What's due Nov. 30 at Reagan UCLA?
UCLA's ads for the RRUMC 4th Floor Patient Care Reconfiguration ask for lump-sum subcontract bids on 16 trade packages, due at DPR Construction's Newport Beach office by 12:00 p.m. Pacific on Nov. 30, 2026. Bidding documents went out on or about Oct. 23 through UCLA's site and DPR's BuildingConnected project.
Electrical and low voltage, Bid Package #25, is the biggest at a $20 million UCLA estimate. Plumbing is $11.35 million and HVAC $10.45 million. The 17 packages add up to $74.65 million.
Every one of those ads says only previously prequalified bidders will be considered responsive. So this round is for subs DPR already cleared, and everyone else sells to them.
What are the 17 trade packages on the 4th floor?
Here they are by size, with UCLA's own estimate for each. The words in quotes are the ads' own package names.
- The big three: "Electrical & Low Voltage" $20,000,000, "Plumbing" $11,350,000, "HVAC" $10,450,000.
- Shell and interiors: "Demolition, Concrete, Framing and Drywall" $9,775,000 (due Dec. 3), "Casework / Millwork" $5,560,000.
- Protection and openings: "Wall Protection" $4,200,000, "Doors / Frames / Hardware" $2,480,000, "Glass & Glazing" $975,000.
- Floors and ceilings: "Resilient Flooring" $2,100,000, "Tile & Associated Waterproofing" $1,540,000, "Acoustical Ceilings" $1,400,000, "Resinous Coatings" $830,000.
- Fit-out: "Specialties" $1,750,000, "D/B Fire Protection" $965,000, "Install Owner Furnished Equipment" $735,000, "Window Treatments/ Overhead Curtains" $290,000, "Interior Signage" $250,000.
BP11 was changed by Addendum 3 to 2:00 p.m. on Dec. 3, 2026, and its bids go to UCLA Contracts Administration. Its mandatory conference and job walk were Nov. 6, so only firms that attended can bid it.
Why is UCLA rebuilding the floor?
The UC Regents approved the $169 million project in May 2024. Their item says the hospital had held occupancy between 107 and 112 percent of capacity for the past 18 months, and that the rebuild would add about 103 licensed beds, a 23 percent increase.
The 4th floor held the 74-bed Resnick Neuropsychiatric Hospital, which UCLA Health said in October 2025 is relocating to a new mental health campus. The ads describe the work as converting the west, east and north wings to medical and surgical space, adding a patient unit in the administrative wing and expanding into the administrative bridge.
The Regents' plan put contractor access on an exterior construction lift on the north side, along Charles E. Young Drive South, with one lane closed for about 20 months. UCLA's project page now estimates completion in March 2029.
How does a subcontractor get prequalified at UCLA?
UCLA posts subcontractor prequalifications on its Projects Currently Bidding page, in the Ad for PQ Sub section. On Nov. 10, 2026 that section held two for a UCLA Health tenant improvement at 5210 Pacific Concourse Drive, run by Clark Construction.
UCLA's Contract FAQ says that when prequalification comes before the bidding documents, a separate Prequalification Questionnaire is posted on the UCLA Online Planroom. The CM sets the questionnaire and its due date.
For email notice of new bids, UCLA asks firms to register as a vendor on its Consultants/Contractors Portal. Contractors who want UCLA jobs of $300,000 or less register through UCLA's Vendor Portal for its Rotating Bidders List.
Who is already working inside the hospital?
UCLA's 2026 bid summary sheets for three smaller jobs in the same building name the firms. For Room 1508F's imaging equipment replacement, MIK Construction was listed first at $1,538,888, with MA Electric for electrical and Rauland California for nurse call. UCLA lists that contract as awarded Oct. 28, 2026.
Two operating room lighting jobs went to bid this year. Harry H. Joh Construction was listed first on ORs 8, 9 and 10 at $130,910, with Juno Electrical System. MZN Construction was listed first on five other ORs at $627,633, with All Around Electric.
