$12.9B OF TEXAS JOBS AREN'T DATA CENTERS

We counted Texas's next 1,989 jobs, and 17 are data centers

By Porter Stanley. Updated .

No. Of 1,989 construction jobs registered with the Texas Department of Licensing and Regulation to start between Nov. 15, 2026 and March 31, 2027, 17 are data center jobs, under 1% of the jobs. They carry $8.1 billion of the $21.0 billion in registered estimated cost, or 39% of the dollars, and 2 buildings in Kent County hold $4.8 billion of that. The other 1,972 jobs are worth $12.9 billion. One you can bid now: Vaughn Construction is taking trade bids on MD Anderson's Proton Therapy Center equipment replacement in Houston until 2 p.m. Central on Dec. 2, 2026.

1,989Texas jobs starting by March
17Are data center jobs
39%Of the dollars
Dec. 2MD Anderson proton bids due

Get all 32 jobs and who to call

Each one with who's on the record and the date. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 32 jobs and who to call

Each one with who's on the record and the date. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

What are the opportunities in Texas right now?

We list 32: 15 are public bids with a stated due date (MD Anderson's proton package and 14 state, county, city and university solicitations from Nov. 19 to Dec. 11, 2026), and 17 are jobs registered with the state to start by March 31, 2027 with no bid date found. We left the 17 data center jobs off the list.

1Public bidDec 2, 2026

Vaughn Construction, which posts the package in its public plan room and points bidders to its construction manager front ends; owner MD Anderson Cancer Center

Bid Package 4 on MD Anderson's proton center equipment swap in Houston: radiation protection, HVAC, electrical and 27 other trade packages

Proton Therapy Center 1, 1840 Old Spanish Trail, Houston, just south of the Texas Medical Center. Bids due Dec. 2, 2026 at 2:00 PM Central

No package value is public; 30 trade packages, 286 bid files

Work: Radiation protection, HVAC, plumbing, electrical, fire protection, low voltage, interiors and envelope (30 packages)

Who to call: Vaughn Construction, which posts the package in its public plan room and points bidders to its construction manager front ends; owner MD Anderson Cancer Center
Vaughn Construction public plan room (app.buildingconnected.com, "MD Anderson PTC1 - Clinical Equipment Replacement - Bid Package 4"); Vaughn Construction Houston office
(713) 243-8300

The opportunity: Vaughn Construction's public plan room lists "MD Anderson PTC1 - Clinical Equipment Replacement - Bid Package 4" with "Bids Due 12/2/2026 at 2:00 PM CST" on every one of its 30 packages. The listing says the center "was built in 2004 and became operational in 2006", that its proton equipment "has reached the end of it's useful life", and that the work covers decommissioning the Hitachi equipment, preparing for and installing the new IBA equipment, a bariatric chamber renovation and MEP upgrades. IBA announced on Jan. 19, 2026 that it will re-equip the center with three Proteus ONE systems. Packages run from 01.74 Final Clean to 28.01 Security, and include 13.01 Radiation Protection, 10.06 Access Flooring, 23.01 HVAC, 26.01 Electrical and 27.03 Nurse Call. Pre-bid questionnaires, a cost proposal, a technical proposal and a HUB response go in with the bid, per the listing.

2Public bidNov 19, 2026

Texas A&M University System

Construction manager at risk proposals for Texas A&M's Virtual Production Institute in Fort Worth

Fort Worth, Tarrant County. Responses due Nov. 19, 2026 at 2:00 PM

Work: Construction management (CMAR) and preconstruction

Who to call: Texas A&M University System
Texas ESBD solicitation TAMUS-CMAR-RFP-02-3498 (txsmartbuy.gov/esbd/TAMUS-CMAR-RFP-02-3498)

The opportunity: The state's Electronic State Business Daily lists "CMAR RFP - Virtual Production Institute Fort Worth - Fort Worth, Texas" from the Texas A&M University System, posted Oct. 22, 2026, with responses due Nov. 19, 2026 at 2:00 PM. It is the builder pick, so trades and suppliers come after the award: watch for the winner.

