Who's building TeraWulf's Anthropic campus in Hawesville, Kentucky

Anthropic's $4 billion data center in Hawesville, Kentucky, already has 1,500 pilings in and its first steel going up.

By Porter Stanley. Updated .

TeraWulf is building a data center campus for Anthropic on the site of the old Century Aluminum smelter at 1627 KY 3543 in Hawesville, Hancock County, Kentucky. Anthropic is the tenant: it signed a 20-year lease for about 401 MW, worth about $19 billion to TeraWulf. TeraWulf puts the build at $4.0 billion to $4.5 billion for site work and the first data halls. Fluor is the EPC contractor, and its price is still being set. On Nov. 23, 2026, the state approved a plumbing plan review for the campus filed by Altstadt Hoffman Plumbing, as the first structural steel went up on building CB-1. 10 firms are named on the job; the list below has all 10.

$4.0-4.5BTeraWulf's build estimate
$19BAnthropic's 20-year lease
482 MWElectric service to the campus
10Firms named on the job

Get all 10 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 10 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 10 firms on the TeraWulf Hawesville data center?

We list the 10 firms named on TeraWulf's Hawesville data center for Anthropic, one row each, strongest tie first, with what each one does on the job and where its name comes from.

1Latest recordJun 11, 2026

Fluor Corporation (Fluor Enterprises, Inc.)

EPC contractor for the three data center buildings: master planning and early works since March 2026, then engineering, buying, building, testing and commissioning under a definitive contract announced Nov. 4, 2026 on TeraWulf's Justified Data Campus for Anthropic in Hawesville, Hancock County, KY

TeraWulf's Justified Data Campus (Project Raylan), 1627 KY 3543, Hawesville (Hancock County), KY

TeraWulf estimates $4.0 billion to $4.5 billion for site work and the first data halls; Fluor's own price is not public, and its guaranteed maximum price was still being set on Nov. 4, 2026

Work: EPC contractor for the three data center buildings: master planning and early works since March 2026, then engineering, buying, building, testing and commissioning under a definitive contract announced Nov. 4, 2026

Who to call: Fluor Corporation (Fluor Enterprises, Inc.)
Fluor Enterprises office line
(Greenville, SC)
(864) 281-4400

The opportunity: A state utility commission filing says: 'TeraWulf has engaged Fluor Corporation as Engineering Procurement, and Construction Management (EPCM).' TeraWulf's energy plan lists a formal kickoff meeting with Fluor as general contractor on Mar. 10, 2026. Fluor Enterprises is the operator on the state construction stormwater coverage for the Raylan Project (May 26, 2026) and the contractor contact on the state building record for Building 2. Fluor Enterprises' Greenville, SC office is the civil engineer on the stamped Building 2 plans. Irving, TX headquarters: (469) 398-7000.

2Permit on the recordNov 23, 2026

Altstadt Hoffman Plumbing

Plumbing contractor: filed the state plumbing plan review for the campus address, approved Nov. 23, 2026 on TeraWulf's Justified Data Campus for Anthropic in Hawesville, Hancock County, KY

TeraWulf's Justified Data Campus (Project Raylan), 1627 KY 3543, Hawesville (Hancock County), KY

State plumbing plan review, submitted and approved Nov. 23, 2026; no value stated

Work: Plumbing contractor: filed the state plumbing plan review for the campus address, approved Nov. 23, 2026

Who to call: Altstadt Hoffman Plumbing
Altstadt Hoffman Plumbing office line
(812) 425-9389

The opportunity: Kentucky's building department lists Altstadt Hoffman Plumbing as the submitter of a plumbing plan review at 1627 State Route 3543, the campus address on every state record. It was created, submitted and approved on Nov. 23, 2026. The record does not say which building or what part of the plumbing it covers.

3Permit on the recordAug 5, 2026

Ramboll Americas Engineering Solutions, Inc.