UCLA also plans a $21.7 million replacement of the whole hospital's nurse call system, now in working drawings with MJP Architects. No bid date is posted.
What else is UCLA bidding right now?
901 Levering Student Housing, a 19-story tower with about 1,130 undergraduate beds in Westwood, has 24 trade packages out through PCL Construction Services, the CM at risk on a $278.3 million contract. They're due Dec. 10, 2026 at 2:00 p.m.
The largest are cast-in-place concrete at $40.26 million, electrical and fire alarm at $30.09 million, and mechanical at $24.3 million. Only subs PCL prequalified who attend one of the mandatory walks, the last on Nov. 17, can bid. Mithun is the architect.
How do the ways into the Reagan UCLA job compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| DPR's Nov. 30 sub bids | Bid one of the 16 packages to DPR's Newport Beach office by 12:00 p.m. Pacific | Subcontractors DPR already prequalified | A lump-sum subcontract with DPR on the 4th floor | Only previously prequalified bidders count, so a new firm can't bid this round |
| Selling to the bidders | A call to the prequalified electrical, plumbing and HVAC subs pricing the floor now | Distributors, manufacturers' reps and suppliers | Your product in a sub's number before Nov. 30 | UCLA doesn't post the bidders where we could read them, so ask DPR who's pricing it |
| The next prequalification | UCLA's Projects Currently Bidding page, where sub prequalifications post under Ad for PQ Sub | Subs who want the next UCLA Health package | A place on a future bidders list | There's no date for the next one on this floor |
| 901 Levering's Dec. 10 bids | PCL's 24 packages on UCLA's new student housing tower | Subs PCL prequalified who attend a walk by Nov. 17 | A subcontract on a $278.3 million tower | The walks are mandatory and end Nov. 17 |
Who should go after the Reagan UCLA job, and who shouldn't?
| Electrical contractors and low voltage firms already prequalified | BP25 is the floor's biggest package at $20 million, due Nov. 30 at noon. |
|---|
| Electrical distributors, lighting, switchgear and nurse call reps | Price the subs bidding BP25 before Nov. 30, and watch the $21.7 million nurse call replacement planned for the whole hospital. |
|---|
| Plumbing, HVAC, drywall, casework and finish subs | Each has its own package on the floor, and 901 Levering carries the same trades at tower scale. |
|---|
| Subs who were never prequalified | This round isn't yours. Get on UCLA's next prequalification instead. |
|---|
What should you do next on the Reagan UCLA job?
- Open UCLA's Projects Currently Bidding page and read the ad for your package.
- If you're prequalified, get your bid to DPR's Newport Beach office before 12:00 p.m. Pacific on Nov. 30, 2026.
- If you sell to subs, call DPR's office and ask who's pricing your package, then call those subs this week.
- If you're not prequalified, register for UCLA's bid emails and watch for the next Ad for PQ Sub.
- Open the full list for the 901 Levering packages and the firms already working inside the hospital.
Questions people ask about the Reagan UCLA 4th floor
Who is building the Ronald Reagan UCLA Medical Center 4th floor project?
DPR Construction, A General Partnership. UCLA's bid ads say the University awarded DPR a CM at risk contract and that DPR bids and awards all the subcontractor packages. HGA is the architect.
How much is the Reagan UCLA 4th floor project?
UCLA's ads put the overall anticipated construction contract at $98,954,000. The UC Regents approved a $169 million project budget in May 2024, which includes $25 million for equipment and the design fees.
When are the Reagan UCLA trade bids due?
16 packages are due at DPR's Newport Beach office by 12:00 p.m. Pacific on Nov. 30, 2026. Demolition, concrete, framing and drywall (BP11) is due at UCLA Contracts Administration by 2:00 p.m. on Dec. 3, 2026, per Addendum 3.
How big is the electrical package?
Bid Package #25, Electrical & Low Voltage, has a UCLA estimated construction cost of $20,000,000, the largest of the 17 packages. Plumbing is next at $11,350,000 and HVAC at $10,450,000.
