What is the museum space in the new Titans stadium?
On Aug. 11, 2026, the city issued a $905,794 building permit to finish out shell space within the new stadium for a Tennessee Titans history and museum. It names no builder.
On Oct. 14, 2026, the city issued the electrical permit for the same space to Maryland Electric Company, with a $1.5 million contract value. The permit gives the project name as "Halll of fame", in the city's spelling. The 2 values are separate filings, and we don't add them.
We found no announcement of a museum or hall of fame in the new stadium, in the Titans' construction updates or in the press. Maryland Electric is a Kingston Springs, Tennessee firm, and it's already on the job: it holds TBA's temporary site power package and the power and low voltage permit for the stadium's LED displays.
What's being bought at the new Titans stadium, and when?
The Titans' Nov. 5, 2026 update says the roof was enclosed in October. Crews are hanging loudspeakers and lightning protection, finishing ribbon boards, and putting in tile, paint, wall coverings, glass handrails and custom woodwork, and the HVAC system is being tested.
Seats were over 40% installed by Nov. 5, retractable seating is under way in the east end zone, and the playing surface goes in early 2027. Structural demolition of the old stadium is planned for early 2027 too.
- TBA packages. TBA's published list names 55 awarded packages held by 51 firms, from concrete and steel to tile, millwork and final clean.
- Team purchases. The Titans list direct awards to firms including Daktronics, Irwin Seating, Verizon and AmpThink.
- Not yet named. We found no firm on any record for the museum's exhibits, the playing surface or the lightning protection.
We found no current bid date. TBA's packages are listed as awarded, and the Titans' posted requests are closed.
How do the ways into the new Titans stadium compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| TBA's interest form | A form on the stadium construction site, plus [email protected] | Subcontractors, vendors, suppliers and professional services | Your interest on file with the construction manager | Most packages are already awarded |
| Turner's prequalification | The system TBA uses for tier-1 subs | Firms that want a direct TBA package | Eligibility for TBA work | Second-tier subs and suppliers don't need it, and it isn't a bid |
| The Titans' direct purchasing | CAA ICON runs the Titans' own requests at [email protected] | Seating, furniture, technology and food service vendors | A route to what the team buys itself | The posted requests are closed |
| Selling to a firm on the list | A call to a firm named on TBA's list or a city permit, like Maryland Electric | Suppliers and lower-tier subs | A conversation with a firm already on the job | The list and permits don't show what's bought |
| The old stadium's demolition | Renascent Demolition's subcontract work for the Titans | Trucking, fencing, security and salvage firms | Work after the new stadium opens | Its bid date was May 16, 2026 and has passed |
Who should go after the Titans stadium job, and who shouldn't?
| Lighting and electrical suppliers | Maryland Electric holds the museum's $1.5 million electrical permit, issued Oct. 14, 2026. |
|---|
| Exhibit, display and AV firms | The museum's builder and exhibit firm aren't named on any record we read. |
|---|
| Finish and closeout trades | Tile, paint, millwork, final clean and furniture work run through closeout. |
|---|
| Firms that need a public bid date | This isn't the job for you, because we found no current one, and most packages are bought. |
|---|
What should you do next on the Titans stadium job?
- Call Maryland Electric if you sell exhibit lighting, wire or gear.
- Fill out TBA's interest form and email [email protected].
- Email the Titans' purchasing team if you sell furniture, seating or technology.
- Open the full list and call the firm named for your trade.
Questions people ask about the new Titans stadium
Who is building the new Titans stadium?
Tennessee Builders Alliance, a joint venture of Turner Construction, AECOM Hunt, Polk & Associates and I.C.F. Builders, is the construction manager at risk. The Titans picked it in August 2023.
Who owns the new Nissan Stadium?
The Metro Nashville Sports Authority, which the Titans call the owner and landlord of both the current and new stadiums. The Titans have a 30-year lease.
How much does the new Titans stadium cost?
$2.1 billion: $840 million from the Titans, $500 million from the State of Tennessee and $760 million in Sports Authority revenue bonds, according to the Titans' 2023 release.
When does the new Nissan Stadium open?
The Titans said in March 2026 they expected keys to the building in February 2027, and the team plays there from the 2027 season. Their Oct. 6, 2026 update counted 4 months to substantial completion.
Is there a Titans museum or hall of fame in the new stadium?
City permits describe one. A building permit issued Aug. 11, 2026 and an electrical permit issued Oct. 14, 2026 both cover finishing out shell space for a Tennessee Titans history and museum, and the electrical permit gives the project name as "Halll of fame". We found no announcement.
Who is doing the museum's electrical work?
The city issued the $1.5 million electrical permit to Maryland Electric Company, a Kingston Springs, Tennessee firm, on Oct. 14, 2026. The same firm holds the power and low voltage permit for the stadium's LED displays.
How do subcontractors and suppliers get on the job?
Through TBA's interest form and [email protected]. Tier-1 subs prequalify through Turner, and second-tier subs and suppliers don't have to. The Titans' own purchases go through [email protected].
Can I still bid on the Titans stadium?
We found no current bid date. TBA's packages are listed as awarded, the Titans' requests are closed, and the old stadium's demolition bids were due May 16, 2026.
Who is the electrical contractor on the stadium?
TBA's list names Gephart Electric on the electrical and electric gear packages. Maryland Electric holds temporary site power, the LED display power and the museum's electrical permit.
What's still being bought at the stadium?
Finishes, seats, the roof-hung systems and HVAC testing were under way on Nov. 5, 2026. The playing surface goes in early 2027, and the museum's fit-out is permitted. The museum's builder and exhibit firm aren't named on any record we read.
What are the risks of chasing this job?
The stadium is about 3 months from substantial completion, so most packages are bought. The permits state no fixture list, and we found no current bid date.
What happens to the old Nissan Stadium?
Renascent Demolition is the Titans' demolition contractor, and structural demolition is planned for early 2027. Its subcontractor bids were due May 16, 2026.
How we built this list
We read the city's building and trade permits on the stadium parcel, TBA's published list of awarded packages, the Titans' direct awards page, the team's construction updates and releases, and press coverage. A row is on the list only if a record ties it to the stadium, its site or the old stadium's demolition. We don't add permit values together, and the $1.5 million figure is the electrical permit's, not the museum's cost. A row with a passed bid date says so, and none is marked open. First published Nov. 7, 2026. We'll update this page when a new permit, firm or bid date appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 7, 2026- Nashville trade permits, stadium parcel
- Nashville building permits, stadium parcel
- Tennessee Titans, April 26, 2023
- Tennessee Titans, Aug. 17, 2023
- Tennessee Builders Alliance, contracting opportunities
- Tennessee Builders Alliance, awarded packages
- Tennessee Titans, direct opportunities
- New Nissan Stadium, Nov. 5, 2026 update
- New Nissan Stadium, Oct. 6, 2026 update
- HOCHTIEF, Nov. 20, 2025
- ENR, June 2, 2025
- Dixie Contractor, July 2026
- Fox Sports, March 24, 2026
- Renascent, Nissan Stadium demolition
- Maryland Electric