3Public bidNov 20, 2026

Texas State University

HVAC renovation of the Mitte building at Texas State University, CSP 754

San Marcos. Responses due Nov. 20, 2026 at 3:00 PM

Work: HVAC

Who to call: Texas State University
Texas ESBD solicitation CSP754MitteHVACRenovation-2026 (txsmartbuy.gov/esbd/CSP754MitteHVACRenovation-2026)

The opportunity: The ESBD lists "CSP # 754 Mitte HVAC Renovation - 2026" from Texas State University, posted Oct. 22, 2026, due Nov. 20, 2026 at 3:00 PM, under the HVAC class codes. It is a competitive sealed proposal, so mechanical contractors can propose directly.

How many Texas jobs starting before April are data centers?

The state registers construction projects for accessibility review before they are built, and each registration gives an estimated cost and start date. We read every one in ATI's copy of that registry with a start between Nov. 15, 2026 and March 31, 2027: 1,993 registrations, $22.65 billion.

Four values do not fit their own scope, so we took them out: a city lane widening at $999 million, a subdivision's sidewalks and landscaping at $121.9 million, an amenity center at $529.9 million with no scope on file, and a 2,400-square-foot bank branch at $32.5 million. That leaves 1,989 jobs and $20.97 billion.

17 of the 1,989 are data center jobs. That is under 1% of the jobs and 39% of the dollars: $8.1 billion. Two buildings in Kent County, filed as Project Hyper Spur Buildings 1 and 2, are $2.4 billion each, so 1 rural county holds $4.8 billion of the data center total. Take those two out and the other 15 data center jobs are $3.3 billion.

Which 17 Texas jobs are the data centers?

These are the 17, with the names, places and estimated costs on their state registrations. We read each scope; Project Longhorn's reads "Type II-B Construction Data Center (S-1)", and the three DAL130 lines are one data center campus in Westlake.

  • Project Hyper - Spur Building 2: Jayton, Kent County, $2,400,000,000.
  • Project Hyper - Spur Building 1: Jayton, Kent County, $2,400,000,000.
  • Skybox Hutto 4 - Core/Shell: Hutto, Williamson County, $550,000,000.
  • New construction ground up two story building, office and data center (SI DFW02CAMPUS LLC): Lancaster, Dallas County, $540,000,000.
  • Colovore Alliance: Fort Worth, Denton County, $430,000,000.
  • DataBank Red Oak - DFW15 Base Building: Red Oak, Ellis County, $425,000,000.
  • Project Longhorn - Building One: Cedar Creek, Bastrop County, $366,000,000.
  • DataBank Red Oak - DFW14 Base Building: Red Oak, Ellis County, $325,000,000.
  • Colovore Hutto: Hutto, Williamson County, $280,000,000.
  • CoreSite DA1: Irving, Dallas County, $200,000,000.
  • DAL130 - Data Center: Westlake, Tarrant County, $83,000,000.
  • DAL130 - Auxiliary Water Building: Westlake, Tarrant County, $45,000,000.
  • Project Gold Phase 2 - DFW39 (Digital Realty): Garland, Dallas County, $20,000,000.
  • Project Gold Phase 2 DFW44 (Digital Realty): Lewisville, Denton County, $20,000,000.
  • DAL130 - Access Control Building: Westlake, Tarrant County, $15,000,000.
  • DFW Data Center Interior Fit-Out 2 (Edged Dallas LLC): Irving, Dallas County, $3,000,000.
  • Equinix data hall renovation: Houston, Harris County, $1,000,000.

We also opened the biggest code names that did not match. Project Jay ($500 million, Fort Worth) says "infrastructure to support 3 manufacturing lines", Project Eagle (Plano) is offices, garages and a central plant, and Project Theo (Cibolo) is a Walmart distribution center. None of them is counted as a data center.

Where is the rest of Texas's construction money going?

The 1,972 jobs that are not data centers are worth $12.9 billion. They include hospital towers in Fort Worth, Katy and Richardson, new high schools and a career center, airport and museum work in Dallas-Fort Worth, an I-35 rebuild in Austin, and plants and distribution centers around San Antonio and Austin.

By metro, Dallas-Fort Worth has 724 jobs and $7.98 billion, 11 of them data center jobs worth $2.11 billion. The Houston area has 618 jobs and $2.58 billion with 1 data center job, a $1 million data hall. The Austin area has 166 jobs and $2.73 billion with 3 data center jobs. The San Antonio area has 174 jobs and $1.25 billion and none.

