What is TeraWulf building in Hawesville, Kentucky?
TeraWulf is turning the old Century Aluminum smelter on the Ohio River in Hawesville into a data center campus for Anthropic. The owner is Justified DataPower LLC, a TeraWulf company, and state records call the job Project Raylan. The site cost TeraWulf about $301.9 million in all, in cash and a stake in the venture.
The plan is three compute buildings on a site with more than 250 buildable acres. Kentucky's building review lists Building 1, called CB-1, at 353,481 sq ft. The campus has 482 MW of electric service and about 401 MW of computing for Anthropic.
How much is the TeraWulf Hawesville data center?
TeraWulf says it will spend about $4.0 billion to $4.5 billion on site work and the first data halls. In June 2026 it said $3.5 billion to $4.0 billion for about 370 MW. This is the owner's estimate, not a contract value.
Anthropic is the tenant, not the builder. Its 20-year lease is worth about $19 billion to TeraWulf, and Anthropic is expected to put about $10 billion more into servers and gear. Those two figures are rent and equipment, not construction. Google gives credit support for the debt that pays for the build.
How far along is the TeraWulf Hawesville data center?
Work started with the smelter. State stormwater coverage for the Hawesville Demolition Project began Apr. 24, 2026. By Oct. 26, crews had hauled out about 105,000 tons of waste, about 4,900 truckloads, and the teardown was about 15% done. The smokestack is due to come down in spring or summer 2027.
Building went up at the same time. By Oct. 26, 1,500 of 4,500 pilings were in and 250 craft workers were on site, with about 500 expected by year end and about 2,000 by spring 2027. The state approved the site, foundation and structural steel for Building 1 on Oct. 6 and for Building 2 on Oct. 21. In November, TeraWulf said the first structural steel was going up on CB-1.
The newest record is from Nov. 23, 2026: a state plumbing plan review at the campus, filed by Altstadt Hoffman Plumbing and approved the same day. TeraWulf plans the first building online about October 2027 and the whole campus by April 2028.
Who is building the TeraWulf Hawesville data center?
Fluor is the builder. TeraWulf held a formal kickoff with Fluor as general contractor on Mar. 10, 2026, and the two announced the definitive engineering, procurement and construction contract for three data center buildings on Nov. 4, 2026. Its guaranteed maximum price is still being set, so Fluor's price is not public.
The state building records name the design team: CI Design is the architect, Ramboll is the engineer of record for structural, electrical, mechanical, plumbing and fire protection, John P. Stopen Engineering designs the piles and foundations, Terracon wrote the soil report, and Millman Surveying did the land survey. ERM runs the environmental studies and the demolition air monitoring.
Why was the Hawesville power deal a fight?
The campus needs 482 MW of electric service. Big Rivers Electric and Kenergy signed a 15-year service agreement with TeraWulf's company on Mar. 20, 2026. At a July 27 public hearing, residents spoke against it. The Kentucky Public Service Commission approved it on Aug. 21, 2026.
The site ties into five 161-kV Big Rivers lines, and TeraWulf owes Big Rivers about $11.2 million net under a substation deal. The state also issued a water withdrawal permit for three wells, up to 2.0 million gallons a day.
How do the ways into the TeraWulf Hawesville data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on TeraWulf's Hawesville data center | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The crews still to come | Supplies and services for a site growing from 250 craft workers to about 2,000 by spring 2027 | Rental, safety, site services and trade suppliers | Steady orders as each building goes up | Work on site runs through Fluor, the EPC contractor |
Who should go after the TeraWulf Hawesville data center?
| Plumbing, mechanical and electrical reps | Altstadt Hoffman Plumbing's plan review at the campus, and Ramboll, the engineer of record for structural, electrical, mechanical, plumbing and fire protection on Building 1, 353,481 sq ft. |
|---|
| Steel, concrete and site suppliers | Fluor's early works, with 1,500 of 4,500 pilings in by Oct. 26, 2026 and first steel on CB-1 in November; John P. Stopen Engineering on the piles and foundations; Terracon on the soil. |
|---|
| Power and electrical gear suppliers | Big Rivers Electric and Kenergy, who serve the campus's 482 MW over five 161-kV lines. |
|---|
What should you do next on the TeraWulf Hawesville data center?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on TeraWulf's Justified Data Campus (Project Raylan) at 1627 KY 3543 in Hawesville.
- Watch for Fluor's guaranteed maximum price and new state plan reviews for the buildings' power, heat and air.
Questions people ask about the TeraWulf Hawesville data center
How much is the TeraWulf Hawesville data center?