Project engineer and engineer of record for the data center buildings: structural, electrical, mechanical, plumbing and fire protection on TeraWulf's Justified Data Campus for Anthropic in Hawesville, Hancock County, KY

TeraWulf's Justified Data Campus (Project Raylan), 1627 KY 3543, Hawesville (Hancock County), KY

State building review for Building 1 (CB-1): 353,481 sq ft, filed Aug. 5, 2026; site, foundation and structural steel approved

Work: Project engineer and engineer of record for the data center buildings: structural, electrical, mechanical, plumbing and fire protection

Who to call: Ramboll Americas Engineering Solutions, Inc.
Ramboll office line
(Syracuse, NY)
(315) 956-6100

The opportunity: The state building record for Building 1 lists 'Ramboll Americas Engineering Solutions Inc' as Project Engineer/Engineer of Record. The stamped plans for Building 2 credit its Syracuse, NY office with structural, electrical, mechanical, plumbing and fire protection design.

What is TeraWulf building in Hawesville, Kentucky?

TeraWulf is turning the old Century Aluminum smelter on the Ohio River in Hawesville into a data center campus for Anthropic. The owner is Justified DataPower LLC, a TeraWulf company, and state records call the job Project Raylan. The site cost TeraWulf about $301.9 million in all, in cash and a stake in the venture.

The plan is three compute buildings on a site with more than 250 buildable acres. Kentucky's building review lists Building 1, called CB-1, at 353,481 sq ft. The campus has 482 MW of electric service and about 401 MW of computing for Anthropic.

How much is the TeraWulf Hawesville data center?

TeraWulf says it will spend about $4.0 billion to $4.5 billion on site work and the first data halls. In June 2026 it said $3.5 billion to $4.0 billion for about 370 MW. This is the owner's estimate, not a contract value.

Anthropic is the tenant, not the builder. Its 20-year lease is worth about $19 billion to TeraWulf, and Anthropic is expected to put about $10 billion more into servers and gear. Those two figures are rent and equipment, not construction. Google gives credit support for the debt that pays for the build.

How far along is the TeraWulf Hawesville data center?

Work started with the smelter. State stormwater coverage for the Hawesville Demolition Project began Apr. 24, 2026. By Oct. 26, crews had hauled out about 105,000 tons of waste, about 4,900 truckloads, and the teardown was about 15% done. The smokestack is due to come down in spring or summer 2027.

Building went up at the same time. By Oct. 26, 1,500 of 4,500 pilings were in and 250 craft workers were on site, with about 500 expected by year end and about 2,000 by spring 2027. The state approved the site, foundation and structural steel for Building 1 on Oct. 6 and for Building 2 on Oct. 21. In November, TeraWulf said the first structural steel was going up on CB-1.

The newest record is from Nov. 23, 2026: a state plumbing plan review at the campus, filed by Altstadt Hoffman Plumbing and approved the same day. TeraWulf plans the first building online about October 2027 and the whole campus by April 2028.

Who is building the TeraWulf Hawesville data center?

Fluor is the builder. TeraWulf held a formal kickoff with Fluor as general contractor on Mar. 10, 2026, and the two announced the definitive engineering, procurement and construction contract for three data center buildings on Nov. 4, 2026. Its guaranteed maximum price is still being set, so Fluor's price is not public.

The state building records name the design team: CI Design is the architect, Ramboll is the engineer of record for structural, electrical, mechanical, plumbing and fire protection, John P. Stopen Engineering designs the piles and foundations, Terracon wrote the soil report, and Millman Surveying did the land survey. ERM runs the environmental studies and the demolition air monitoring.

Why was the Hawesville power deal a fight?

The campus needs 482 MW of electric service. Big Rivers Electric and Kenergy signed a 15-year service agreement with TeraWulf's company on Mar. 20, 2026. At a July 27 public hearing, residents spoke against it. The Kentucky Public Service Commission approved it on Aug. 21, 2026.

The site ties into five 161-kV Big Rivers lines, and TeraWulf owes Big Rivers about $11.2 million net under a substation deal. The state also issued a water withdrawal permit for three wells, up to 2.0 million gallons a day.

How do the ways into the TeraWulf Hawesville data center compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on TeraWulf's Hawesville data centerEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell
The crews still to comeSupplies and services for a site growing from 250 craft workers to about 2,000 by spring 2027Rental, safety, site services and trade suppliersSteady orders as each building goes upWork on site runs through Fluor, the EPC contractor

Who should go after the TeraWulf Hawesville data center?

