What is Vantage building in Port Washington?
Vantage Data Centers, based in Denver, is building Lighthouse on 672 acres on Port Washington's north side, with OpenAI and Oracle as the users; BizTimes reports it is part of the Stargate project. The campus is four single-story data center buildings of about 2.5 million square feet in all, the largest about 759,000 square feet, plus central utility plants full of chillers, an operations center and a warehouse.
Vantage broke ground Dec. 17, 2025. By September 2026 the campus was 20% to 25% complete with 2,800 to 3,000 workers on site each day, and a second building had topped out. Wisconsin's DNR issued the air permits for 45 diesel emergency generators on June 12, 2026. Vantage expects to turn the buildings over to Oracle and OpenAI beginning at the end of 2027, and to finish in 2028.
Who gets what?
No one has published the campus's trade split. By the math on Turner & Townsend's data center cost index, about $7.2 billion of the $15 billion is electrical work and about $5 billion is pipes, heat and air. Ozaukee Press and Weitz put the campus at $15 billion; ENR called the first phase $8 billion in late 2025.
Which firms are on the job?
Vantage has four general contractors on site: Whiting-Turner and The Weitz Company build one data center building each, and Turner and McCarthy, in a joint venture, build the other two. Michels and Veit are subcontractors, Gurtz Electric bought a building in town for its work on the job, Langan is the civil engineer, Corgan designed the campus, Ramboll advises Vantage, and American Transmission Co. builds the Decker substation on the site. The City of Port Washington's own work for the campus names three more: Vinton Construction and Kapur & Associates on the sewer and water extension, and GRAEF on the road changes. 14 firms in all are on the list below.
How do the ways into the Port Washington Stargate campus compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Port Washington Stargate campus | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Port Washington Stargate campus?
| Electrical distributors and gear reps | Gurtz Electric and the four general contractors' electrical packages on 902 megawatts of buildings. |
|---|
| Mechanical, chiller and pipe reps | The central utility plants full of chillers, and the city's sewer and water extension. |
|---|
| Site, concrete and steel suppliers | Michels and Veit on 672 acres of site work. |
|---|
What should you do next on the Port Washington Stargate campus?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the Port Washington Stargate campus.
Questions people ask about the Port Washington Stargate campus
How much is the Port Washington data center?
$15 billion, per Ozaukee Press and The Weitz Company.
Who is building the Port Washington data center?
Whiting-Turner, The Weitz Company and a Turner and McCarthy joint venture are the general contractors for Vantage Data Centers. 14 firms are named in all, listed above.
Who will use the Port Washington data center?
OpenAI and Oracle; Vantage expects to start turning buildings over to them at the end of 2027.
How we built this list
We read Ozaukee Press, BizTimes, ENR, the contractors' own pages, Wisconsin DNR's permits and OSHA's partnership agreement, and kept each firm a page names on this campus or on the city's work for it, marked as such (read Nov. 16, 2026). The City of Port Washington's document center refused our reads. The trade split is the math on Turner & Townsend's published data center shares. Phones are each firm's own office line. First published Nov. 17, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.