What shade work is in the Trevino Metro Park bid?
The city's playground and furnishing plan, dated Oct. 2, 2026, marks 3 proposed shade locations. The detail sheet draws a four-post and a two-post shade canopy, and the drawings name one canopy vendor, Renfrow & Co, with the words "or equal" right under it.
The decorative metal panel spec covers the panels in the canopy: laser-cut aluminum, 1/4 inch thick, in a pattern called "bb Leaves", with a powder coat finish. That spec, not the drawings, names Parasoleil as an approved panel maker, and lets others in with samples, 3 past projects and proof they can cut the design. Whether the shelter spec's pre-approval rule reaches the canopies isn't stated, so ask through the solicitation.
The two picnic pavilions are a separate item. The shelter spec says they "shall be equal to Northwest Series shelters manufactured by CRS Inc." and asks makers it doesn't name for written pre-approval at least 10 days before bid opening.
Who showed up to the Trevino Metro Park pre-bid?
The city's attendance list from the Oct. 28, 2026 pre-bid names 12 firms that signed in as primes and 3 as subs, along with the design firm, an insurance broker and city staff. The pre-bid wasn't mandatory, so the list shows interest, not bids.
Most of the 12 are civil and sitework contractors that already work for the city. ATI holds City of Austin council contracts this year for 4 of them, from a $1.3 million roundabout in October to a flood project of up to $30.9 million in August, and a $16.5 million park build in Harris County for another.
We found no news story naming the bid or any of these firms in searches of KVUE, the Austin American-Statesman, Community Impact, the Austin Monitor and other Austin outlets. The press covered the park's planning from 2019 to 2023.
What else is in the Trevino Metro Park bid?
The plans name KOMPAN for 9 play pieces across two play areas, with the maker installing the equipment and its safety surface. They name Infiltrator for 3 precast tanks of 4,500 to 6,000 gallons in the onsite septic system, and Texas Metal Tanks for a galvanized rainwater cistern, each "or approved equal".
The restroom pavilion is 3,270 square feet, with split-face limestone, a standing-seam metal roof, perforated metal screens and Elkay and Sloan fixtures. Lithonia LED poles light the site, and Hunter or equal irrigation waters the new planting.
Site work covers the entry, access road, parking lot, sidewalks, trail connections, a new 8-inch water line for 2 fire hydrants, rain gardens, trees and a wildflower meadow.
How do the ways into Trevino Metro Park compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| Quote the general contractors | A price to the firms bidding the park, before 2 PM on Nov. 19 | Shade, playground, tank, concrete and landscape suppliers and subs | A line in the winning bid | The attendance list shows interest, not bids |
| Bid it yourself as the prime | An eResponse bid on Austin Finance Online with a 5% bid guaranty | General and civil contractors | The whole $6.5 million estimate | Bonds, ROCIP insurance, MBE/WBE compliance plan due with the bid |
| Offer an equal product | Your product as an equal to the one the plans name | Makers of canopies, tanks, irrigation, roofing and fixtures | A chance to replace the named brand | The engineer of record decides; the shelter spec wants pre-approval before bid opening |
| The MBE/WBE goals | Certified firms the primes must reach out to | Certified minority- and women-owned subs and suppliers | A share of the 6.11% in goals | Only for firms certified with the city |
| After the award | Selling to the winner once the city signs | Suppliers who miss bid day | Purchases over 300 days of work | Prices are mostly set in the winning bid |
Who should go after Trevino Metro Park, and who shouldn't?
| Shade canopy and shade structure makers and dealers | 3 canopies are on the plans with one vendor named "or equal", and the bidders need prices by Nov. 19. |
|---|
| Civil, sitework and concrete contractors in Central Texas | The access road, parking, sidewalks, utilities and septic system are most of the site work. |
|---|
| Precast tank, irrigation, lighting and plumbing suppliers | Each has named products in the specs that the bidders must price. |
|---|
| Playground equipment reps who don't carry KOMPAN | This isn't the job for you: the plans name KOMPAN and have the maker install. |
|---|
What should you do next on Trevino Metro Park?
- Get the plans and specs from the city's solicitation page, IFB 6100 CLMC1141, and find your section.