Plumbing, mechanical and electrical repsAltstadt Hoffman Plumbing's plan review at the campus, and Ramboll, the engineer of record for structural, electrical, mechanical, plumbing and fire protection on Building 1, 353,481 sq ft.
Steel, concrete and site suppliersFluor's early works, with 1,500 of 4,500 pilings in by Oct. 26, 2026 and first steel on CB-1 in November; John P. Stopen Engineering on the piles and foundations; Terracon on the soil.
Power and electrical gear suppliersBig Rivers Electric and Kenergy, who serve the campus's 482 MW over five 161-kV lines.

What should you do next on the TeraWulf Hawesville data center?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on TeraWulf's Justified Data Campus (Project Raylan) at 1627 KY 3543 in Hawesville.
  3. Watch for Fluor's guaranteed maximum price and new state plan reviews for the buildings' power, heat and air.

Questions people ask about the TeraWulf Hawesville data center

How much is the TeraWulf Hawesville data center?

TeraWulf estimates $4.0 billion to $4.5 billion for site work and the first data halls. That is the owner's estimate, not a contract value. Anthropic's servers, about $10 billion more, are on top.

Is the Anthropic data center in Kentucky a $19 billion project?

No. About $19 billion is what Anthropic's 20-year lease is worth to TeraWulf, which is rent, not construction. TeraWulf puts the build at $4.0 billion to $4.5 billion.

Is Anthropic building the Hawesville data center?

No. Anthropic is the tenant. TeraWulf owns the campus through Justified DataPower LLC, and Fluor is building it.

Who is building the TeraWulf data center in Hawesville?

Fluor is the EPC contractor for the three data center buildings. The definitive contract was announced Nov. 4, 2026. 10 firms are named on the job, listed above.

Where is the TeraWulf Hawesville data center?

It is at 1627 KY 3543 in Hawesville, Hancock County, Kentucky, on the Ohio River, on the site of the old Century Aluminum smelter.

How big is the TeraWulf Hawesville data center?

Three compute buildings on more than 250 buildable acres, with 482 MW of electric service and about 401 MW of computing. Building 1 is 353,481 sq ft in the state's review.

When will the TeraWulf Hawesville data center open?

TeraWulf plans the first building online about October 2027 and the whole campus by April 2028.

How many workers are on the Hawesville data center?

TeraWulf said 250 craft workers were on site in late October 2026, about 500 by year end and about 2,000 by spring 2027.

Who supplies power to the TeraWulf Hawesville campus?

Big Rivers Electric and Kenergy, under a 15-year, 482 MW service agreement the Kentucky Public Service Commission approved on Aug. 21, 2026.

What is the newest permit on the TeraWulf Hawesville campus?

On Nov. 23, 2026, Kentucky approved a plumbing plan review at the campus address, filed by Altstadt Hoffman Plumbing.

What happens next on the TeraWulf Hawesville data center?

Steel goes up on the first building, Fluor sets its guaranteed maximum price, and crews grow toward about 2,000 by spring 2027. We'll update this page when a new permit or firm appears.

How we built this list

We read Kentucky's public building records for 1627 State Route 3543 (Building 1, Building 2 and a plumbing plan review), with the stamped plans; the state utility commission case for the campus's power, including the electric service agreement, TeraWulf's energy plan and ERM's reports; state water and stormwater permits; TeraWulf's and Fluor's releases and TeraWulf's quarterly report; and local and trade news, read through Nov. 24, 2026. We kept each firm a public record names on this campus. Altstadt Hoffman's tie is by address: its plan review is at the campus address but does not say which building. Left out: the owner, the tenant (Anthropic), the lender-side backer (Google), the site's seller, the grid operator, the lawyers, a training college, a floodplain permit agent whose record names a person but not the firm, and firms named only in unread or unrelated records. No one has named the demolition, steel, pile or electrical subcontractors in a public record yet. Phones are each firm's own line from its own site or its own documents; Fluor's is its Greenville, SC office, Terracon's is its main line, and ERM's and Millman's are the numbers printed on their own reports and survey. First published Nov. 24, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 10 firms, free

All 10 firms on the TeraWulf Hawesville data center

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.