Where does TSMC's $265 billion go?
Most of a chip plant's money goes to the chip-making tools inside it. Construction Physics puts it plainly: roughly 70 to 80 percent of a new fab's cost is the process tools. At 75 percent, that is about $200 billion of TSMC's $265 billion.
The rest builds the buildings. Of a fab's construction cost, close to two-thirds is its systems: the power, air, ultrapure water, exhaust and gas lines. On TSMC's plan that is about $44 billion for the systems and about $22 billion for the structure, finishes and site work. These are estimates from one published analysis, not TSMC's own figures, and the money is spent over years across 12 facilities.
Which firms are on the permits?
By kind of work, the permits name 22 firms on electrical work, 16 on fire protection (sprinklers, alarms and underground fire lines), 8 on air (mechanical) and 7 on chemical tanks and gas systems. Two Taiwan firms, United Integrated Services (a general contractor on Fab 21) and Marketech, hold nearly 160 of the permits between them.
We read every City of Phoenix permit at TSMC's campus and its related sites: 815 permits on the campus, the first issued in March 2021 and the newest on Nov. 10, 2026. They name 50 firms. 35 hold systems permits (electrical, mechanical, plumbing, compressed gas, fire sprinkler and alarm, chemical tanks), 27 hold structure and site permits (structural, grading, civil, stormwater), and 12 hold both.
How do the ways into TSMC's Phoenix campus compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the permits | A call to the firm's main line, asking for the TSMC Phoenix team | Every supplier, distributor and sales rep | A conversation with a firm already working on the campus | Start with the firms with the newest permits |
Who should go after TSMC Phoenix?
| Electrical distributors and gear reps | The systems firms on the permits hold the electrical, power and controls work. |
|---|
| HVAC, piping, gas and water reps | Mechanical, plumbing, compressed gas and chemical tank permits name their firms. |
|---|
| Concrete, steel, site and rental reps | Structure, grading and civil permits name the site and building crews. |
|---|
What should you do next on TSMC Phoenix?
- Pick the firms whose permits match what you sell, and call their main lines this week.
- Ask for the team on the TSMC Arizona campus in north Phoenix.
Questions people ask about TSMC's Phoenix chip campus
How much is TSMC investing in Arizona?
$265 billion in total, after a $100 billion addition announced July 16, 2026 (City of Phoenix), for 12 facilities.
How much of a fab's cost is construction?
By Construction Physics' analysis, roughly 70-80% of a new fab's cost is the process tools; the building is the rest, and about two-thirds of the building's cost is its systems.
Who is building TSMC's Phoenix fabs?
City of Phoenix permits name 50 firms on the campus, from the large fab contractors to fire protection, electrical, site and concrete firms. The full list is above.
How we built this list
We read every City of Phoenix permit at 5088 W Innovation Cir and every permit naming TSMC (the campus, its water plant and lift station) on the city's public permit layer on Nov. 11, 2026: 815 permits on the campus. Permits for TSMC's supplier sites (Supplier Site A on Pinnacle Peak Rd and 19th Ave, and Site B at 555 W Pinnacle Peak Rd) were left out, and so were flow tests, sign permits and inspection or storage filings. Company names were merged across spellings; TSMC itself, 'OWNER' and 'TO BE BID' were left out. Main lines come from each firm's own website or the Arizona contractor registry; where none could be confirmed as a company line, the row says so. First published Nov. 12, 2026. We'll update this page as Phoenix issues new permits on the campus.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.