We counted metros by county: Dallas-Fort Worth is Dallas, Tarrant, Collin, Denton, Ellis, Johnson, Kaufman, Parker, Rockwall, Wise, Hunt, Hood and Somervell; Houston is Harris, Fort Bend, Montgomery, Brazoria, Galveston, Liberty, Waller, Chambers and Austin counties; Austin is Travis, Williamson, Hays, Bastrop and Caldwell; San Antonio is Bexar, Comal, Guadalupe, Medina, Wilson, Atascosa, Bandera and Kendall.

What is MD Anderson bidding on Dec. 2?

MD Anderson's Proton Therapy Center 1 sits at 1840 Old Spanish Trail, just south of the Texas Medical Center. Vaughn Construction's listing says it "was built in 2004 and became operational in 2006" and that its proton equipment has reached the end of its useful life.

Bid Package 4 covers taking out the Hitachi equipment, preparing for and installing the new IBA equipment, a bariatric chamber renovation and MEP upgrades. IBA announced on Jan. 19, 2026 that it will re-equip the center with three Proteus ONE systems.

Bids are due Dec. 2, 2026 at 2:00 PM Central on all 30 packages. The listing has 286 bid files and asks for pre-bid questionnaires, a cost proposal, a technical proposal and a HUB response with each bid.

  • Site and structure: 01.74 Final Clean, 3.10 Structural Precast, 4.01 Masonry, 5.50 Ornamental Metals.
  • Envelope: 07.01 Waterproofing, Dampproofing and Joint Sealants, 07.03 Roofing, 07.06 Composite Panels, 07.10 Fire Caulking, 08.28 Glass and Glazing, 11.52 Window Washing Equipment.
  • Interiors: 06.02 Architectural Woodwork, 08.00 Doors, Frames and Hardware, 09.01 Plaster, 09.02 Drywall, 09.05 Acoustical Ceilings and Wall Panels, 09.07 Carpet, Vinyl Flooring and Base, 09.10 Epoxy Flooring, 09.12 Painting, 10.00 Specialties, 10.06 Access Flooring, 10.08 Signage.
  • Special: 13.01 Radiation Protection.
  • MEP and low voltage: 21.01 Fire Protection, 22.01 Plumbing, 23.01 HVAC, 26.01 Electrical, 27.01 Data and Telecommunications, 27.02 Audio Visual, 27.03 Nurse Call, 28.01 Security.

The news covered IBA's new machines in January. We found no story that names the trade packages or the Dec. 2 date.

How do the ways into Texas's next jobs compare?

Way inWhat it isBest forWhat you getThe limit
MD Anderson's proton packageA trade bid to Vaughn Construction on Bid Package 4, before 2 p.m. Central on Dec. 2, 2026Radiation protection, HVAC, electrical, plumbing, fire protection, low voltage, interiors and envelope subsA priced line in one of 30 packagesPre-bid questionnaires, a technical proposal and a HUB response go in with the bid
The state and city bid boardsDirect bids on the 14 dated Texas solicitations on this list, from Nov. 19 to Dec. 11, 2026Prime contractors, mechanical, elevator, civil and building firmsA contract with the agencyEach portal has its own registration and some have mandatory meetings
The registered jobs before a builder is namedA call to the owner or its architect on a job registered with the state to start by March 31, 2027Builders, design-assist trades and manufacturers' reps who sell to the specAn early seat before the trade packages go outMost registrations name no builder or architect yet, and costs are the registrant's estimates
The data center jobsSelling into the 17 data center registrations through their buildersElectrical, mechanical, controls and site firms with data center referencesLarge scopes on a few jobs17 jobs in 1,989, and $4.8 billion of their $8.1 billion sits in 1 rural county

Who should use this Texas list, and who shouldn't?

Radiation protection and shielding firms in HoustonVaughn lists 13.01 Radiation Protection among 30 packages due Dec. 2, 2026.
HVAC, plumbing, electrical and fire protection subsThe proton package has its own line for each, and the hospital towers on the list start between Dec. 2026 and Feb. 2027.
Reps who sell to schools, hospitals and officesThose jobs are most of the 1,972 that are not data centers, and the registrations name the owner to call.
Firms that only want data center workThis isn't the list for you: 17 of 1,989 jobs, and the biggest 2 are in Kent County.

What should you do next on these Texas jobs?

  1. Open Vaughn Construction's public plan room, find MD Anderson PTC1 Bid Package 4 and join your trade's package before 2 p.m. Central on Dec. 2, 2026.
  2. Check the 14 dated public bids on the list, starting with Nov. 19, and note any mandatory meeting, like the University of Houston's on Nov. 16.
  3. Call the owners of the registered hospital, school and campus jobs that start in your area before March 31, 2027.
  4. Open the full list for every job, date and owner.

