journal).
Oracle says 30 New Mexico firms hold more than $994 million in contracts, but it has not named them. 14 firms in all are named on the list below.
How do the ways into Project Jupiter compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Project Jupiter | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after Project Jupiter?
| Electrical distributors and gear reps | RT Electric on the intersection work, and a campus built around up to 2.45 gigawatts of on-site fuel cells. |
|---|
| Mechanical, HVAC and plumbing reps | JB Henderson Construction, and the HVAC, insulation and plumbing work in the $994 million Oracle says went to New Mexico firms. |
|---|
| Concrete, site and utility suppliers | Concrete Strategies, Sundt and Smith & Aguirre on the buildings, the utilities and the highway work. |
|---|
What should you do next on Project Jupiter?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Project Jupiter.
Questions people ask about Project Jupiter
How much is Project Jupiter in New Mexico?
Doña Ana County approved up to $165 billion in industrial revenue bonds, but that is a 30-year ceiling, not the cost. An $18 billion loan package finances the build, and the developers report about $4.7 billion invested through June 30, 2026.
Who is building the Stargate data center in New Mexico?
Clayco and Kiewit New Mexico Co., working together. 14 firms are named in all, listed above.
Where is Project Jupiter?
In Santa Teresa, Doña Ana County, New Mexico, along the Pete V. Domenici Highway (NM-136) next to the Santa Teresa border crossing.
How many people work on Project Jupiter?
STACK says more than 5,000 workers are on site, 1,652 of them New Mexico residents (KVIA, Nov. 11, 2026).
Why did Doña Ana County send a breach notice?
On Nov. 10, 2026 commissioners voted 4-0 to send a second notice in a month, for a jobs report due Oct. 31 that did not arrive (Albuquerque Journal).
How will Project Jupiter get its power?
From up to 2.45 gigawatts of Bloom Energy fuel cells on site. That plant is not built yet, and its air permit hearing set for Dec. 7 was called off with no new date.
How we built this list
We read EPA's public stormwater permit records for Santa Teresa (every operator on 'Project Miner', the builders' name for the site, and on the power plant sites), the state air permit docket, Doña Ana County's Project Jupiter compliance documents (the 2026 annual report and the site study), the state water right records and a court petition on the site's well, suppliers' own project lists, Oracle's releases and the news, and kept each firm a source ties to this job. Santa Teresa is unincorporated and commercial building permits go through the state's login-only portal, so no building permit naming a contractor was read. Oracle says 30 New Mexico firms hold $994 million in contracts but names only JB Henderson. Four firms the Border Industrial Association named as Santa Teresa recruits in data center work are left out, because no source states a contract on this job. The trade split is the math on Turner & Townsend's published data center shares, applied to the about $4.7 billion the developers report invested through June 30, 2026. Phones are each firm's own office line. First published Nov. 18, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 18, 2026- Albuquerque Journal: Doña Ana County issues new breach notice to Project Jupiter developers (Nov. 10, 2026)
- KVIA: Doña Ana County says Project Jupiter missed job report deadlines (Nov. 11, 2026)
- Albuquerque Journal: Project Jupiter air permit faces new delay (Nov. 6, 2026)
- Construction Review Online: first building tops out at Project Jupiter (Oct. 28, 2026)
- Albuquerque Journal: Building Project Jupiter and opportunity in southern NM, by Clayco's Bob Clark (Oct. 5, 2026)
- Albuquerque Journal: First look at Project Jupiter site (Oct. 16, 2026)
- Oracle: Project Jupiter awards nearly $1 billion in contracts to local businesses (Oct. 23, 2026)
- Project Jupiter 2026 Consolidated Annual Report to Doña Ana County (July 31, 2026)
- Oracle: Oracle, BorderPlex and Bloom Energy to power Project Jupiter with fuel cells (April 27, 2026)
- Searchlight New Mexico: Project Jupiter site work continues (Aug. 31, 2026)
- Los Alamos Daily Post: Land Commissioner again denies Project Jupiter pipeline request (July 15, 2026)
- NMED docket AQB 26-57(P): YGI response with the declaration of Trinity Consultants (filed Oct. 19, 2026)
- Doña Ana County: Project Jupiter Phase I Environmental Site Assessment, part 1 (Aug. 2025)
- EPA stormwater permit NMR10084L: Stack Offsite Utilities for Project Miner, Sundt (Aug. 20, 2026)
- EPA stormwater permit NMR10082D: Project Miner Intersection Improvements, Smith & Aguirre (July 20, 2026)
- EPA stormwater permit NMR10088O: Project Miner Intersection Improvements, RT Electric (Oct. 24, 2026)
- EPA stormwater permit search (Construction General Permit records for Santa Teresa, NM)