TeraWulf estimates $4.0 billion to $4.5 billion for site work and the first data halls. That is the owner's estimate, not a contract value. Anthropic's servers, about $10 billion more, are on top.
Is the Anthropic data center in Kentucky a $19 billion project?
No. About $19 billion is what Anthropic's 20-year lease is worth to TeraWulf, which is rent, not construction. TeraWulf puts the build at $4.0 billion to $4.5 billion.
Is Anthropic building the Hawesville data center?
No. Anthropic is the tenant. TeraWulf owns the campus through Justified DataPower LLC, and Fluor is building it.
Who is building the TeraWulf data center in Hawesville?
Fluor is the EPC contractor for the three data center buildings. The definitive contract was announced Nov. 4, 2026. 10 firms are named on the job, listed above.
Where is the TeraWulf Hawesville data center?
It is at 1627 KY 3543 in Hawesville, Hancock County, Kentucky, on the Ohio River, on the site of the old Century Aluminum smelter.
How big is the TeraWulf Hawesville data center?
Three compute buildings on more than 250 buildable acres, with 482 MW of electric service and about 401 MW of computing. Building 1 is 353,481 sq ft in the state's review.
When will the TeraWulf Hawesville data center open?
TeraWulf plans the first building online about October 2027 and the whole campus by April 2028.
How many workers are on the Hawesville data center?
TeraWulf said 250 craft workers were on site in late October 2026, about 500 by year end and about 2,000 by spring 2027.
Who supplies power to the TeraWulf Hawesville campus?
Big Rivers Electric and Kenergy, under a 15-year, 482 MW service agreement the Kentucky Public Service Commission approved on Aug. 21, 2026.
What is the newest permit on the TeraWulf Hawesville campus?
On Nov. 23, 2026, Kentucky approved a plumbing plan review at the campus address, filed by Altstadt Hoffman Plumbing.
What happens next on the TeraWulf Hawesville data center?
Steel goes up on the first building, Fluor sets its guaranteed maximum price, and crews grow toward about 2,000 by spring 2027. We'll update this page when a new permit or firm appears.
How we built this list
We read Kentucky's public building records for 1627 State Route 3543 (Building 1, Building 2 and a plumbing plan review), with the stamped plans; the state utility commission case for the campus's power, including the electric service agreement, TeraWulf's energy plan and ERM's reports; state water and stormwater permits; TeraWulf's and Fluor's releases and TeraWulf's quarterly report; and local and trade news, read through Nov. 24, 2026. We kept each firm a public record names on this campus. Altstadt Hoffman's tie is by address: its plan review is at the campus address but does not say which building. Left out: the owner, the tenant (Anthropic), the lender-side backer (Google), the site's seller, the grid operator, the lawyers, a training college, a floodplain permit agent whose record names a person but not the firm, and firms named only in unread or unrelated records. No one has named the demolition, steel, pile or electrical subcontractors in a public record yet. Phones are each firm's own line from its own site or its own documents; Fluor's is its Greenville, SC office, Terracon's is its main line, and ERM's and Millman's are the numbers printed on their own reports and survey. First published Nov. 24, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 24, 2026- TeraWulf: Kentucky PSC approves 482 MW power agreement (Aug. 24, 2026)
- TeraWulf: Google credit backstop and definitive Fluor EPC agreement (Nov. 4, 2026)
- Fluor: EPC contract with TeraWulf in Kentucky (Nov. 4, 2026)
- Kentucky Dept. of Housing, Buildings and Construction, Building 1 record (read Nov. 24, 2026)
- Kentucky Dept. of Housing, Buildings and Construction, Building 2 record (read Nov. 24, 2026)
- Kentucky Dept. of Housing, Buildings and Construction, plumbing plan review (Nov. 23, 2026)
- Kentucky PSC Case 2026-00115, Big Rivers response to the Attorney General (June 11, 2026)
- Kentucky PSC Case 2026-00115, TeraWulf energy plan (Aug. 14, 2026)
- Kentucky Division of Water, construction stormwater KYR10U650 (May 26, 2026)
- Kentucky Division of Water, construction stormwater KYR10U544 (Apr. 24, 2026)
- The Hancock Clarion: Fiscal Court updated on data center plans (Nov. 5, 2026)
- ENR: TeraWulf advances $4B data center at former Kentucky smelter (Aug. 25, 2026)
- ENR: Fluor wins EPC contract for TeraWulf data center complex (Nov. 5, 2026)
- Construction Review Online: TeraWulf Kentucky data center (Nov. 23, 2026)
- TeraWulf 10-Q, third quarter 2026