Questions people ask about Texas data centers and construction

Is Texas all data centers now?

No. 17 of the 1,989 construction jobs registered with the state to start between Nov. 15, 2026 and March 31, 2027 are data center jobs. They do carry 39% of the registered dollars, $8.1 billion of $21.0 billion.

How many data centers start construction in Texas before April 2027?

17 data center jobs are registered with the Texas Department of Licensing and Regulation to start between Nov. 15, 2026 and March 31, 2027: 15 data center buildings and 2 support buildings on the DAL130 campus in Westlake.

How much are those Texas data center jobs worth?

$8,103,000,000 in registered estimated cost. Two Project Hyper buildings in Kent County are $2.4 billion each, so they hold $4.8 billion of it.

Where are the new Texas data centers being built?

Jayton (Kent County), Hutto, Lancaster, Fort Worth, Red Oak, Cedar Creek, Irving, Westlake, Garland, Lewisville and Houston, by the registrations. Dallas-Fort Worth holds 11 of the 17.

What are the biggest Texas jobs that are not data centers?

By registered cost: the Project Eagle office campus in Plano (11 registrations, $1.05 billion), the Cook Children's West Tower finish-out in Fort Worth ($651.9 million), Project Jay's manufacturing upgrade at Alliance in Fort Worth ($500 million), the I-35 rebuild in central Austin ($407.8 million) and Walmart's distribution center in Cibolo ($400 million).

Who is building MD Anderson's proton therapy equipment replacement?

Vaughn Construction posts Bid Package 4 in its public plan room and points bidders to its construction manager front ends. IBA supplies the three new Proteus ONE systems, per IBA's Jan. 19, 2026 release.

When are bids due on MD Anderson's proton therapy center?

Vaughn's listing shows bids due Dec. 2, 2026 at 2:00 PM Central on every one of the 30 packages in Bid Package 4.

What trades are in the MD Anderson proton bid package?

30 packages, from final clean, structural precast, masonry and roofing to drywall, epoxy flooring, access flooring, radiation protection, fire protection, plumbing, HVAC, electrical, data, audio visual, nurse call and security.

How does a subcontractor get on the proton package?

Join the package for your trade in Vaughn Construction's public plan room. The listing says pre-bid questionnaires, a cost proposal, a technical proposal and a HUB response go in with the bid.

What is TDLR TABS?

The Texas Department of Licensing and Regulation's Architectural Barriers registry, where owners register construction projects for accessibility review. Each registration gives the owner, address, scope, estimated cost and estimated start and end dates.

Are the registered costs real?

They are the registrant's estimates. We dropped 4 that did not fit their scope, like a $999 million lane widening, and the totals above are after that.

What happens next?

The proton package closes Dec. 2, 2026. The registered jobs start on their estimated dates through March 31, 2027, and builders put out trade packages as they go. We'll recount as new jobs are registered.

How we built this list

We read every construction job in ATI's copy of the Texas Department of Licensing and Regulation's TABS registry with an estimated start from Nov. 15, 2026 to March 31, 2027 and a record dated July 1, 2026 or later: 1,993 registrations, read through Nov. 9, 2026. We dropped 4 whose stated cost does not fit their scope: a lane widening at $999,000,000, a subdivision landscape line at $121,878,499, an amenity center with no scope at $529,918,059 and a 2,400-square-foot bank branch at $32,500,000. That leaves 1,989 jobs and $20,966,790,537. We matched data center, data hall and the operators' names in each job's name, owner and scope, then read all 15 matches one by one; all 15 are data centers. We added the 2 support buildings on the DAL130 data center campus, and we opened Project Jay, a $500 million code name, which says manufacturing. Costs are the registrant's estimates, and a campus filed as several buildings counts as several jobs. Jobs that start before Nov. 15 are outside the count, including 3 Project Hyper buildings in Childress County at $2.4 billion each. For the list we added MD Anderson's proton package from Vaughn Construction's public plan room and 14 dated solicitations from the state's Electronic State Business Daily and Harris County's bid portal. We left every person's name, phone and email off. First published Nov. 10, 2026. We'll recount when the registry adds jobs, and update the proton package if Vaughn moves the date.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 32 jobs, free

All 32 Texas opportunities, with dates

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.