Can any subcontractor bid?
No. Every Nov. 30 ad says only previously prequalified bidders will be considered responsive. BP11 also required its Nov. 6 mandatory conference and job walk.
How does a subcontractor get prequalified at UCLA?
UCLA posts subcontractor prequalifications on its Projects Currently Bidding page under Ad for PQ Sub, and its Contract FAQ says a Prequalification Questionnaire is posted on the UCLA Online Planroom. The CM sets the questionnaire and due date. To get UCLA's bid emails, register as a vendor on its Consultants/Contractors Portal.
How do suppliers get on the Reagan UCLA job?
Sell to the prequalified subs pricing your package before Nov. 30. UCLA's FAQ says plan holders are listed on the UCLA Online Planroom, and DPR's Newport Beach office takes the bids. For a product, UCLA's FAQ points vendors to its Vendor Information Form.
Why is UCLA rebuilding the 4th floor?
The Regents' May 2024 item says the hospital had run between 107 and 112 percent of capacity for 18 months, with patients boarding while they waited for beds. The 4th floor held the Resnick Neuropsychiatric Hospital, which UCLA Health said is relocating to a new mental health campus.
When will the new beds open?
UCLA's project page estimates completion in March 2029. The Regents' 2024 plan had said October 2027.
What other UCLA projects are bidding now?
901 Levering Student Housing, a 19-story tower with about 1,130 undergraduate beds, has 24 trade packages due Dec. 10, 2026 through PCL Construction Services, the CM at risk, on a $278.3 million contract. Only PCL-prequalified subs who attend a mandatory walk by Nov. 17 can bid.
How we built this list
We read UCLA Capital Programs' Projects Currently Bidding page and all 17 advertisements for bids on the RRUMC 4th Floor Patient Care Reconfiguration, including Addendum 3 for BP11, the two 901 Levering advertisements, UCLA's project pages for the floor, the nurse call replacement and 901 Levering, its Contracts Awarded and Bid Results pages and their bid summary sheets, the Contract FAQ, the UC Regents' May 2024 approval, UCLA Health's October 2025 release, and Daily Bruin coverage. ATI's own permit and bid records hold nothing for this job, so every row here comes from UCLA's own bid office. A row is on the list only if a UCLA record ties it to the hospital or to an open UCLA trade package. We left every person's name, phone and email off the list. The floor's size differs by record: 67,400 gross square feet in the ads, 67,464 in the Regents' item, 64,464 on the project page. First published Nov. 10, 2026. We'll update this page when UCLA posts an addendum, a bid result or an award for these packages.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 10, 2026- UCLA Capital Programs, Projects Currently Bidding
- UCLA, Advertisement for Bids, RRUMC 4th Floor, Bid Package #25 Electrical & Low Voltage
- UCLA, Advertisement for Bids, RRUMC 4th Floor, Bid Package #23 Plumbing
- UCLA, Advertisement for Bids, RRUMC 4th Floor, Bid Package #24 HVAC
- UCLA, Advertisement for Bids, RRUMC 4th Floor, BP11, Modified by Addendum 3
- UCLA Capital Programs, RRUMC 4th Floor Patient Care Reconfiguration
- UCLA Capital Programs, RRUMC Nurse Call Replacement
- UCLA Capital Programs, 901 Levering Student Housing
- UCLA, Advertisement for Bids, 901 Levering Student Housing, Multiple Bid Packages
- UCLA, Advertisement for Bids, 901 Levering, BP09 Cast in Place Concrete
- UCLA Capital Programs, Contracts Awarded Last 6 Months
- UCLA Capital Programs, Bid Results
- UCLA Capital Programs, Contract FAQ
- UCLA Capital Programs, Notification of Bidding Opportunities
- UC Regents, Item F1D, May 15, 2024
- Daily Bruin, UC Regents approve acute care bed expansion, May 16, 2024
- Daily Bruin, overcrowding protest at UCLA's hospital, May 6, 2026
- DPR Construction, Newport Beach office
- PCL Construction, Los Angeles office