- Send your price to the general contractors on the attendance list before 2 PM on Nov. 19, 2026.
- If you're offering an equal, send the cut sheets and samples the spec asks for, and ask the city's procurement contact about the pre-approval rule.
- Watch for the bid tab about an hour after bids close, then call the low bidder.
Questions people ask about John Trevino Jr. Metro Park
Who is building John Trevino Jr. Metro Park?
No one yet. The City of Austin is taking bids until 2 PM on Nov. 19, 2026, and opens them at 3 PM. Twelve general contractors signed in as primes at the city's Oct. 28 pre-bid, but the meeting wasn't mandatory, so that list doesn't show who will bid.
When are bids due for John Trevino Jr. Metro Park Phase I?
Before 2 PM Austin time on Nov. 19, 2026, through Austin Finance Online, solicitation IFB 6100 CLMC1141. The city says it posts the bid tab about an hour after the solicitation closes.
How much will John Trevino Jr. Metro Park Phase I cost?
The city's estimate for the solicitation is $6.5 million. The real figure is the winning bid, and the city funds Phase I from the voter-approved 2018 parks bond.
What's being built in Phase I?
About 10.61 acres of the 330-acre site: a 3,270 square-foot restroom pavilion, a 300 and a 600 square-foot picnic pavilion, 3 shade canopies, two play areas, an entry, access road and parking, trails and sidewalks, rain gardens, trees, a wildflower meadow, a rainwater cistern and an onsite septic system.
Who designed John Trevino Jr. Metro Park Phase I?
MWM Design Group, Inc. of Austin is named on the plans as both the civil engineer and the landscape architect. Gustafson Guthrie Nichol was hired in 2019 to help write the park's master plan.
What shade structures are in the park?
The plans mark 3 shade canopy locations, drawn as four-post and two-post canopies with laser-cut aluminum panels, and the drawings name one canopy vendor, Renfrow & Co, "or equal". The panel spec separately names Parasoleil for the laser-cut panels. The picnic pavilions are separate pre-engineered steel shelters, specified as equal to CRS Inc.'s Northwest Series.
What playground equipment is in the park?
The playground plan lists 9 KOMPAN pieces across a play area for ages 2 to 5 and one for ages 5 to 12, and says the manufacturer will install the play structures, signage, safety surface and drainage.
How can a subcontractor or supplier get on this job?
Price the general contractors before Nov. 19. Bidders must also make good-faith efforts to reach certified minority- and women-owned firms at least 7 business days before bid opening, and every sub must register as a City of Austin vendor before a contract is signed.
When does construction start at John Trevino Jr. Metro Park?
The city's project page projects construction to start in spring 2027. The contract gives the builder 300 calendar days after notice to proceed to reach substantial completion.
Where is John Trevino Jr. Metro Park?
At 9501 FM 969 Rd in East Austin, Travis County, on former ranch land between FM 969 and the Colorado River. The city bought it in 2003.
What are the risks of chasing this job?
It's a small public job with a 5% bid bond, liquidated damages of $950 a day, a rolling owner-controlled insurance program and a Sustainable SITES documentation duty. Named products set the standard, so an equal needs the engineer's approval.
How we built this list
We read the city's solicitation page, all 1,353 pages of the project manual, the 135-sheet plan set, the Oct. 28 pre-bid attendance list and the parks department's project page, and searched the press. ATI's own records gave each firm's recent public contracts. A row is on the list only if a city document ties it to this bid and a seller has a real way in, so the KOMPAN playground, which the plans have the maker supply and install, is described here but not listed. The attendance list shows who came, not who will bid, so no firm is called a bidder. First published Nov. 8, 2026. We'll update this page when the city posts an addendum, the bid tab or the award.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 8, 2026- City of Austin, solicitation IFB 6100 CLMC1141
- City of Austin, pre-bid attendance list, Oct. 28, 2026
- City of Austin, project manual and specifications, Volume 1
- City of Austin, plans and drawings, bid set, Oct. 2, 2026
- Austin Parks and Recreation, Phase 1 project page
- Austin Monitor, Jan. 28, 2019