What is TerraPower building near Kemmerer, Wyoming?
TerraPower, the nuclear company Bill Gates founded, is building Natrium Kemmerer Unit 1 near Kemmerer, in Lincoln County, Wyoming, next to PacifiCorp's retiring Naughton coal plant. The reactor is cooled by sodium and makes 345 MW. Its molten-salt storage can boost the plant's output to 500 MW when needed.
The site covers 60 acres: a 30-acre Nuclear Island holds the reactor, kept apart from a 30-acre Energy Island with the salt tanks and turbine. The Sodium Test and Fill Facility and the Kemmerer Training Center are going up first. TerraPower says about 1,600 workers will be on site at peak, and about 250 will stay to run the plant.
How much does the Natrium plant cost?
The trade press puts the project at an estimated $4 billion. Up to $2 billion of that is federal cost-share from the U.S. Department of Energy, matched by TerraPower. TerraPower's own releases give no total cost.
TerraPower has announced its suppliers in rounds, most recently 12 contracts on Aug. 31, 2026. It does not publish what any contract is worth.
Why did Bechtel leave the Natrium project?
Bechtel was the engineering, procurement and construction contractor from October 2020 through the first phase. In September 2026, Bechtel and TerraPower parted ways on the full build. Bechtel stays on site to finish the Sodium Test and Fill Facility.
TerraPower reopened the contract and did not name any possible contractors or a timetable. The exit left Kemmerer's plans to house 1,600 peak workers in limbo (Oct. 13, 2026). No successor had been named as of Nov. 22, 2026.
What permits does the Natrium plant hold?
The plant has no local building permits. It runs on a state permit and a federal one. The Wyoming Industrial Siting Council approved TerraPower's permit for all the non-nuclear work on Jan. 14, 2025.
The NRC voted on March 4, 2026 to grant the construction permit, and issued Construction Permit CPAR-1 (Docket 50-613) to US SFR Owner, LLC, a TerraPower company, on March 9, 2026. Nuclear construction began April 23, 2026.
What happened at the Natrium site in October 2026?
On Oct. 14, 2026, Curtiss-Wright delivered and installed the Stage 1 Training Simulator at the site, years before the reactor runs. On Oct. 15, Bill Gates, Govs. Mark Gordon, Brad Little and Spencer Cox, and Sen. John Barrasso toured the Sodium Test and Fill Facility and the reactor pit, then about halfway to its 120-foot depth.
The visit came as TerraPower moved from groundwork toward vertical construction. Gov. Gordon said federal policy had cost the project two years, a problem now solved, and he sees no new delays. CEO Chris Levesque said a second or third reactor at Kemmerer depends on data centers moving in nearby. Construction is set to finish in 2030, with power in 2031.
Which firms are on the Natrium project?
Most named firms make the reactor's parts. HD Hyundai makes the reactor vessel, Doosan Enerbility the core barrel and guard vessel, ENSA the reactor head and Marmen the rotating plug. Premier Technology won the sodium-air heat exchanger, TerraPower's largest single award as of October 2024, and Hayward Tyler builds the sodium pumps.
On the site, Earth Work Solutions of Gillette, Wyoming had a $10 million site preparation contract for Bechtel. Sargent & Lundy designed the Kemmerer Training Center. TerraPower says other subcontractor teams are keeping work going on site, but it has not named them. 27 firms in all are on the list below.
Who TerraPower hired before
TerraPower is young, so its record is short: the builder it picked for its next Natrium plants, and an equipment maker that worked on its lab in Everett, Washington and is on this job too.
- Hyundai Engineering & Construction: builder (EPC) on Up to eight future Natrium plants (Meta deal), U.S., sites not named, 2026.
- James Fisher Technologies: equipment designer and builder on an injection casting furnace system for TerraPower's laboratory, Everett, WA, 2023. Also on this job.
These are earlier or other jobs for the same owner. They are not counted in the 27 firms on this job.
How do the ways into the Natrium project compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on TerraPower's Natrium project in Kemmerer | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The main build contract still to be awarded | A place on a team going after TerraPower's rebid construction contract | Builders, site, mechanical and electrical subcontractors | A share of an estimated $4 billion project | No winner yet, and TerraPower has named no bidders or timetable |
Who should go after the Natrium project?
| Site work, concrete and steel suppliers | Earth Work Solutions' site preparation for Bechtel, and the reactor pit headed to 120 feet as the job moves to vertical construction. |
|---|
| Pumps, valves, piping and heat exchanger suppliers | Premier Technology, Hayward Tyler, Thermal Engineering International, BWXT Canada, KROHNE and Valserve all hold heat transfer and sodium system awards. |
|---|
| Builders and big subcontractors | The main construction contract is being rebid after Bechtel's exit. The firm that wins it will hire the trades for about 1,600 workers at peak. |
|---|
What should you do next on the Natrium project?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on TerraPower's Natrium plant near Kemmerer, Wyoming.
- Watch for TerraPower to name a new lead contractor for the main build.
Questions people ask about the Natrium plant in Kemmerer
How much does the Natrium plant in Kemmerer cost?
It is an estimated $4 billion, as reported in the trade press, with up to $2 billion of federal cost-share that TerraPower matches. TerraPower has not published its own cost or any contract values.
Who is building the Natrium plant?
TerraPower, the company Bill Gates founded, owns and develops it. Bechtel was the engineering, procurement and construction contractor through the first phase and is finishing the Sodium Test and Fill Facility. The main build contract is being rebid. 27 firms are named on the job, listed above.
Why did Bechtel leave the Natrium project?
In September 2026 Bechtel and TerraPower parted ways on the full construction phase. Bechtel stays on site to finish the Sodium Test and Fill Facility, and TerraPower reopened the contract. TerraPower named no contractors or timetable for the new pick.
Who will replace Bechtel at Kemmerer?
No one has been named as of Nov. 22, 2026. Hyundai Engineering & Construction was picked in 2026 to build as many as eight future Natrium reactors, but it has not been named for Kemmerer.
How far along is the Natrium plant?
Nuclear construction began April 23, 2026. On Oct. 15, 2026, the reactor pit was about halfway to its 120-foot depth, and the project was moving from groundwork toward vertical construction. Curtiss-Wright installed the Stage 1 Training Simulator on Oct. 14, 2026.
When will the Natrium plant be finished?
Construction is targeted to finish in 2030, with commercial power in 2031. Wyoming's governor said in October 2026 that he sees no new delays.
How many workers will the Natrium plant need?
About 1,600 workers at peak, and about 250 permanent staff once it runs. Kemmerer's plans to house the peak crew went into limbo in October 2026 after the lead contractor backed out.
What permits does the Natrium plant hold?
The Wyoming Industrial Siting Council approved its state permit on Jan. 14, 2025. The NRC voted on its construction permit on March 4, 2026 and issued Construction Permit CPAR-1 (Docket 50-613) to US SFR Owner, LLC, a TerraPower company, on March 9, 2026. There are no local building permits.
Who makes the Natrium reactor's big parts?
HD Hyundai makes the reactor vessel, Doosan Enerbility the core barrel, guard vessel and internal supports, ENSA the reactor head and Marmen the rotating plug. Hayward Tyler builds the sodium pumps.
How can subcontractors get on the Natrium project?
Call the firms already on the job, starting with Bechtel and Earth Work Solutions for site work and the equipment makers for parts and service. The bigger way in is the main construction contract TerraPower is rebidding: the firm that wins it will hire the trades.
What happens next at the Natrium site?
TerraPower has to pick a new lead contractor for the main build, and Bechtel is finishing the Sodium Test and Fill Facility. We'll update this page when a new contract or firm appears.
How we built this list
We read TerraPower's own releases on the start of construction, the state permit, the training center and every supplier round from August 2023 to August 2026; Bechtel's and Curtiss-Wright's releases; Zachry Group's release; the Federal Register notice of the NRC construction permit; and trade and local news, all on Nov. 22, 2026. We kept each firm a public record names on this project. Left out: TerraPower and its permit company (the owner), the U.S. Department of Energy (the funder), PacifiCorp (the utility partner), Hyundai Engineering & Construction (picked for future Natrium plants, not this one), fuel suppliers off site, workforce housing builders in town, and a crane firm seen only in a photo. There are no local building permits for the plant, and TerraPower publishes no contract values. Phones are each firm's own line from its own site, mostly headquarters lines; GE Vernova Hitachi, Mirion, James Fisher Technologies, HD Hyundai, Doosan, ENSA, Teledyne Brown, Thermal Engineering International, Jensen Hughes, KROHNE, Valserve and Framatome show no main line we could read. First published Nov. 22, 2026. We'll update this page when a new contract, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 22, 2026- ENR: TerraPower reopens EPC competition for $4B Natrium nuclear project (Sept. 23, 2026)
- WyoFile: Lead contractor pulls out of Gates' Natrium nuclear power plant project (Sept. 21, 2026)
- ANS Nuclear Newswire: TerraPower, Bechtel part ways on Natrium project (Sept. 21, 2026)
- Cowboy State Daily: Kemmerer plans for 1,600 nuclear plant workers in limbo (Oct. 13, 2026)
- Cowboy State Daily: Bill Gates tours Kemmerer's Natrium nuclear facility (Oct. 16, 2026)
- Curtiss-Wright: Stage 1 simulator installed at TerraPower's Natrium site (Oct. 14, 2026)
- TerraPower: construction begins on Natrium Kemmerer Unit 1 (April 23, 2026)
- Bechtel: Bechtel and TerraPower begin construction at Natrium Kemmerer Unit 1 (April 23, 2026)
- Federal Register: Construction Permit CPAR-1, US SFR Owner, LLC (March 16, 2026)
- TerraPower: Wyoming Industrial Siting Council permit (Jan. 2025)
- TerraPower: Kemmerer Training Center construction begins
- POWER magazine: Kemmerer 1 enters construction, timeline (April 2026)
- TerraPower: next round of vendor contracts for Kemmerer Unit 1 (Aug. 31, 2026)
- TerraPower: another round of vendor contracts (Feb. 13, 2025)
- TerraPower: awards for Natrium (Dec. 18, 2024)
- TerraPower: Natrium equipment contract to Premier Technology (Oct. 3, 2024)
- TerraPower: second round of contracts for Natrium vendors (Feb. 7, 2024)
- TerraPower: contract awards for Natrium vendors (Aug. 1, 2023)
- World Nuclear News: TerraPower awards Natrium supplier contracts (July 10, 2025)
- ANS Nuclear Newswire: TerraPower awards subcontract for Natrium project (July 15, 2025)
- Zachry Group: NAS awarded BOA for TerraPower's advanced nuclear project (Sept. 18, 2024)
- Cowboy State Daily: Earth Work Solutions to begin work on $10M nuclear reactor project (May 1, 2024)
- Earth Work Solutions: project list (read Nov. 22, 2026)